55 PINE ST.PDFiiiiiiiiiiiiii
12812
55 PINE ST
ADDRESS:
TAX ACCOUNTIPARCEL NUMB
BUILDING PERMIT (NEW STRU,
COVENANTS (RECORDED) FOR:
CRITICAL AREAS: DETERMINATION: E] Conditional Waiver [j Study Required [—] Waiver
DISCRETIONARY PERMIT #'S:
DRAINAGE PLAN DATED: aw--
PARKING AGREEMENTS DATED:
EASEMENT(S) RECORDED FOR:
PERMITS
PLANNING DATA CHECKLIST DATED:
SCALED PLOT PLAN DATED:
SEWER LID FEE $: LID #:
SHORT PLAT FILE: LOT: BLOCK:
SIDE SEWER AS BUILT DATED:
SIDE SEWER PERMIT(S) #:
SOILS REPORT DATED:
STREET USE / ENCROACHMENT PERMIT #:
WATER METER TAP CARD DATED:
LATEMP\DSrs\Fonns\Street File Checklist.doc
TURA ASSOCIATES, In JUN 2 8 MI
PET
T(UL
Consultants in Geotechnical Engineering, GeologyC-1) 2006
and
Environmental Ear(h Sciences BY
June 8, 2006
Project No. T4893
Mr. Ross Woods
Point Edwards, LLC
2901 Alaskan Way, Suite 107
Seattle, Washington 98121
Subject: Grading Review
Buildings 6 and 7
Point Edwards Condominiums
Edmonds, Washington
References: 1. Preliminary Gcotechnical Report, UNOCAL Site, Project No. T4893,
prepared by Terra Associates, Inc., dated November 21, 2001
2. Steep Slope Hazard Review, Point Edwards Condominiums (UNOCAL Site),
Project No. T4893, prepared by'ren-a Associates, Inc., dated December 13, 2002
3. Geologically Hazardous Areas Review, Point Edwards Condominiums (UNOCAL Site),
ProjectNo. T4893, prepared by Terra Associates, Inc., dated January 20, 2003
Dear Mr. Woods:
As requested, %vi�,r�ev i ewed a plan sheet by Triad Associates titled Building 617 and Anienity Building Fine
Grading and Excavation Cross Seclions dated June 1, 2006. 'Me plans indicate that excavations to accommodate
a portion of the daylight lower building levels in the northern portion of Building 7 and the southern portion of
Building 6 will extend from the western side of the buildings to the existing steep slope at approximately Elev.
I 10.0. This grading will lower the elevation of the top of the slope by about four feet. The western side of both
buildings will be setback approximately 30 to 35 feet from the modified top -of -slope.
Based on our review, it is our opinion that the proposed grading at this location will not adversely impact stability
of the steep slope provided that the recommendations for erosion prevention and site drainage presented in the
referenced documents are followed. The planned grading will enhance the existing stability of the slope due to
unloading resulting from the soil removal and will result in improved surface drainage at the top of the slope by
directing surface runoff away from the slope crest to the yard drainage system.
12525 Willows Road, Suite 101, Kirkland, Washington 98034
Phone (425) 821-7777 * Fax (42-5) 821-4334 Imam
STRI:tT FILE
Mr. Ross Woods
June 8,2006
Afteriialive Keyway Drainage
The plan indicates a fill emban1cment having a maximum thickness of about six feet will be constructed in the
yard area west of the southern, portion of Building 7. Much of the embankment rill will be constructed over
existing grades of about 20 percent. As discussed in Section 5.2 and shown on Figure 3 (General Slope Fill
Detail) of our referenced preliminary geotechnical report, embankment fills placed on slopes exceeding a grade of
20 percent must be keyed and benched into competent native soils, and should be constructed with a toe drain in the
excavation for the keyway cut at the toe of the fill slope.
The keyway drain shown on Figure 3 of our referenced preliminary report consists of a six-inch diameter
perforated PVC pipe that is enveloped in washed drainage aggregate. Typically, the keyway drain is connected to
a fightline pipe that daylights at an approved point of controlled discharge, such as the site storm sewer system.
However, due to site elevations, a keyway drain constructed as shown on this figure cannot be connected to the
site storm drainage system.
Considering this, and because we do not expect that the keyway drain will collect or discharge significant
volumes of water, it is our opinion that adequate keyway drainage can be provided by constructing several ballast -
rock drainage windows in the toe of the fill embankment in lieu of using a continuous drain pipe. The rock
drainage windows will provide adequate hydrostatic relief should any sub -fill seepage find its way to the toe of
the fill embankment. A detail showing this alternative drainage option is attached as Figure 1. The need for
additional or alternate sub -fill drainage should be based on field conditions observed at (he time of construction.
Lightweight rill
The plans show the southeastern portion of the betow-grade parking garage for Building 7 will underlie up to
about ten feet of landscape fill. We understand that lightweight polystyrene foam will be used for much of the fill
over the parking garage ceiling slab. The planned grading indicates two rockeries with maximum heights of
about seven to eight feet will be constructed against and supported by the polystyrene foam in the northern
portion of the fill area.
In our opinion, rockeries built in accordance with Associated Rockery Contractors (ARC) Standard Rockery
Construction Guidelines may be constructed on and against the polystyrene foam material. We recommend
placing at least six inches of a crushed rock leveling course between the base rocks of the rockery and the
polystyrene foam subgrade.
Conceptual information provided by Mr. Jeff Brink of DO Engineers indicates the product to be used for the
lightweight fill is Type IX Insulfbam R-TECH. However, our review of material properties for the Insulfbam
products and analysis indicate that Type I Insulfbarn R-TECH is an acceptable alternative for the proposed
application.
Project No. T-4893
Page No. 2
Mr. Ross Woods
June 9, 2006
We trust the information presented is sufficient for your current needs. If you have any questions or require
additional information, please call.
Sincerely yours,
TERRA ASSOCIATE, S, INC.
'EM.-e
)etail
Project No. TA893
Page No. 3
A
ORIGINAL GROUND SURFACE
(PREPARED PER GEOTECHNICAL REPORT)
STRUCTURAL FILL
(SEE NOTE 1)
GEOTEXTILE SEPARATION LAYER
(MIRAFI 500X OR EQUAL)
BALLAST ROCK DRAINAGE
WINDOW (SEE NOTE 2)
—y-
1.5'
rr!�'
C' Q0 0m,
00 q'000XV '0 c�'00 0 C>oe/
, -0 �:eto--,jn' -- o6n - o
0 �'Qy�o
C�
0Q),
2' (M I \N.)\\
KEYWAY EXCAVATION
6' (MIN.) STRUCTURAL FILL
(SEE NOTE 1)
NOT TO SCALE
NOTES:
STRUCTURAL FILL SHALL BE COMPACTED TO A MINIMUM OF 95% OF ASTM D 698 MAXIMUM
DRY DENSITY VALUE.
2) 2-INCH BALLAST ROCK DRAINAGE WINDOW; 1.6 THICK, 6 WIDE, CONSTRUCTED 39 (MAX.)
ON CENTER ALONG TOE OF EMBANKMENT FILL. SPACING OF GRAVEL WINDOWS MAY BE
ADJUSTED BASED ON CONDITIONS OBSERVED DURING CONSTRUCTION.
Terra
Associates, Inc.
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
ALTERNATIVE KEYWAY DRAIN DETAIL
POINT EDWARDS CONDOMINIUMS
BUILDINGS 6 & 7
EDMONDS, WASHINGTON
Proj. No. T4893 I Date JUNE 2006 1 Figure 1
DCI-ENGINEERS
D'AMATO CONVERSANO INC.
1. Mark DAmato - Guy A. Conversano
Elizabeth A. fensen Roger L. fleeringa - Mark D. Aden
Harr), fones It Troy E. Bean - Tom C Xia, A.D.
Richard L. Hemmen - Grant C Buckingham
Point Edwards Site Retaining Walls
Edmonds, Washington
Structural Calculations
For
Permit
Prepared For:
Weber + Thompson P.L.L.C.
September 14, 2006
DC1 Job 4 06-11-009
RIE'SU13
SEP 19 2006
8U11)ING DEPARTIWEMT
MY OF EDA40t4OS
10900 NE 4TH STREET, SUITE 1200 - BELLEVUE, WA 98004 - PHONE (42�TRFETAfk�7.8986
BELLEVUE SPOKANE EVERETT PORTLAND SAN DIEGO
Point Edwards Site Retaining Walls
September 14, 2006
DO Job # 06-11-009
0 Amenity #2 Retaining Walls
0
=,---DC1-ENGINEERS.
D 'AMATO CO NVERSANO -1 NC. PROJECT NO: 06-11-031 SHEET NO:
PROJECT: Point Edwards Amenity #2 DATE: 8/24/06
SUBJECT: 8'-0 Retaining Wall @ Pool Area BY: BSB
Seismic Pressure = 170.0 p0
Design Lateral Pressure = 35 pef
Surcharge Pressure 75.0 psi
SOIL SURCHARGE
00assive Lateral Pressure 300 pci
ase Friction 0.40
pnit We-ghl of S�l 120 pCf
Tnbulary ter,gth of Wall 10
Concrete Strength 4000
Column DL 0.00 k
Column LL 0 00 k
105
Wt of Sod above Heel 6.
I OL
Wt at Wall
Wt. of Foof..g
4k y N-j
r
e. 4
0
rki
750.0 pIt IZ Iff 6.9 367.5 pff 75JO pit 170 pit
&W
Wall ok footing loe ok Footing Heel
d = 9.0" d = MAY" d = 2D.010
V� = 2.08 k Vv = 3.36 k V,, = TOM k
OVc = 10.25 k +V� = 22-77 k OVc = 22.77 k
M� = 8,85 fl-k M, = 1.68 fl-k M,, = 30.67 H-k
FS Sliding ok FS Overturning ok
Sliding Resistance 5.6 k Z19 RM = 50.7 ff-k 3.75
Sliding Force 26k OTM = 13.5 tf-k
Soillteoring ok
X = - 2L7 Lt-k = 2.91'
9.9 k
e = 1.09' < b/6 = 1.33'
If e < b/6. Then If e > b/6, Then...
SoflBearing = P M 2.24 kit Soil Bearing 2 0.5.P L
Stress Left A S Stress 3 b e
Soil Bearing = P 10 2 9.9 k I jg 2.26 ksf
- = = OM&
Stress Right A S 3 4.0, IJW
P = D -L = 9.9 k A = &0 st vridth 8.73'
M = Pe = I 0S fi-k S = 10.7 ftA3
0
Load Factors
D 1.2
L : .0
E .0
H 0.07
WAU
Wall Concrete (fc) =
4 ksi
Wall Reinfofc4ng (ty) =
60 k�
Cover =
2,n
Bar Size =
Bar Area =
0.31
Bar Spacing =
2 �.
AS provided = 031 A2/ft.
Bar Diameter =
0.625
d =
969
a12 =
023
As Requfred = 0 208 inA2/f! OK
As Minimum =
"TOE
Wall Concrete (fc)
4 K.
Wall Reinforcing (fy)
60 ksi
Cover
3 in.
Bar Size
Bar Area
031
Bar Spacing
181
As Provided =
0.21 inA2/fl.
Bar Diameter =
0.625
d =
20.69
a/2 =
0.15
As Required =
0.0 18 inA21111 CK
As Minimum =
HEEI
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
6
Bar Area =
0.44
Bar Spacing =
I-n-
As Provided =
0.44 inA2/ff.
Bar Diameter =
0.75
d =
20.63
a/2 =
0-32
As Required =
0.336 inA2/fl OK
As Minimum =
=�i--DCLENGINEERS
;!=;- D'AMATO CONVERSANO INC.
1PROJECT: Point Edwards Amenity #2
SUBJECT: 8'-0 Retaining Wall @ Pool Area
Seisrnic, Pressure = 170.0 psf
Design Lateral Pressure = 35 pcf
= 75 0 sf
PROJECT NO: 06-11-031 SHEET 1,10i
DATE: 8/24106
BY: BSB
�urc rge ressure
ive Lateral Pressure = 300 pcf
SOIL
ase Friction = 0.40
nit Weight of Sail z 120 pcf
riloutary Length of Wall
Concrete Strength 4000 psi
Column OL 0 00 It
Column 1.1. 0.00 k
W:. of Sosl above Heel 6 11
AkODL
!�;�.Wrnn
W.0fWall 4,
Wt of Footing 24k
#24 'r
SURCHARGE
d 10.5,
75DD plf
1.0,
1.9
6.9
367-5 plf 75.Oplf 170 pit
8.W
Wall ok
Footing Toe
ok
Footing Heel
d ?.0"
d = 20.0"
d = 20.0"
V,, = 3.47 k
Vv
= 4A2 k
Vu = 7.67 k
4vc = 10.25 k
4vc
= 22.77 k
4Vc = 22.77 k
mu = 11.87 fl-k
M,,
= 221 ft-k
Mu = 23JDO ff-k
FS Sliding ok
FS Overturning
ok
Sliding Re-kistance
4-5 k
RM
38.0 ff-k
Sliding Force
4.9 k
0.91
OTM
.2 ft-k
Sail Bearing ok
k
X 2.23
Oe = 1.77 > b/6 = 1-33
'I e < b/6, Then...
It e > b/6, Then...
Soil Bearing P M
2.87 list
Soil Bearing -
2
Stress Left A S
Stress
3 b e
[ =P
Sail Bearing P M
-0.40 list
-
2 9.9, k
2.95 W
Stress Right A S
4
3 .0 1.77
P = D+L = 9.9 k
A = 8.0 sf
v,idth 6.70r
M = Pe = 17.4 ft-k
s = 10.7 JtA3
0
7 Load Factors
D 0.9
L 0.0
E 1�0
H 1.6
1
WAL.I,
Wall Concrete (fc) =
41ks;
Wall Reinforcing (ty) =
60 ksi
Cover =
Bar Size =
Bar Area =
0.31
Bar Spacing z
- 1.
As Provided = 0.31 snA2/ft.
Bar Diameter =
0625
d =
9.69
a12 =
0.23
As Required = 0.279 042/ft 0�
As Minimum =
TOT
Wall Conciete (fc) =
4 k�
Wall Reinforcing (fy) =
60 ku
Cover =
3 in.
Bar Size =
-
Bar Area =
031
Bar Spacing =
I
As Provided =
0.21 inA2/fj.
Bar Diameter =
0.625
d =
2D.69
a12 =
0.15
As Required =
0.024 inA2/ff 0 K
As Minimum =
I-IEEL
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (ty) =
60 ksi
cover =
3 in.
Bar Size =
A
Bar Area =
0."
Bar Spacing =
12 in.
As Provided =
0." inA2/ff.
Bar Diameter =
0.75
d =
20.63
ar2 =
0.32
As Required =
0-252 inA2/fj OK
As Minimum =
�M=DCI-ENGINEEKS
� D'AMATO CONVERSANO I NC-
IPROJECT: Point Edwards Amenity #2
SUBJECT: 8'-0 Retaining Wall @ Pool Area
Seisrnic Pressure = 170.0 psi
Design Lateral Pressure = 35 pcf
ha Pr = 75 0 nsf
PROJECT NO: 06-11-031 SHEET NO:
DATE 8124106
BY: BSO
urc rge essure, SOIL SURCHARGE
eassive, Lateral Pressure = 300 pc:
= 040
ase Friction
120 pc
U61 Weight of Soil
Tributary Length of Wall 10
Concrete Sfreriglh 4DOO psi
0.00 k
Column DL
-;t
0.00 It
Column U. �w
Wt. of Soil aboye Heel 611� AC fr,oMm Ca�kymn'.,,
Wt. of Wall k
k
Wt. of Footing 2. J1,
Zr-
rj
f
--,150,0PI
EO
750D pit 1.01 Iff 6Z 367.5 pit 75.0 pit 170 pit
&W
won ok Footing Toe ok Footing Heel
d 9.0- d = 20.0" d = 20.0"
Vu = 2.28 k Vu = 3.34 k V,, = 5.11 k
#Vc = 10.25 k 4Vc = 22.77 k +V,, = 22.77 k
m. = 7.88 ff-k Mu = 1.67 fl-k M,, = 15.34 ft-k
FS Sidling ok FS Overturning ok
Sfiding Resistance 3.3 k - 1.03 RM = 25.3 ff-k 1.90
Slicling Force 3.2 k OTM = 133 tf-k -
SoilBearing ok
k
X 2.n
D7 < b/6 133
4*, . <=b"6. Then... If e > b/6, Then
Soil Bearing 2 P
So' Bearing = 2.22 list =1 I
Stress Left A S --- Stress 3 _5.b e
Soil Beating . -L - -t = = 0.24 ksf 2 9,k I.,
Siren Right A S 3
P = D-L = 9.9k A = 8-0sf yvidlh 8.75,
M = Pe = 10.6 ff-k s = 10.7 ftA3
L;2323d--FacR-tom-r-s-j
l D 0.6
L 0-,..
6 0."
H 1.0
u
WALL
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (fy) =
60 kii
Cover =
2.n.
Bar Size
Bar Area
031
Bar Spac4ng
; 2 ,.
As Provided =
0.31 snA2/fi.
Bar Diameter =
0625
d =
969
a12 =
0.23
As Required =
0. 1 a5 snA2/ff 0<
As Minimum =
Wall Concrete (rc)
4 "
Wall Reinforcing (fy)
60 ksi
Cover
3 in.
Bar Size
Bar Area
0-31
Bar Spacing
ls;ri.
As Provided =
0.21 inA2/ft.
Bar Diameter =
0.625
d =
20.69
a/2 =
0.15
As Required =
0.018 inA2/fl OK
As Minimum =
I -[EEL
Wall Concrete (fc) =
4 U
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0.44
Bar Spacing =
12 in.
As Provided =
0.44 inA2/tt.
Bar Diameter =
0.75
d =
20.63
a12 =
0.32
As Required =
0-16BinA2/ft OK
As Minimum =
=---DC1-ENG1NEERS
Ma D'AMATO CONVERSANO INC.
PROJECT: Point Edwards Amenity #2
SUBJECT: 8'-0 Retaining Wall @ Pool Area
Seismic Pressuie = 170.0 pet
Design Lateral Pressuire = 35 pet
= 75.0 pst
PROJECT NO: 06-11-031 SHEET NO:
DATE: 9124/06
BY: BSB
Surc arge ressure
�jse Friction = 0.40
4"assi�e Lateral pressure = 300 pet
SOIL
U"nst We,ght of Sol = 120 pet
3
Tributary Length of Wall = 1.0'
Concrete Strength = 4000 psi
Column DL = 0 00 k
Column LL 0.00 k
Wt. of Soil above Heel 6.1 1,
Wt. of Wall 1.4 k
rx
Wt. of Footing 2.4 k
4,
rZ. �,-
SURCHARGE
10.5,
40
r
Za
750.0 pit
1.0, 1.9 6Z
367.5pil 75D pit 170 pit
8.W
Wall ok
Footing Toe ok
Footing Heel
d 9.01,
d = 2D.0-
d - 20ff
V, = 2.50 k
Vu = 3-54 k
V,,' = 8.52 k
4Vc = 10.25 k
+V, = 22.77 k
+Vc = 22-77 k
Mv = 8.84 ft-k
Mv = 1.77 ft-k
Mu = 25-56 ff-k
FS Sliding ok
FS Overturning
ok
Sliding Resistance =
-
4,8 k 1.40 RM
42.2 ft-k 2-111
Sliding Force =
3.5 k - DIM
14.8 ff-k
SoilBearing ok
21.1 �1-k
X =- = 2-79
,." k
1.2Z < b/6 IW
*I,
. <=b/6, Then...
If e > b/6. Then...
Soil Bearing =
2.36 ksf sea Becnng
2 P L
Stress Left A S
Stress,
3 -5-b e
=/I
SoilBearing P M
=
0.11 kst
2 99 k
a 2-37 ksf
Stress Right A S
3 4 a _ 1.27]
p = D-L = 9.9 k
A = 8.0 Sf �idlh 834'
M = Pe = 12D fil-k
S = 10.7 ftA3
0
WAI,L
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (ty) =
60 kSi
Cover =
Bar Size =
Bar Afea -
0-31
Bar Spacing =
As Provided = 0.31 nA2/11.
Bar Diameter =
0.625
d =
9.69
a/2 =
0.23
As Required =
As Minimum =
TOE
Wall Concrete ft) =
4 X9
Wall Reinforcing (fy) =
60 U
Cover =
3 in.
Bar Size =
Bar Area =
0-31
Bar Spacing =
1 E::...
As Provided =
0-21 inA2/h.
Bar Diameter =
0.625
d =
20.69
a/2 =
0.15
As Required =
0.0 19 inA2/ft OK
As Minimum =
HEEL
Wall Concrete (
Wall Reinforcing (ty) =
60 ksi
Cover =
3 in.
Bar Size =
4
Bar Area =
0.44
Bar Spacing =
� 2 iri.
As Provided =
0-44 inA2/ff.
Bar Diameter =
0.75
d =
20.63
a/2 =
032
As Required =
0-290 inA21ff OK
As Minimum =
�-�DCI-ENGINEERS
�-%= D'AMATO CONVERSANO INC.
IPROJECT: Point Edwards Amenity #2
SUBJECT: 1 V-0 Retaining Wall @ Pool Area
Seismic Pressure = 170.0 PSI
Design Lateral Pressure = 35 Fict
Surcha-e Pressuire = 75.0 pst
PROJECT NOi 06-11-031 SHEET NO:
DATE: 8124106
BY: BSB
as. Friction
40a,,im,e Lateral Pressure
= 300 Pct
z 040
J,'
SOIL
,n,f Weight of Sail
= 120 pcf
Tributary Length of Wall
Concrete Strength
- 1.0
4000 p,
Column Of.
0 00 k
Column U.
O.DO k
.et
W1. of Sod above Heel
= 9.2 k
AC
W1. of Wall
= 2.4 k
r,
Wt. of Footing
= 4.5 k
7V
SURCHARGE
14.2S
v A
975.0 plf
117 , 1.33' 6.67'
498B pit 75.0 pit 170 p
11.00,
Wall ok
Feeling Toe ok
Footing Heel
d = 110"
d = 29.0"
d = 29.0"
Vu = 2.82 k
Vu = 8.69 k
Vu = 16.49 k
+VC = 14.75 k
f,V,, = 33jD2 k
#Vc = 33.01 k
M,, = 16.2D ft-k
M� = 13,03 ft-k
M, = 55.00 fl-k
FS Sliding . ok
FS Overturning
ok
Sliding Resistance
93k
RM
125.1 ft-k
Sliding Force
2.66
3.5 k
OTM
---- i- = 5.03
4.9 ft-k
Soil Bearing ok
79.4 ff-k
x 4.17Z
k
O-W < b/iS 1,83
If . <=b/6. Them..
Soil Bearing = _L , = = 1.93 ksf
Stress Left A S
Sell Bearing =_L . M = = 1.00 ksf
Stress Right A S
P = D + L = 16.1 k A = 1110$f
M = Pe = 9.3 ff-k S = 20.2 ftA3
0
It e > b/6. Then...
Soil Bearing 2 P L
Stress 3 0.5.b e
2 _ 6.1 k 10- 2.19 kst
5.5, 0.r
3 _,B
�idth 14.76
Load Factors
D 1.2
L 1 -0
E 1.0
H 0.07
WALL
Wall Concrete (fc)
4 ksi
Wall Reinforcing (ty)
60 k�i
Cover
2 in
Bar Scze
Bar Area
044
Bar Spacing z
. 2 r
As provided z 0.44 in�2/11.
Bar Diameter =
0.75
d =
13.59
a61`2 z
0-32
As Reqtred = 0.271 W21h 0<
As Minimiarn =
ICE
Wall Concrete (rc)
4 U
Wall Reinforcing (Ify)
60 ksi
C47VW
3 in.
Bar Size
Bair Area
0.31
Bar S
As provided =
0.21 inA21fi.
Bar Diameter =
0.625
d =
29.69
ar2 =
0.15
A� Requtired =
OD98 ilnAVII OK
As Minimum =
HEEL
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
--
Bar Area =
0.44
Bar SpacuV =
12
As provided =
0.44 iriA2,11.
Bar Dometer =
0.75
d =
29.63
a12 =
0.32
As Required =
0.417 jnA2/tf CK
As Minimum =
D*AMATO CONVERSANO INC
1PROJECT: Point Edwards Amenity #2
SUBJECT: 11'-0 Retaining Wall @ Pool Area
Seismic Pressure = 170.0 psi
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 75 0 psi
Passive Lateral Pressure 300 PCf A.,
PROJECT NO: 06-11-031 SHEET NO:
DATE: 8/24/06
BY: BSB
SOIL SURCHARGE
VWa -I,on 040
U
U.=
i,
hi of Sail A
120 pcf
ev, -i:�j
Tributary Length of Wall 10'
Concrete Strength 4WO psi
Column DL 0.00 k
Column U. 0.00 k
V. 14.25
Wt. of 561 above Heel 9.2 k Ac �om c6fumA
Wt. of Wall 2.4 k
Wt. of Footg
4.5 k
'10
E-Q
975D 0 3.0, 1.33' 6.67 498.8 plf 75.0 plf 170 r
I 1.W
Wall ok Footing Toe ok Footing Heel
d 13.0" d = 29.0" d = 29.0"
V,, = 5.66 k Vv = 13.01 k V,, = 12-37 k
#Vc = 14.75 k 4Vc = 33.02 k +V,, = 33.01 k
M. = 25." Il-k M, = 19-52ft-k Mv = 41.�5ff-k
FS Slicling ok FS Overturning ok
Sliding Resistance 7A k 0.91 RM = 93.9 fl-k = 712
Sliding Force & I k OTM = 443 ff-k
Soil Bearing ok
X =- 60.0 ff-k = 3,77
16.1 k
Oe = 1.79 < b/6 = IS3
. < b/6, Then...
Sail Bearing P M 2.89 U
Stress Left A S
Soil Bearing P M OJD4 U
Stress Right A S
P = D-L = 16.1 k A = 11.0 Sf
M = Pe = 25-7 tl-k S = 20.2 ffA3
0
It a � b16, Then...
Sol Bearing = 2r�_P L
Stress 3 0_5.b e
2 6 1 k I'Cr 2B9 ksf
3 5.5 1 761
width 11.16'
Load Factors
D O�9
L 0.0
E I -'
H 1.6
%%'A-LL
Wall Concrete (fc) =
4 ks;
Wall Reinforcing (ty) =
60 ks.
Cover =
Bar Size =
Bar Area =
0.44
Bar Spacing =
:: -
As Provided = 0
44 inA2/H.
Bar Diameter =
075
d
13+59
a/2
032
As Required 0 426 inA2/h 01
As Minimum
TOE
Wall Concrete (fc)
4 ksi
Wall Reinforcing (fy)
60 k�
Cover
3 in.
Bar Size
Bar Area
0.31
Bar Spacing
1 J� �fj.
As Provided =
0-21 inA2/ft,
Bar Diameter =
0.625
d =
29.69
a/2 =
0.15
As Required =
0. 147 inA2/ft OK
As Minimum =
FEEEL
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
6
Bar Area =
0.44
Bar Spacing =
12 ir.
As Provided =
0." inA2/ff.
Bar Diameter =
0.75
d =
29.63
a12 =
0.32
As Required =
0313 inA2/fI �L,
As Minimum =
D'AMATO CONVERSANO INC. PROJECT NO 06-11-031 SHEET NO:
7LE2d �F2acEf�
PROJECT: Point Edwards Amenity #2 DATE: 8/24106
06
D 0,S
SUBJECT: 11 '-0 Retaining Wall @ Pool Area BY: BSB
L -, M��
Seisrnic Pressure a 170.0 psf
H 1.0
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 75.0 psi
SOIL SURCHARGE
Possi�e 010,01P,essute = 300 pcf
ase Friction = 040
WALL
U nit We.ght of Soil 120 P�f
Tirbutory Length of wall 1.0
Wall Concrete (fc) =
Wall Reinforcing (ty) =
4 ksi
60 i�
Concrete Strength 4000 psi
Cover =
2,n
Column DL 0 00 k
Bar Size
Column U. 0.00 k
Bar Area =
044
Bar Spacing =
2.
WI of Soil above tie -el 9.2 k Ac liorn. 0, urm�j � 'I, , ,
I 1 -1. - .
R, IN
As Provided = 0
44.-�2/1`1.
Klk ;a T, 7
Wt of Wall 2 4 k 4, . .�. 41
Bar Diameter z
075
4 rt
Wt of Fooling -51,
d=
13-59
'4;
ar-) =
032
As Required = 0281
m42/tf
SK
150.001.4
As Minimum
x
7
10
Wall Concrete (fc)
4
Wall Reinforcing (fy)
60 ksi
975.0 pit 3.0' 1.33' 6.67 498.8 pff 75D pit 170 pit
in.
Cover =
3
I I.W
Bar Size =
Wall ok Fooling Toe ok Footing Heel
Bar Area =
0.31
d 13.0'- d = 29.0" d = 29.(r
Bar Spacing =
! � sr...
V,, = 3.68 k V,, = 9.60 k V,, = 8.25 k
As Provided =
021 inA2/fi.
#V� = 14.75 k OVi, = 33.02 k +Vc = 33.01 k
Bar Diameter =
0.625
d=
29.69
Mv = 16.74 fi-k M,, = 14.40 ft-k Mv = 27S) ft-k
a/2 =
0.15
As Required =
0.10BinA2/ff
CK
FS Sliding ok FS Overturning ok
As Minimum =
Sliding Resistance 5.4 k RM = 62-6 fl-k
. HEE
2.16
Sliding Force 5.2 k OTM = 29D ft-k
Wall Concrete (fc) =
4 U
Wall Reinforcing (fy) =
60 ksi
SoilBearing ok
Cover =
3 in.
Bar Size =
4
7L3 fi-k
Bar Area =
0.44
X = - = 4.67'
16.ik
Bar Spacing =
11 i-�.
As Provided =
0.44 in^21fl.
= OW < b/6 = ).83'
Bar Diameter =
0.75
#e
d =
29.63
if e < b/6. Then... If e > b/6, Then...
a/2 =
0-32
Sail Bearing P M SalBecring 2 P
As Required =
0.2D9 inA2/fj
CK
. 2.13 ksf
Stress Leh A S - Stress 3 b e
I
As Minimum =
Sail Bearing P M 2 6.1 k I IT
=
- _ - = = 0.80 ksf L_ 2_30 U
Stress Right A S 3 5_5 OW
P = D-L = 16.1 k A = IWO width 14,W
M = Pe z 13-4 ff-k S = 20.2 fjA3
0
4�-C= L)UI-hN (-,,IN LLK15 PROJECT NO: 06-11-031- FSHEETNO:
0=- D*AMATO CONVERSANO INC.
PROJECT: Point Edwards Amenity #2 DATE: 8f24/06
SUBJECT: 1 V-0 Retaining Wall @ Pool Area BY: BSB
Seisr'nic Pressure = 170.0 pill
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 75.0 pill
SOIL SURCHARGE
assive La ressure = 300 pcf
lop P
C,,e F,,Cf,,:al
= 0.40
U u
hit Weight of Sod - 120 pcl
TribularY Length of Wall
Concrete Strength 4000 psi
Colurrvi, DL 0.00 k
Column I.I. �W"
0.00 k
illi:. iA
Z 14.25
Wi of Soil above Heel 9-2 k Ac dt�d D e-
wt of Wall 2 4: V.1
7v
Wt. of Foofing 4,5
i X-r,
-7
EQ
975.0 plf 3.0' 1.33' 6.67 498.8 plf 75.0 pit 170 plf
I I.W
Wall ok Footing Toe ok Footing Heel
d 1"*' d = 29.0" d = 29.0"
V,, = 3.99 k Vu = 10.20 k Vu = 13.74 k
+Vc = 14.75 k +Vc = 33.02 k +Vc = 33.01 k
M,, = 18.49 fl-k M,, = 15.30 ft-k Mu = 45.83 ff-k
FS Sliding ok FS Overturning ok
Sliding Resistance 8.0 k RM = 1043fl-k
1.42 - 3.29
Sliding Force 5.6 k OTM = 31.7 fi-k
Soil Bearing ok
72.6 tt-k X
16.) k
#e 11-W < b/6 = IW
0 e<b &Then... If e b/6, Then...
Scil Bearing P . M 2-27 ksf Soil Bearing 2[__O_ P L
Stress Left A S Stress 3 .5 to e
2 1& 239 ksf
Sail Bearing P M 0.67 ksf
Stress Wight -S 5_5 I.W
A 3
P = D-L = 16.1 k A = ]I-0sf vidth 13.50r
M = Pe = 16.1 ft-k s = 20.2 hA3
WAU,
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (ty) =
60 ksi
Cover =
'n
Bar Size =
Bar Area =
044
Bar Spacing =
j* -,
As Provided =
0 44 rn�2/111
Bar Diameter =
075
d =
13-59
a/2 =
0.32
As Required =
0.310.nA2/ft
As Minimum =
Wall Concrete (fc) =
4 kit
Wall Reinforcing (ty) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0-31
Bar Spacing =
, E;.n.
As Provided =
0.21 in�2/ff.
Bar Diameter =
0.625
d =
29.69
a/2 =
0.15
As Required =
0.115 inA2/ft OK
As Minimum =
FIEEL
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0."
Bar Spacing =
As Provided =
0.44 inA2jtt.
Bar Diameter =
0.75
d =
29.63
a/2 =
032
As Required =
03Q inA2/ff OK
As Minimum =
7 Load :Foctors
D 1.0
L 0.8
E 0.5
H I -C'
0
Point Edwards Site Retaining Walls
September 14, 2006
DCI Job # 06-11-009
Building 6 & 7
Retaining Walls
DCI-EN GIN EEW!)
D'AMATO CONVERSANO INC.
1PROJECT: PROJECT NAME
SUBJECT: Retaining Wall Design
seismic Pressure = 170.0 psf
Design Lateral Pressure = 35 pcf
= 75 0 st
PROJECT NO: SHEET NO:
DATE:
Non -Seismic BY:
Surcharge Pressure i'
SOIL SURCHARGE
**.--.a Lateral Pressure = 30*0 PC I
as.
Cron = 040
Unit Weight of Soil = 120 pcf
Trioutory Length of wall 1.0,
-V
Concrete Strength 4000 psi
0 00 k fr"
Column DL
Column LL 0 00 k
3, 4
AC cled
Wt of Soil croove Heel 84k
Wt of Wall I . 61,
34k
W? of Footing
V`
1111 f
EQ
9M.0 plf 1.0* Lo' 7.0' 437.5 pit 75.0 pit 170 p
9.00'
Wall ok Footing Toe ok Footing Heel
d 9.0" d = 26.0" d = 26.0-
VU = 4.5D k VU = 5-53 k Vv = 10.60 k
OVc = 10.25 k 0VC = 29.60 k VC = 29.60 k
Mu = 17.83 fl-k M,, = 2.76 ft-k Mu = 37.09 ft-k
FS Sliding ok FS Overturning ok
Sliding Resistance 6.1 k 0.94 RM = 57.4 fl-k IZ2
Sliding Force 6.5 k OTM = 31.5 ft-k
Soil Bearing ok
X = 32.2 fl-k = 2.4 1'
13.4 k
e = 2.09' b/6 1.50'
If e < b/6, Then... It e > b/6, Then...
Soil Bearing Soil Bearing 2 P
= -L - = = 3.55 Ut
Stress Left A S Stress 3 5-b :e
Soil Bearing 2 103 't I 1 3.69 lal
-0.58 f 't
Stress Right A S 3 2011
P = D-L = 13.4k A = 9.0 5f vAdth 7.24*
M = Pe = 27.13 fl-k s = 13.5 fIA3
Load Factors
D 0.90
L 0.00
E 1.00
H 1.60
WALL
Wall Concrete (fc) =
4 ksi
Wall Reinforcing (ty) =
60 ksi
Cover =
Bar Size =
Bar Area =
044
Bar Spacing =
As Provided = 0 44,nA2/tt.
Bar Diameter =
075
d =
963
a12 =
0 + 32
As Required = 0 426 inA2/tf 01(
As Minimum =
TOE
Wall Concrete (fc) =
4 ks!
Wag Reinforcing (ty) =
60 kSi
Cover =
3 in.
Bar Size =
Bar Area =
0.31
Bar Spacing =
lc�.
As provided =
0-211 . A /N.
Bar Diameter =
0.625
d =
26.69
af2 =
0.15
As Required =
0.023 inA2/fi OX
As Minimum =
HEEL
Wall Concrete (fc) =
4 kSi
Wan Reinforcing (ty) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0.44
Bar Spacing =
i 2 :,-..
As Provided =
0." inA2/fL
Bar Diameter =
0.75
d =
26.63
a/2 =
0.32
As Required =
0.313 inA2/ff OK
As Minimum =
DCI-EN GIN EERS
9=
- D'AMATC, CONVERSANO INC.
I PROJECT NO: SHEET NO:
Load Factors
PROJECT: PROJECT NAME
DATE:
D 13)
SUBJECT: Retaining Wall Design
Non -Seismic BY:
L 1.00
E 1.00
Seismic Pressure = 170.0 psf
-H 0.00
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 75.0 pst
SOIL SURCHARGE
Passive Lateral Pressure z 3W pcf
Base Friction = 040
**Unit
WALL
Weight of Sod = 120 pcf
Wall Concrete (fc)
4 ksi
Tributary Length of Wall = 10'
Wall Reinforcing (ty)
60 ks,
Concrete Stiengin = 4000 ps,
Cover=
1.9
-
Column DL = 0 00 k
Bar Size =
Column LL = OODk
Bar Area =
044
841,
Wt of W clocive Heel JA eli Dior C61umn
12 5'
r
Bar SpacAng =
As Provided = 0.44
inA2/ff."
wi. ot War 161,
Bar Diameter =
0.75
Wt. of Footing 34k
d=
9.63
a/2 =
032
As Re 0.293 in A2/ff
-quired =
I So
Z�4
As Minimum
IOE
EO
Wall Concrete (rc) =
4 ks,
Wall Reinforcing (fy) =
60 ksi
900.0 Pit 1.0* 1.0* 7.0'
437-5 pit 75.0 pit 170 pit
Cover =
3 in.
9.00'
Bar Size =
wall ok Footing Toe ok
Footing Heel
Bar Area =
0.31
d 9.0- d = 26.0-
d = 26.0"
Bar Spacing =
I
V,, = 2.45 k VU = 3.94 k
V,, = 14.13 k
As Provided =
0.21 jnA2/ft.
#VC = 1025k OVC = 29.60 k
+Vc = 29.60 k
Bar Diameter =
0.625
d=
26.69
Mu = 12.25 11-k M,, = 1.97 ff-k
Mu = 49.46 ft-k
a/2 =
0.15
As Required =
0.0 17 !nA2/ft
OK
FS Sfidin-a ok
FS Overturning ok
As Minimum =
Sliding Resistance 7.7 k
RM = 76.S ft-k
FIEEL
2.52
Sbaling Force 3.1 k
4.00
OTM = 19.1 fi-k
Wall Concrete (fc) =
4 ksi
Wall Re inforcing (ty) =
60 ksi
Soil Beaning ok
Cover =
3 in.
Bar Size =
0
44.6 fl-k 3.34'
Bar Area =
0.44
,3 4 k
Bar Spacing =
12;n..
As Provided =
0.44 inA2/ft.
e 1.16' < b/6 = I-W
Bar Diameter =
0.75
d=
26.63
I" e < b/6. Then... It e
> b/6, Then...
a/2 =
0.32
Sol Bearing P M Soil
Bearing 2 P
As Required =
0.418 inA2/11
oil
. = = 2.63 kst
Stress Left A 5
Stress 3 _5_b:]�:j
r�03:
As Minimum =
Saii5earing P - 2L = = 0,34 ksf
k I _0.
2 2.66 ksf
Stress Rign! A S
3 4 l."
P = DIL = 13.4 k A = 9-0sf
%vidth 10.07
14, = Re = 15-5 fl-k 5 = 13.5 ftA3
0
.4
D 'AMATO CONV E RSAN 0 1 NC. F ��JECT NO: SHEET NO: Load Factors
PROJECT: PROJECT NAME DATE: D 0.60
SUBJECT: Retaining Wall Design Non -Seismic BY: L 0.00
E 0.70
Seismic Pressure = 170.0 psl 1.00
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 75.0 psf SOIL SURCHARGE
ive Lateral Pressure = 300 pcf t,
60-a's: friction = 040 ; ": -
WALL
Unit Weight of Sal 120 pcf 4 ksi
Wall Concrete (17c) =
Tributary Length of Wall 10'
Wall Reinforcing (fy) = 60 ks,
Conciele Strength 4000 psi Cover= 2.n.
Co�u-n DL 0 00 k Bar Size =
Co umn LL 0.00 k Bar Area = 044
77
Bar Spacing r
IZS'
Wt of Soil obo�e Heel 84k A oid D am ColdrIn"n 0 in�2/11.
As Provided =
Wt. at Wall 1 6 K
Bar Diameter = 0.75
Wt. of Fooling 3 4 k
dz 9.63
0-32
a/2 =
0.282,nA2/ft
k As Required =
P
(0_1 150 C
As Minimum
TOE
4 ksi
7-
Wall Concrete ffc) =
EQ
900.0 pit 1.0, 1.0* 7Z 437.5 pit 75.0 plf 170 pit Wall Reinforcing (fy) = 60 U
Cover = 3 in.
9.00' Bar Size =
Wall ok Fooling Toe ok Footing Heel Bar Area = 031
d 9.0" d = 26.0- d = 26.0- Bar Spacing =
V,, = 2,94 k V,, = 4.12 k VU = 7.07 k As Provided = 0.21 inA2/ft.
�Vc = 10.25 k �Vc = 29.60 k +VC = 29.60 k Bar Diameter = 0.625
d= 26.69
Mu = 11.78 tf-k M,, = 2.06 tt-k M� = 24.73 fl-k a/2 = 0.15
As Required = 0.017 jnA2/" OK
FS Sliding ok FS Overturning ok As Minimum =
Sliding Resistance 4.5 k RM = 38.3 ff-k HEET
1.85
Sliding Force 4.2 k OTM = 20.7 fl-k Wall Concrete (fc) = 4 ksi
Wafl Reinforcing (fy) = 60 ksi
Soil Bearing ok Cover = 3 in.
Bar Size = 6
43.1 fl-k 3.23' Bar Area = 0.44
13.4 k Bar Spacing = , 2 �n.
0- As Provided = 0." inA2/h.
e = 1.27' < b/6 = 1.50' Bar Diameter = 0.75
d= 26.63
It e < b/6, Then... It e b/6. Then... a/2 = 032
Soil Bearing = P . M 2.74 ksf Soil Bec--wg 2 0__P L As Required = 0.2D9 inA2/ff 0 K
A - -Ss .5.b e
Stress Left S Stra 3 As Minimum =
34k /7
Soil Bearing P M 2 .0.
= - . - = = 0.22 ksf _ = 2.76 ksf
Stress Right A S 3 4.5. 1_2TJ -
P = D-L = 13.4 k A = 9.0 Sf wIct'. 9.68'
M = Pe = 17.0 ff-k S = 13.5fM3
DCI -ENGINEERS
D'AMATO CONVERSAN PROJECT NO SHEET NO:
0 1 NC- Load Factors
PROJECT: PROJECT NAME DATE:
I D 1.00
SUBJECT: Retaining Wall Design Non -Seismic BY: L 0.75
1 E 0-yi
Seismic Pressure = 170.0 psf H 1.00
Design Lateral Pressure = 35 pcf
S h e Pressure = 75.0 psf
SOIL SURCHARGE
urc a
4p.sswegL...) Pressure 300 pcf
B B
ase Fncl,on 040 WAU
Unit Weight 01 Sol 120 Pct Wall Concrete (fc) z 4 kSl
Wag Reinforcing (ty) =
TrOulory Length at wall 0* 60 Ksi
Concrete Strength 4000 psi Cover = 2n.
Bar Size = 6
ColumnDL 0 00 k
Bw Area 0."
Column LL 0 00 k
�-10 0,
Bar Spacing
125
WI of Soil obo�e Heel 8 4 AC d6d F)l from Col
As Provided
Wt at Wall l6k Bar Diameter 0.75
.4-, �V
WI. of Footing 34k d= 9.63
ar2 = 032
4, As Reqtwed = 0313 inA21ft on�
0. C As Minimum =
TOE
4 k3l
EQ Wall Concrete (fc) =
900.0 plf iff 1.0* 7.Or 437.5 plf 75.0 pit 170 pff Wag Rewdorcng (ty) = 60 ksi
cover = 3iih.
9.00' Bar Size =
Wall ok Footing Toe ok Footing Heel Bar Area = 0.31
d 9.0" of = 26.0" d = 26.0" Bar Spacing = !�:;.
V,, = 3.21 k V,, = 4.35 k V,, = 11.78 k As provided = 0.21 inA2/fl.
OVc = 10.25 k VC = 29.60 k VC = 29.60 k Bar Dorneter = 0.625
d= 26.69
M, = 13.11 ft-k Mu = 2.17 ft-k Mu = 41.21 ft-k ar2 = 0.15
As Required = 0.0l8inA2/fl OK
FS Sliding ok FS Overturning ok As Minimurn =
Sliding Resistance 6�;l RM = 63.8 ft-k UEEEL
= ; 2.80
1.46 4 kSi
Sliding Force k OTM = 22.8 fl-k Wall Concrete (fc) =
Wall ReWorcing (fy) = 60 U
Soil Beating ok Cover = 3 bL
Bar Size =
4 1.0 fl-k Bar Area = 0.44
X 3.07'
.4 k Bar Spacing =
0 AS provided = 0.44 inA2/ff.
e = 1.43* < b/6 = 1.50' Bar Diameter = 0.75
d= 26.63
If e < b/6. Then... If e > b/6, Then... ar2 = 0-32
Soil Bearing = P M 2.90 ksf Sail Bearing 2 As Required = O_UB inA2/ft
Stress Left A S - Stress 3 0 .5. b As Minimtxn =
Soil Bearing = P _!�_ 0.07 li:st 2 __13 4 '. / ".'I = 2.90 ksf
Stress Right A S 3 4.5 _ 1 43
p = D-L = 13.4 k A = 9.0 Sf ,iridth 9.21'
M = Pe = 19.1 fi-k S = 13,5 ft�3
0
DCI -ENGINEERS
D'AMATO CONVERSANO INC. PROJECT NO: SHEET NO: Load Factors
PROJECT: PROJECT NAME DATE: D 0-WI
L 0.00
SUBJECT: Retaining Wall Design Non -Seismic BY: E I.r.lo
Seismic Pressure = 170.0 pst _H
Design Lateral Pressure = 35 pcI
Surcharge Pressure = 75 0 psf
fr SOIL SURCHARGE
Possi�e Lateral Pressure = 300 pcf
WALL
_4L
Unit Weight of Soil Wall Concrete (fc) 4 ks,
B s
a e Friction = 040
= 120 pcf
Tributary Length of Wall = 1.0, F,
Wall Reinforcing (ty) 60 ksi
Q 'A'
Concrete Strengtn = 4000 psi
Cover= '2,n
Column OL 0 00 k ;--.f Bar Size =
Column LL 0 00 k Bar Area = 0-31
Bar Sparing
3 0'
W1 of Soil aao�e Heel = l4k A
0,31 inA2/11.
As Provided =
wt� of Wall = o4k Bar Diameter = 0.625
Wt of Footing =
7.68
d=
0.?3
�qf a/2 =
As Required = 0. 189 jnA 2/ft OK
an Pff
44
As Minimum
TOE
-.4
'R 4 K9
EQ Wall Concrete (fc) =
on lolf 1.0* 043' 4.0' 157-5 pit 75.0 pit 170 plf Wall Reinforcing (ty) = 60 ksi
450 Cover= 3 in.
SAX Bar Size =
Wall -ok Footing Toe ok Footing Heel Bar Area = 0.31
d = 7.0" d = 14.0- d - 14.0" Bar Spacing = 1 A :ri.
Vi, = 0.76k V, = 3.90 k Vu = 2.48 k As Provided = 0.21 inA2/ff.
VC = 7.96 k = 15.94 k 4VC = 15.94 k Bar Diameter = 0.625
d= 14.69
M� = 6.35 fl-k M,, = 1.95 ft-k M,, = 4.95 tt-k a/2 = 0.15
As Required = 0.030 inA2/ft O-K
FS Sliding ok FS Overturning ok As Minimurn =
Sliding Resistance 1 �2? RM = 9.0 ft-k 1.22 U[EEL
Sliding Force 0.9 k OTM = 7.4 fl-k Wall Concrete (fc) = 4 ksi
Wall Reinforcing (ty) = 60 ksi
Soil Bearing ok Cover = 3 in.
Bar Size = 5
2.6 ft-k Bar Area = 031
X 3.2 k 037 Bar Spacing = ; _2 !"'.
0 As Provided = 0.21 inA2/11.
e 2.19 b/6 0.97 Bar Diameter = 0.625
d= 14.69
if e < b/6, Then... If e > b/6, Then... a/2 = 0.15
Soil Bearing = P 1.73 k5f Soil Bearing 2 =P/ L As Required = 0.076 inA2/fI 0K
Stress Left A S Stress 3 b e As Minimum =
Sri] Bearing = .0.63 ks, 2 3.2 k 1.0, 2.60 ksf
Stress Right A 3 2.9, 2.10.1
P = D�I_ = 3-2 k A = 5_8 Sf vAdIh 2.45*
M = Pe = 6.7 ft-k S = 17ftA3
0
i5iRtUlCI-ENGINEERS
_. D'AMATO CONVERSANO INC.
PROJECT NO:
SHEET NO:
Load Factors
PROJECT: PROJECT NAME
DATE:
D 1.20
SUBJECT: Retaining Wall Design
Non -Seismic
BY:
L 1.00
E 1.00
Seismic Pressure = 170.0 psi
H 0.00
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 75 0 psf
SOIL
SURCHARGE
Lolc(ol Pressure 300 pcf
ea,ss,ve
a e Friction 040
WALL
Unit Weight of Sol 120 pcf
wall Concrete (rc)
4 ksi
Tributary Length of Wall 1.0*
4,
Wall Reinforcing (ty)
60 ksi
Concrete Strength 4000 psi
Cover =
2,n
Column DL = 0 OD k
Bar Size =
Column LL = 0.00 k
Bar Area =
0.31
eAm
3:0 1C.
Bar Spac4ng =
Wt of Soil o0ove Heel = 1 41� AC
Cled Oil
it n
3 (Y
-7-
As Provided
0 31 in 2/ft.
wl of Wall = 041,
Bar Diameter
0625
Wt. of Footing 13k
d=
768
a 2 0.23
As Required = 0 186.n�2/ff OK
As Minimum =
TOE
7 Wall Concrete (fc) 4 kSi
Wag Reinforcing (fy) 60�ksi
0.0 pit
Iff
0.83'
4.(Y
157.5 pit 75D pit 170 pit
450
Cover =
3 in.
S.83*
Bar Size =
Wall ok
Footing Toe
ok
Footing Heel
Bar Area =
0.31
d = 7.0-
d = 14.0"
d = 14Ar
Bar Spacing =
lz:,.
Vv = 0.74 k
vu =
2.74 k
Vu = 3-30 k
As Provided =
0.21 inA2/11.
+Vc = 7.96 k
VC =
15.94 k
+Vc = 15.94 k
Bar Diameter =
0.625
d =
14.69
M,, = 6.25 H-k
MU =
1.37 fl-k
M,, = 6.61 fl-k
a/2 =
0.15
As Required =
0.021 inA2/fI Ok
FS Sliding ok
FS Overturning
ok
As Minimum =
Sliding Resistance
1.5 k
RM
= 12.0 ft-k
HEEL
Sliding Force
0.7 k
2.08'
OTM
1.91
= 6.2 ft-k
Wall Concrete (fc) =
4 U
Wall Reinforcing (fy) =
60 Icsi
Soil Bearing ok
Cover =
3 in.
Bar Size =
3.7 ft-k
Bar Area =
0.31
3.2 k
0
Bar Spacing =
1A M.
As Provided =
0.21 inA2/11.
e 1.75' > b/6 0.97'
Bar Diameter =
0.625
d =
14.69
If e < b/6. Then...
If e > b/6, Then...
a/2 =
0.15
Sail Bearing P M
Soil Bearing
2 P
As Required =
0-101 inA2/f1 OK
Stress Leh A
1.53 ksf
Stress
3 - - e
0- 5�
As Minimum =
Soililearing P - M
-0A4 ksf
2 3' : _a
iz2 ksf
Stress Right A S
3 2-1
F, = DL = 3.2 k
A = 5S St
width 3.50'
M = Pe = 5.6 fl-k
S = 5.7 flA3
�M DCI -ENGINEERS
D'AMATO CONVERSANO INC.
PROJECT: PROJECT NAME
SUBJECT: Retaining Wall Design
Seismic Pressure = 170.0 psf
Design Lateral Pressure = 35 pcf
= 75 0 -sl
PROJECT NO: SHEET NO: Load Factors
DATE: D 0.60
L 0.00
Non -Seismic BY: E 0.70
H 1-00
urc orge ressure
.:eLateral Pressure = 300 pcf
,.0n
Fee. = 040
1w
SOIL SURCHARGE
Unit Weight of SDI 120 pcl
Tributary Length of Wall 0*
Concrete Strength '11300 psi
t .
Column DL 0 00 k
V.;,
r".
Column LL 0.00 k
......
..�F,_3 0'
Wt of SDI at:>ove Heel l4k Ac
am. vrTin*-,,,14�4,v,
3 0*
Wt of Wall 0.4 k
Wt. of Footing 1-3 k
41,
EQ
0.0 pit 1.0*
0.83'
4.0'
157.5 pit 75.0 pit 170 plf
450
5.83'
Wall ok Footing Toe
ok
Footing Heel
d = 7.0-
d = I,k0-
d = 14.0"
V� = 0.51 k
V, =
2.02 k
V,, = 1.65 k
+Vc = 7,96 k
+Vc =
15.94 k
0c = 15.94 k
M,, = 4.29 ft-k
Mu =
1.01 ff-k
Mir = 3.30 li-k
FS Sliding ok
FS Overturning
ok
Sliding Resistance OS k
RM
= 6.0 ff-k 1.21
-
Sliding Force 0.6 k
1.29
OTIVI
= 4.9 ft-k
Soil Bearing ok
5.0 ft-k
1.58'
3.2 k
e 1.34' > b/6 0.97'
If e < b/6, Then
if e > b/6, Then...
Soil Bearing P
Soil Bearing
2 P L
= = 1.30 ksf
Stress Left A S
Stress
7_
3 0.5 b e
P M
Soil Bearing - . - = = -0.20 ksf
2 3.2k I a
�4,
1.35 ksf
Stress Right A S
3 2_7 1
P = 0-1. = 3.2k A = 5.8 sf
idth 4.74'
M = Pe = 4.3 ft-k S = 5.7 fIA3
I*
WALL
Wall Concrete (fc) =
4 kSi
Wall Reinforcing (ty) =
60 ksi
Cover =
2".
Bar Size =
Bar Area =
031
Bar Spacing =
; �- ".
As Provided =
0-31 inA2/ft.
Bar Diameter =
0.625
d =
768
a/2 =
0.23
As Required =
0 128 InA2/ft 0<
As Minimum =
TOE
Wall Concrete (fc) =
4 V-9
Wall Reinforcing (ty) =
60 Irsi
Cover =
3 in.
Bar Size =
Bar Area =
0-31
Bar Spacing =
I � i..
As Provided =
0.21 inA2/tt.
Bar Diameter =
0.625
d =
14.69
a/2 =
0.15
As Required =
0-015 inA2/fI 3K
As Minimum =
FEEEL
Wall Concrete (fc) =
4 kSi
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0.31
Bar Spacing =
As Provided =
0.21 in42/ft.
Bar Diameter =
0.625
d =
14.69
a/2 =
0.15
As Required =
0.050 inA2/ft OK
As Minimum =
DCI -ENGINEERS
D'AMATO CONVERSANO INC.
PROJECT: PROJECT NAME
SUBJECT: Retaining Wall Design
Seismic Pressure = 170.0 psf
Design Lateral Pressure = 35 pcf
= 75 0 -sf
PROJECT NO: SHEET NO: Load Factors
DATE: D 1.00
L 0.75
Non -Seismic BY: E 0.53
H 1.00
urc arge essure
assive Lateral Pressure
ase Friction
300 pcf
040
SOIL SURCHARGE
Unit We,ghl of Soil
120 pcf
Tributary Length of Wall
1.0*
Concrete Strength
4000 psi
Column DL
0 00 k
Column LL
0 00 k
3 0-
Wt. of Soil above Heel
I 4k
AC
3.0*
Wt of wall
04k
Wt. of Fooling
'P
EQ
0.0 pit Iff oaX 4Z
157.5 pit 75.0 pit 170 p
450
&aX
Wall ok Fooling Toe ok
Footing Heel
d 7.0- d = 14.0"
d = 14.0"
V,, = 0.59 k V,, = 2.33 k
Vu = 2.75 k
#Vc = 7.96 k +Vc = 1&94k
+V, = 15.94 k
Mu = 4.97 ff-k = 1- 17 Il-k
Mir = 5.50 ft-k
FS Sliding ok FS Overturning ok
Sliding Resistance l3k RM
= 10.0111-k
I.?G
Sliding Force 0.7 k OTM
1.78
= 5.6 ft-k
SollElearing ok
4.4 ft-k
1.37'
3.2 k
e 1.55' > b/6 = 0.97'
If e < b/6, Then... IT e > b/6, Then...
Soil Bearing = P M = = 1.42 ksf Soil8earing
2
P
Stress Left A 5 Stress
3
0 5-b e
r2
Soil Bearing = P M = = -0.32 ksf
2
3 '.0"1
1-5-1 kf
Stress Right A S
3
2 . 1 55
p = D-L = 3.2 k A = 5.8 sf width
4.11'
M = Pe = 4.9 ft-k S = 5.7 IIA3
0
WALL
Wall Concrete (fc) =
4 kSi
Wall Reinforcing (ty) =
60 kSi
Cover =
Bar Size =
Bar Area =
0.31
Bar Spacing =
As Provided = 031 nA2/ft
Bar Diameter =
0625
d =
7.68
a12 =
0.23
As Required = 0.
148 inA2/tt
As Minimum =
TOE
Wan Concrete (fc) =
4 KS,
Wall Retriforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0.31
Bar Spacing =
I � ;.-.
As Provided =
0.21 inA2/fl.
Bar Diameter =
0.625
d =
14.69
a12 =
0.15
As Required =
0.0 18 inA2/ft OK
As Minimum =
REEL
Wall Concrete (fc) =
4 U
Wall Reinforcing (fy) =
60 U
Cover =
3 in.
Bar Size =
L
Bar Area =
0.31
Bar Spacing =
1 S V �.
As Provided =
0.21 inA2/ft.
Bar Diameter =
0.625
d =
14.69
a12 =
0.15
As Required =
0.084 inA2/ft 0?1'
As Minimum =
DC I -ENG IN EERS
D'AMATO CONVERSANO INC.
Project
Subject
X
Project No. Sheet No.
Date
B�:
Loads: BLC 1, soil
�Results for LC 1. wall
'Aug 21, 2006 at 10:24 AM
untitled.r3d
CTkft
L . . ....
Loads: BLC 2, surcharge
Results for LC 1, wall
Aug 21, 2006 at 10:24 AM
untitled.r3d
Results for LC 1, wall
Member y Shear Forces (k)
Aug 21, 2006 at 10:24 AM
untitled.r3d
Results for LC 1, wall
blember z Bending Moments (k-ft)
Aug 21, 2006 at 10:24 AM
untitled.r3d
0
00
WE DCI -ENGINEERS
D'AMATO CONVERSANO INC.
Project Number
Sheet Number
06-11-031
Project:
Pt. Ed. Building 6/7
Date:
8/21/2006
Sub)ect:
Retairuing Wall Design
By:
Dtiveway Slab
fc
4 ksi
fy
60 ksi
h
10 in
w
12 in
cover
2 in
d (in.)
7.6875 in
assume a
= 0. 1 *d
0.1*d
0.76875 in.
1 st Iteration
0.213 in A 2
a
0.313 in.
2nd Iteration
As
0.207 in A 2
a
0.304 in.
3rd Iteration
As req'd
in A 2/ft.
a =
0.304 in.
As provd'd 0.207 in A 2/tt.
Bar #
5
diam. Bar
0.625 in
area Bar
0.31 in A 2
Mu
7 k-ft 84 k-in
Mi
7.78 k-ft 93.33 k-in
Vu 1.1 k
phi 0.75
phi*Vc 8.75 k
OK
Steel & Spacing
5 at 18 in.
ft
ODCLENGINEERS
_. D'AMAI'O CONVERSANO INC. F�T NO: SHEET NO:
PROJECT: PROJECT NAME DATE:
SUBJECT: Retaining Wall Design Non -Seismic BY:
Soil Load (x*H) 26H
S harge Load
= 75.0 psf
SOIL
SURCHARGE
Ourcive Lateral Pressure
= 300 pcI
Base Friction
= 0.35
Unit Weight of Soil
= 120 pcf
Tributary Length of Wall
= 1.0,
Concrete Strength
4000 psi
Column DL
0.0 k
Column LL
= 0.0 k
f-10.0"
Wt. of Soil above Heel
= 30k
Ac
u
rom Col' nin
W1. of Wall
= 1.3 k
Wt. of footing
= 1.3 k
io, -
A.57- 450D pit-,-.:.
900.0 plf
2.5'
0.83' 2.5'
78.0 pli 75.0 pit
5.83'
Wall
Footing Toe
Footing Heel
d 7.5"
d = 14.0"
d = 14.0
Vu = 2.45 k
Vu = 7.47 k
V� = 6.90 k
+Vc = 8.54 k
iloVc = 15.94 k
Vc = 15.94 k
Mu = 12.24 ft-k
Mu = 9.34 ff-k
Mu = 8.62 ft-k
FS Slicling
Sliding Resistance
2.2 k
Sliding Force
1.25
1 8 k
Bearing ok
11.3 tf-k
X = 2.00'
5.6 k
e = 0.9 1, < b16 0.97'
ff e < b/6. Then...
SoilBearing
=
Stress Left A S
1.87 ksf
Soil Bearing P M
=
Stress Right A S
0.06 ksl
P = D+L = 5.6 k
A = 5.8 sf
M = Pe = 5.1 ft-k
s = 5.7 fjA3
ri
FS Overturning
RM = 13.3 ft-k = 1.32
OTM = 10.1 ft-k
It e > b/6. Then...
Soil Bearing 2
P
P
Stress 3
0 0 5 b e
b e
5-b e
2
6 I . 0'
6 k
6 k
k 0
1 -.0
1.87 ksf
3
2.1" 111111�j
width 6.01'
WA_LL
Wall Concrete (fc) =
4 K51
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
031
Bar Spacing =
; , in
As Provided =
0-31 -12/ft-
Bar Diameter =
0.625
d =
665
a/2 =
0.23
As Required =
0 424 rnA2/fj
As Minimum =
IOE
Wall Concrete (fc) =
40
Wall Reinforcing (fy) =
60 ksi
Cover =
3 in.
Bar Size =
Bar Area =
0.31
Bar Spacing =
1A in
As Provided =
0.21 inA2/ft.
Bar Diameter =
0.625
d =
14.69
a/2 =
0.15
As Required =
0. 143 inAZrtt
170K
As Minimum =
HEEL
Wall Concrete (fc) =
4 U
Wall Reinforcing (fy) =
6OU
Cover =
3 in.
Bar Size =
Bar Area =
031
Bar Spacing =
1
As Provided =
0.21 inA2/ft.
Bar Diameter =
0.625
d =
14.69
a/2 =
0.15
As Required =
0.132 inA21tt
I
C.
As Minimum =
�ft DCI -ENGINEERS
D'AMATO CONVERSANC) INC. PROJECT NO: SHEET NO:
I -
PROJECT: PROJECT NAME DATE:
SUBJECT: Retaining Wall Design Non -Seismic BY:
Soil Load (x*H) = 26H
Surcharge Load = 75.0 pst
SOIL SURCHARGE
assive Lateral Pressure 300 pCf
Wase Friction 0.35 1.,... . .4 - . " - . I.. I
WALL
Unit Weight of Soil 120 pcf
Wall Concrete (f c) 4 ksi
Tributary Length at Wall = 1.0, 60 ksi
Wall Reinforcing (fy) =
Concrete Strength = 4000 psi .4.
Cover = 3 in.
Column DL = 0.9 k
Bar Size = 5
Column LL 0.0 k Bar Area = 0.31
Bar Spacing = 12;
Its
Wt. of Soil above Heel = 05k A
As Provided = 031 inA2/ft.
* 0.2 k Bar Diameter = 0.625
Wt. of Wall
* l3k
Wt. of Footing
d= 6.65
a/2
0.23
As Required
0 inA
0.0 PI I
As Minimum
001 2/ft
TOE
ZZ
n 4 ksi
Wall Concrete (f c) =
0.0 pit 2.5* 0.83' 2S 78.0 plf 75.0 plf Wall Reinforcing (fy) = 60 ksj
Cover = 3 in.
5.83* Bar Size = 5
Wall Footing Toe Footing Heel Bar Area = 0.31
d 7.5" d = 14.0- d = 14.01. Bar Spacing = 18:n.
Vu = 0.37 k vu = -0.65 k VU = 2.82 k As Provided = 0.21 inA2/ft.
OVc = 8.54 k 4VC = 15-94 k OVC = 15.94 k Bar Diameter = 0.625
d= 14-69
MU = 0.28 ft-k Mu = -0.81 M, = 3.52 ft-k a/2 = 0.15
As Required = -0.0 12 inA2/ft
FS Sliding FS Overturning As Minimum =
Sliding Resistance 0.6 k 1.32 RM 5.5 ft-k F[UL
Sliding Force 0.5 k OTM 0.7 ft-k Wall Concrete (fc) = 4 ksi
Wall Reinforcing (fy) = 60 ksi
woil Bearing ok Cover = 3 in.
Bar Size = 5
8.5 ft-k Bar Area = 031
x = -2 4.20'
.0 k Bar Spacing = 18:n.
As Provided = 0.2) inA2/ft.
e = - 1.29' < b/6 = 0.97' Bar Diameter = 0.625
d= 14.69
If e < b/6. Then... 11 e > b/6, Then... a/2 = 0.15
Soil Bearing P M Soil Bearing 2 P L As Required = ().054 inA2/ft
Stress Leff A S -0. 16 ksf Stress 3 0_5.b e As Minimum =
SoilBeadng P M 2 2.9kT
1.0
1.15 ksf _ = 0.460
Stress Right A S 3 2.9 _ _1.29.1
P = D+L = 2.9 k A = 5.8 sf vvidth 12.6 V
M = Pe = -3.7 ft-k S = 5.7 tfA3
—'/ -g
PERMITEXPIRES
CITY OF EDMONDS r
CONSTRUCTION PERMIT APPLICATION
OWNER NAME/NAME OF BUSINESS
4blItIr �Spjvltxl) D's 16
MAILING ADDRESS
a/
CITY ZIP;?. TELEPHONE
11\_�54tliel - /*
NAME I/
ADDRESS
1.�C/4``/-t'F _]�#
NAME CBL#
J�WZ_
ADDRESS
Im aiL M-/y W/& )�Wf7l
CITY ZIP ELEPHONE
STATE LICENSE NUMBER EXPIRATtON)DATE� CHECKED BY
PROPERTY TAX ACCOUNT PARCEL NO
NEW
0 RESIDENTIAL
PLUMBING / MECH
ADDITION
COMMERCIAL
MIXED USE
COMPLIANCE OR
CHANGE OF USE
REMODEL
MULTIFAMILY
SIGN
REPAIR
GRADING
CYDS
FENCE
( X FT.)
DEMOLISH
TANK
OTHER
GARAGE
CARPORT
RETAINING WALL
ROCKERY
F!RE SPRINKLER
F RE ALARM
(TYPE OF USE. -BUSINESS OR ACTIVITY) EXPLAIN:
Iry
NUMBER NUMBEROF
OF DWELLING
STORIES UNITS
DESCRIBE WORK TO BE DONE z7
I/ I Ze /_ A 7 A-,-, — — 1 -7 —7 9
PERMIT
NUMBER
JOB jSUI EJAPT#
ADDRESS /
05 �; �".je'01V, /'� � � r�
PLAT NAME]SUBDIVISION NO, LOT NO. LID NO.
I LID FEE $
PUBLIC RIGHT OF WAY PER OFFICIA:L STREET MAP TESCP Approved 81
Rw Permit Required
EXISTING PROPOSED Street use Permit Required 13
Inspection Required _M�
Sidewalk Required U
REQUIRED DEDICATION FT Unde(groun
wiring required
METER SIZE LINE IZE NO. OF FIXTURES PFIV REQUIRED
YESU NOD
REMARKS
OWNER/CONTRACTOR RESPONSIBLE FOR EROSION CONTROUDRAINAGE
ENGINEERING REVIEWED BY -.17 ' 7 1 1 1 nATr
19
RECYCLE
PUBLIC
LL
/11ARIANCE Oil CU SHORELINEORADB# INSPECTION EPA
REO'D COMPL T EXEMPT
ES 13 No
CA# ZONE SIGN AREA HEIGHT
[3 WAIVER ALLOWED PROPOSED ALLOWE
,Q� PROPOSED
OSTUDY ft 1 1 _7 13511.1
LOT COVERAGE REQUIRED SETBACKS (FT) PROPOSED SETBACKS (FT)
I
ALLOWED PROPOSED FRONT SIDE REAR FRONT L/RSIDE REAR
Ot /!�;t
z
PARKING
", I LOTAREA Pl_�;qN�NG REVIEWED BY DATE/
RF(Yr) . Ppr)vin 1 10.
TYPE OF CONSTR UCTION
�ODE
.";zov
'A
SPECIAL INSPECTIC, N
ANT
R REO X
U
EQUIRED YES
�'CONSULT
REMARKS
BY:
1
STF
BY:
wescripilion
E
2�74E
LOT SLOPE% VESTED DATE
I
Plan Check
. .
Building Permit
PLAN CHECK NO:
Plumbing
THIS PERMIT AUTHORIZES ONLY THE WORK NOTED. THIS PERMIT COVERS WORK TO
BE DONE ON PRIVATE PROPERTY ONLY. ANY CONSTRUCTION ON THE PUBLIC
Mechanical
DOMAIN (CURBS, SIDEWALKS, DRIVEWAYS, MARQUEES, ETC.) WILL REQUIRE
Grading
SEPARATE PERMISSION.
PERMIT APPLICATION: SEE ECDC 19.00.005(A)(6)
PERMIT LIMIT: SEE ECDC 19.00.005(A)(6)
Engr. , Review
SEE �4CK OF PINK PERMIT FOR MORE INFORMATION
Engr. Inspection
'APPLICANT, ON BEH .
ALF OF Hls�' SPOUSE, HEIRS, ASSIGNS AND SUCCESSORS
IN INTEREST, AGREES TO IND" 11 FlyhEFEND AND HOLD HARMLESS THE CITY OF
ITS 01 A LOYEES, AND AGENTS FROM ANY AND
Fire Review
,,?ASHINGTON,
ot HAT
ATIM� C"A M PO'R DAMAGES OF WHAT t)EMTORE, ARISING DIRECTLY OR INDIRECTLY
FROM THE ISSUANCE OF THIS PERMIT. ISSUANCE OF THIS PERMIT SHALL NOT BE
FY, WAIVE OR IILY %,fkk4lJIREMENT OF ANY CITY ORDINANCE
1_=WWYWAYTHE S * _E�FORCE ANY ORDINANCE PROVISION.-
CITYI�
Fire Inspection
LandscapeInsp.
\ \ k-,A-
I HEREBY ACKNOWLEDGE THAT I HAVE #MAD THIS APPLICATION; THAT THE INFORMATION
GIVEN IS CORRECT; AND THAT I AM THE OWNER, QRl THE DULY AUTHORIZED AGENT OF
THE OW�BW ,(GREE TO COMPLY&TIN A%4STATE LAWS REGULATING CONSTRUC-
4 1 NG THE WORK AUTHON
A 00 14 �S �BY NO PERSON WILL BE EMPLOYED
IN-VId A 10 OF THE LABOR PODE 0 A E OF WASHINGTON RELATING TO
AT
WORKMEN'S COMAJ!9
fj�kPA,,XCE AND RCW 18:27.
CALL
FOR INSPECTION
(425)
771 -0220
F T 111.1
SIGNATUMPEW NT):.'
DATE SIGNED
OCCUPANT
GROUP ...-
FEE
Description
FEE
State Surcharge
City Surcharge
Base Fee
v2A.11 1.1 �'_ I J—_
Recording Fee
Plan Chk. Deposit 01
Receipt #
fotal Amt. Due
Receipt #
APPLICATION APPROVAL
This application is not a permit until signed by the
Building Official or his/her Deputy: and Fees are paid, and
receipt is acknowledged in space provided.
I, I Zlr,�RE DATE
-A
ATTENTION F LIZ&
IT IS UNLAWFUL TO USE OR OCCUPY A BUILDING OR STRUCTURE UNTIL
A FINAL INSPECTION HAS BEEN MADE AND APPROVAL OR A CERTI-
FICATE OF OCCUPANCY HAS BEEN GRANTED. UBC109 / IBC110 / IRC110.
6/05
PRESS HARD - YOU ARE MAKING 4 COPIES
ORIGINAL - FILE YELLOW - INSPECT(
PINK -OWNER GOLD - ASSESSOR
fu
-roo.
Ci)
V11 At
LU
C4
I - 4:
Ilk.
C4
P. LIP I
13
I U I
L
In
uj
QP
do
LI --- L
a T
71
lol
lies
v
ca
I . . 'I til ------- IN
' ;v"A
pd,
Pit
Zv 7.1s..
14'
-INN
VA
77j,
IDA*
�P:
'Itt
'e�
'*g , t ov�
'R4
7P— _R
EN
%
VIA-.
�Slv
k is
q
DEC 22 2005
TERRA ASSOCIATES .. Inc. BUILDIN
C17y OGFDEEDPMAORNTMENT
Consultants in Geotechnical'Engineering, Geology DS
and
Environmental Earth Sciences
June 25, 2004
Project No. T-4893
Mr. -koss Woods
Point Edwards, LLC
2801 Alaskan Way, . Suite 107
Seattle� Washington 98121
Subject: - Building Drainage
Point Edwards Condominiums
Pine Stieet.and Unoco Road
Edmonds,.Washington .
Referenc . e: Preliminary Geotechnical Report, UNOCAL Site. Project No. T-4893, prepared by
Terra Associates, Inc., dated November 21, 2001
Dear Mr. Woods:
g6o' . hnical report, drainage of below -grade building walls can be accomplished
As discus6cd in -our refe=ced tec
by attaching prefabricated wall drainage panels to the backfilled'side of the wall. Water intercepted,by the
drainage. panels is routed to a footing drain at the base of the wall that conveys the water to the storm system.
As w6 have discussed with you, the footing drain may be ornitted from the daylight side'of the buildings, provided
the elevation of the basement slab is not below outside finished grade and the final exterior grades promote
positive . drainage avVayfrom the building areas..
estions or require
We trust the information presented is.sufficient for -your current needs. If you have any qu
additional "information, please call.
Sincerely yours,
TERRA ASSOCIATES, INC.
John CAO& kv
C/-_�510q
cc: Longitude 122, LLC
STREET FILE
12525 Willows Road, Suite 101, Kirkland, Washington 98034
Phone (425) 821-7777 a Fax (425) 821-4334
0
'A
DC
D'A M.
. v
I. --ENGINEERS
A , TO CONVERSANO INC.
I. Mark DArnato - Guy A. Conversano
Elizabeth A. lensen Rc�ger L. I leer&uiga - Alark D. Aden
I -lam, Jones 11 Troy E. Bean - Tom C. Xia, Ph.D.
Richard L. I lennnen - Grant C. Buckingham
Point Edwards Building 8
Edmonds, WA
Structural Calculations
For
�4
'�.�..".""Concrete and Foundation Permit Response Comments
Prepared For:
2n P.L.L.C.
Weber+Th*R on
1-1
Ak, CA
a,
December 19, 2005
DO Job # 5-11-263
RESUB
DEC 2 2 2005
BUILDING DEPARTMENT
CITY OF EDmONDS
S K_j
TREET FILE
10900 NE 4'rii STREET, SUITE 1200 - BF'I,I,EVLIE, WA 98004 * PHONE (425) 827.2238 o FAX (425) 827.8986
B I: 1, 1, 1: v k.] E SPOKANE E v F R FTT P 0 RT LA N 1) SAN Dwco
Ro-=
Point Edwards Building 8
December 19, 2005
DCl Job # 5-11-263
Structural Calculations Index
FOOTING and WALL CALCULATIONS Section A
Footing Depth Diagram A-1
Revised Wall Foundation Calculations A-2 to A-9
WIND CALCULATIONS Section B
Wind Calculations B-1 to B-2
Wind Speed -Up Effects Diagrams B-3 to B-4
ETABS MODEL Section C
Etabs Model Diagrams C-1 to C-5
LATERAL STABILITY Section D
Sliding Stability Calculations D-1 to D-2
4"
9
Point Edwards Building 8
December 19, 2005
DO Job # 5-11-263
FOO'TING
SECTION A
0
p
T.O. FARAI�57
EL- 157.00,
MAIN ROOF
W. PLATE
p 151.19,
LEVEL L5
T.O. Gypl
EB- 14200'
BEVELEE) 5117INS,
Tylp.
LEVEL L2
SYPCRETE
EL. 151.00,
LEVEL LI
T.O. P.T. SLAB
EL. 12011561
LEVEL PI
EL: 511LIh6l
VINYL VaNpol"
TYP
SY5TEM, TYP
42' NISH AT-.F.
ALUM 4 &LA55
6UAFl TYP
ALUM 4 CLASS
WARDRAIL. TYP
al
ryp.
T
VINYL VOID i eevELM Slic-INS j
SYSTID-1. rtr
I =N—
II [NEI
...............
.....................
.......... * ....... 11- . .......... H.
..... m ........
...... ........
..... .........
PARAPET
MAIN ROOF
T.O. PLATE
m- 151.151
LEVEL L5
TO. &YPl
m 142.00'
LEVEL L2
TD. Q.YPl
EL- 151.00,
I I MIN. c4jQ-, ::: I tjnj::[L 11 Ilu 11 9 11 11 111
TO OPERASLE RETA NIN&- Jill [I it LJLJ Pil I&==LL--Jj
kqImpo" -VIALL LEVEL LI
EL. 120,66'
OFIENING5 (TYF4.- T.O. J-.T. SLAZ
LINE OF
BEYOND I FARKIN015ARAOE LEVEL PI
SLAB
EL. illy,05,
OF
SX-I-REHE- L f0 I HI SOIL
100.
PARTIAL
EA5T ELEVATION
51-ALEOW - 1'-0* AT 52^ ANSL2
� --- Ll
AT 5.2' ANSLE
F-T6 PET, STIR-\) I Cbtq-ririL4ES DCw
rltF- fv-og�-- .
IN 'lilt��-
SHIl
TYP.
T.O. PARAPET
EL. 157.00,
MAIN ROOF
T.O. PLATE
El- 151.151
.........
42' f4l
ALLIM
�P
6UAIL.A
LEVEL Ls
,i, T.O. &YprRETr
1-fW F4 142.00'
......
T'
VINYL
5Y5TE:M'TYP
........... .. .....
............
..................
....... ............
pill
- ---- -
. .....
[um
..........
...........
TYP.
&- qg'-O"
LEVEL L2
Ail T.O. rlypcgrm
I �1-
11
I-F EL ISID01
IF
CONIZIRETE
CONCRE=M
I
TERRACE
bY.Y. ��rl
ppzo
-
In
LEVEL LI
T,O. P.T. SLAB
TY
TYP. FiWFF�E
--�'
-
12* MIN. Cj-R.
TO -- -;w
FARK]No6A�AOE
Fl-t- P EPZ VC-7-
LEVEL PI
ope'llNer. cryp)
I I
TO. SLA5
— — — — — —
EL. 111.66'
PARTIIAL.
1,A,l ELEVATION
AT 5.2' ANI
�-1
130
DCUENGINEERS
�MATO CONVERSANO INC.
PROJECT: Point Edwards Building #8
A SUBJECT: South Retaining Wall - Short Version
Design Lateral Pressure
Surcharge Pressure
= 35 pcf
= 75.0 psf
Passive Lateral Pressure
= 300 pcf
Base Friction
= 0.40
Unit Weight of Soil
= 120 pcf
Tributary Length of Wall
1.0,
Concrete Strength
= 4000 psi
Column DL
= 0.0 k
Column LL
0.0 k
PROJECT NO: 05-11-263 SHEET NO: A. z
DATE.- 12-20-2005
Non -Seismic BY'. JDB
C-C
SOIL SURCHARGE
7.0'
Wt. of Soil above Heel
2.2 k AdIded-13C from Co umn
Wt. of Wall
0.9 k
Wt. of Footing
3.6 k
0.'33' 99.0 plf
0i
3
.01
999.0 plf
4.5' 0.83' 2.67' 350.0 plf
8.00,
ok
Footing Toe
ok
d = 32.0"
V u 0.65 k
VU
7.96 k
7.92 k
�Vc
36.43 k
M' 3.40 ft-k
U.
Mu
17.90 ft-k
FS Sliding -ok
Sliding Resistance
3.3 k
1.31
Sliding Force
2.5 k
SoilBearing ok
24.4 ft-k
X 6.8 k 3.59'
e = 0.41' <
b/6 =
1.33'
If e < b/6, Then...
Soil Bearing
P M
_
Stress Left
+
A S
= = 1. 11 ksf
Soil Bearing
P M
_
Stress Right
-
A S
= = 0.59 ksf
P = D+L
= 6.8 k
A = 8.0 sf
M = Pe =
2.8 ft-k
S = 10.7 ftA3
75.0 plf
Footing Heel
d = 32.0"
Vu = 9.35 k
OVC = 36.43 k
Mu = 12.48 ft-k
FS Overturning ok
RM 20.4 ft-k
OTM 9.6 ft-k
If e > b/6, Then...
15.0'
2.12
Soil Bearing 2 P L
Stress 3 0.5*b e
2 - 6.8 k 1.01 = 1.26 ksf
3 4.0' 0.41'
width 10.78'
:1
D -ENGINEERS
C I
D 'AMATO CONVERSAN 0 1 NC. PROJECT NO: 05-11-263 SHEET NO:
PROJECT- Point Edwards Building #8 DATE: 12-20-2005
)UBJECT: South Retaining Wall - Short Version Seismic BY: JDB
Design Lateral Pressure = 35 pcf
Surcharge Pressure = 138.0 psf
SOIL SURCHARGE
Passive Lateral Pressure = 300 pcf
Base Friction = 0.40
Unit Weight of Soil 120 pcf
Tributary Length of Wall = 1.0,
Concrete Strength = 4000 psi
"";R
Column DL 0.0 k
Column LL 0.0 k
V�
15.0'
Wt. of Soil above Heel = 2.2 k A
Wt. of Wall = 0.9 k
�Ml- k -
Wt. of Footing 3.6 k
�z
F
uk
999.0 pIf 4.5' 0.83' 2.67' 350.0 plf 138.0 plf
8.00'
Wall ok Footing Toe -ok Footing Heel -
d 7.0" d = 32.0" d = 32.0"
VU = 1.09 k VU = 10.08 k Vu = 9.35 k
ovc = 7.92 k Oc = 36.43 k OVC = 36.43 k
MU = 5.87 ft-k MU = 22.69 ft-k Mu = 12.48 ft-k
FS Sliding ok FS Overturning ok
Sliding Resistance 3.3 k RM 20.4 ft-k 1.60
Sliding Force 3.1 k OTM 12.7 ft-k
SoilBearing ok
21.2 ft-k
X = = 3.13'
e = 0.87' < b/6 = 1.33'
If e < b/6, Then...
Aw Soil Bearing _ P + M = = 1 .40 ksf
Stress Leff A S
Soil Bearing _ P - M = = 0.29 ksf
Stress Right A S
P = D + L = 6.8 k A = 8.0 sf
M = Pe = 5.9 ft-k S = 10.7 ftA3
If e > b/6, Then..
Soil Bearing 2 P L
Stress 3 0.5*b e
2� 6.8 k 1. 1.44 ksf
3 � 4.0' 0.q87
width 9.39'
&-a
j=m`la. DCI -ENGINEERS
D'AMATO CONVERSANO INC. PROJECT NO: 05-11-263 SHEET NO:
PROJECT: Point Edwards Building #8 DATEi 12-20-2005
I
)UBJECT: South Retaining Wall - Tall Version Non -Seismic BY� JDB
Design Lateral Pressure = 35 pcf REFC-xEttce C-7
Surcharge Pressure = 75.0 psf SOIL SURCHARGE
Passive Lateral Pressure = 300 pcf
Base Friction = 0.40 4
Unit Weight of Soil 120 pcf
Tributary Length of Wall = 1.0,
Concrete Strength = 4000 psi
"M
Column DL 0.0 k
Column LL 0.0 k
15.01
Wt. of Soil above Heel = 6.4 k Ad
Wt. of Wall = 1.5 k
Wt. of Footing 7.2 k
N,
M,
4
1350.0 plf
6.5' 0.83,
4,67'
12.00'
Wall
ok
Footing Toe
d = 7.5"
d = 44.0"
-ok
VU =
1.06 k
VU =
15.61 k
ovc =
8.54 k
0c =
50.10 k
MU =
9.17 ft-k
Mu =
50.72 ft-k
FS Sliding ok
Sliding Resistance 6.6 k 1.24
Sliding Force 5.3 k
Soil Bearing ok
85.1 ft-k
X 5.62'
15.1 k
e = 0.38' <
b/6
= 2.00'
If e < b/6, Then...
Soil Bearing
P
M
_
�Mw
Stress Left
+
A
= =
S
1.50 ksf
Soil Bearing
P
M
_
Stress Right
-
A
= =
S
1.02 ksf
P = D+L
= 15.1 k A
= 12.0 sf
M = Pe =
5.7 ft-k
S
= 24.0 ftA3
542.5 plf 75.0 plf
Footing Heel
d = 44.0"
VU = 21.83 k
�Vc = 50.09 k
Mu = 50.98 ft-k
FS Overturning ok
RM
OTM
If e > b/6, Then
69.5 ft-k
30.7 ft-k 2.26
Soil Bearing 2 P L
Stress 3 0.5*b e
2 15.1 k 1.0' 1 .80 ksf
3 6.0' 0.38'
width 16.86'
FS Sliding ok
Sliding Resistance 6.6 k
Sliding Force
6.8 k
SoilBearing
ok
73.3 ft-k
X =
4.84'
15.1 k
e = 1.16' <
b/6 = 2.00'
If e < b/6, Then...
Soil Bearing _
P + m = =
1.99 ksf
low Stress Left
A S
00.53ksf
Soil Bearing _
P m ksf
- = =
Stress Right
A S
p = D+L
= 15.1 k A = 12.0 sf
M = Pe =
17.5 ft-k S = 24.0 ftA3
FS Overturning ok
RM 69.5 ft-k
0.98 OTM 42.5 ft-k 1.64
1�(A% C) ri GKOE Is IN PLAC-4 AHi3
L-lAt-L. IS 7-IEV TD 0-12-uclva-E
If e > b/6, Then
Soil Bearing 2 P L
Stress 3 0.5*b e
2 - 15.1 k 1.0' ksf
3 6.0' 1.16'
width 14.53'
Ma
j70w@'M'_ DCI -ENGINEERS
D'AMATO CONVERSANO INC. PROJECT NO: 05-11-263 SHEET NO:
PROJECT: Point Edwards Building #8 DATE: 12-20-2005
,UBJECT: Lvl 1 to Lvl 2 East West Wall Non -Seismic BY: JDB
Design Lateral Pressure
= 35 pcf
C-C6
Surcharge Pressure
= 75.0 psf
Passive Lateral Pressure
= 300 pcf
SOIL SURCHARGE
Base Friction
= 0.40
Unit Weight of Soil
= 120 pcf
k_,
T(ibutary Length of Wall
= 1.0,
Concrete Strength
= 4000 psi
Column DL
= 0.0 k
5j
Column LL
= 0.0 k
47
Wt. of Soil above Heel
= 3.1 k
Ad
Wt. of Wall
= 1.3 k
Wt. of Footing
= 3.6 k
999.0 Plf
4.5' 0.83'
2.67' 443.5 plf 75.0 plf
8.00,
Wall ok
Footing Toe
-ok Footing Heel
d = 7.5"
d = 32.0"
d = 32.0"
VU = 0.89 k
VU =
12.88 k Vu = 10.72 k
OVc = 8.54 k
Vc =
36.43 k Vc = 36.43 k
Mu = 6.48 ff-k
Mu =
28.99 ft-k Mu = 14.31 ft-k
FS Sliding . ok
FS Overturning ok
Sliding Resistance
3.6 k
RM 24.8 ft-k
Sliding Force
- 0.95
3.8 k
1.38
OTM 17.9 ft-k
Soil Bearing ok
01�-
- LVALL- IS KbT 13Acr-FILL03 fjAI'TIL_
DiAPAkA(_,H 0 14 PLACr_
23.4 ft-k
X 2.94'
L) 'S LA% -o tl- (1006 1 s I N 11 LAC�E
8.0 k
e = 1.06' <
b/6 =
1.33'
If e < b/6, Then...
Soil Bearing
P M
_
Stress Left
+
A S
=
1.79 ksf
00.20ksf
Soil Bearing
P M
_
Stress Right -
A - S
= = ksf
P = D+ L
= 8.0 k
A = 8.0 sf
M = Pe =
8.5 ft-k
S = 10.7 ftA3
If e > b/6, Then
Soil Bearing 2 P L
Stress 3 0.5*b e
2 8.0 k 1.0' 1 .81 ksf
3 4.0' 1.06'
width 8.8 1'
j7E'=0-M'_ DCI -ENGINEERS
D'AMATO CONVERSAN 0 INC. PROJECT NO: 05-11-263 SHEET NO: A-7
PROJECT: Point Edwards Building #8 DATE� 12-20-2005
-)UBJECT: Wall Below P1 at Corner Non -Seismic BY: JDB
Design Lateral Pressure = 35 pcf RE F C-
Surcharge Pressure = 75.0 psf
Passive Lateral Pressure = 300 pcf SOIL SURCHARGE
Base Friction 0.40
Unit Weight of Soil = 120 pcf
Tributary Length of Wall = 1.0,
Concrete Strength = 4000 psi
Column DL = 0.0 k
Column LL 0.0 k
15.0'
Wt. of Soil above Heel 4.7 k Ad
Wt. of Wall 1.2 k
Wt. of Footing 3.2 k
g"
1050.0 plf
2.08' 0.83'
4.09'
Aw�
Ltv-,,
7.00'
Wall ok
Footing Toe
d = 7.0"
d = 32.0"
-ok
VU = 0.88 k
VU =
9.11 k
ovc = 7.92 k
OVC =
36.43 k
Mu = 6.26 ft-k
M, =
9.47 ft-k
FS Sliding ok
Sliding Resistance
4.0 k
Sliding Force
3.7 k
SoilBearing ok
20.0 ft-k
X = = 2.2 1'
e = 1.29' >
b/6 = 1. 17'
If e < b/6, Then...
Soil Bearing
P M
_
Stress Leff
+ = =
A S
2.73 ksf
Soil Bearing
P M
_
Stress Right
- = =
A S
-0. 14 ksf
P = D+ L
= 9.1 k A
= 7.0 sf
M = Pe =
11. 7 ft-k S
= 8.2 ftA3
437.5 plf
75.0 plf
Footing Heel
d = 32.0"
Vu = 12.50 k
Vc = 36.43 k
Mu = 25.56 ft-k
FS Overturning ok
RM 22.3 ft-k
OTM 17.3 ft-k 1.29
If e > b/6, Then
Soil Bearing 2 P L
Stress 3 0.5*b e
2 9.1 k 1.0,
3� 3.5' 1.29'
width 6.62'
e = 1.12' >
b/6 = 0.67'
If e < b/6, Then...
If e > b/6, Then...
Soil Bearing
P m
Soil Bearing
2
P
L
Stress Left
= =
—A + S
2.41 ksf
Stress
3
0.5*b
e
Soil Bearing
P m
2
3.6 k
1.0-
Stress Right
- = =
A S
-0.61 ksf
-
3
2.0'
(2 71 DO
1.12'_ - 2.71 kst
P = D+ L
= 3.6 k A
= 4.0 sf
width
2.65'
M = Pe =
4.0 ft-k S
= 2.7 ftA3
e = 1.42' >
b/6 = 1. 17'
If e < b/6, Then...
If e > b/6, Then...
SoilBearing
P m
Soil Bearing
2
P
L
ow� Stress Left
—A + S
2.38 ksf
Stress
3
0.5*b
e
Soil Bearing
P m
2
7.5 k
1.0'
Stress Right
-
A S
-0.23 ksf
-
3
3.5'
1.42'
P = D+L
= 7.5 k A
= 7.0 sf
width
6.25'
M = Pe =
10.7 ft-k S
= 8.2 ftA3
C
,A
0
Point Edwards Building 8
December 19, 2005
DC1 Job # 5-11-263
WIND
LCULATIONS
SECTION B
-.9
ODCI-ENGINEERS
D'AMATO CONVERSANO INC.
Project
Subject
I-JINO &AL-c,�
L-il N 1�3 C-A L,(-(ILxn o m ON
Project No.
os-11- 2/,3
Sheet No.
�- I
Date
By jl)
L) tC CA-,'F- 6 0
�-J 131
HE-76W-z 5q
V4E L
T'D P D C, aAf 14 ku crl-- lf!7C-r k,t 1, (-7 VJE 2-0 C� N ERV.
H VT- F-7- 7-
0. 2-C
0.0 -Ls
2.0 PS F
.,-�N-rFeNAt- PRE3)0,�,!� C, cp; S�! (
J0
0,
L A44 -
9 0E
D&'rl6.rJ 6,41AX ekc-3�5u4c�
0
(6,q s o,5o
9,:5 N
7D-rAL- -<ue,FA-c�E- Ak-i�'Ar * ? p (
8 (5 q 2- s sn'JA -1 -7 v
VVVIN� .�04 LIP <<
LIJ k)L31- 60utvv F� Alvlf DJke(-(--)01J
mg-iADCI-ENGINEERS
D'AMATO CONVERSANO INC.
Project
pl- eD J?LOG
Subject
C-L-A'MQlr4(: 0006t'4
vsE Ac-lv,,�L- K-2, 1,1�
CA-
LIJPA(-C-S
L4
26 1 f, s F
qoDr-
r3 76 q E �. e ,
0 (,b
C)
ps
P, q �'— � , 0 1
Z) k %-�
L(
es r-
Project No.
,5 -15 -1 (- 2 62
L
Sheet No.
Date
12- - IS
By_10 D;
'ALL
bw 1 41, ^0, Pf INLK —,AS, UCN 7
ID "I'll 5C'LIND
sC Imj_5
--c
P"A
ToF 13 B,^
6' PVC IE W56 (IN -SO
nit \, *' , :: .1 - S
'v
Fr roF 10' DIP IE f. 'P (OUT -SS)
rNT
50LINL,
sc. W6375
CON UC T1 E4SEUE
S 7 ro
10- DIP IE 17.07 (IN-5)
;2: cup IE9tosj (PLI)Gorrm)
2. DIP fE 8.3o (OUT-"� SCALE: 1"= 30'
F ic 53 ON -NW)
ED
PROPOSED WA TER
6" 1E 12 15 Nul-NE)
EASEMENT
El; S�1,7 — — — — — - --- ---------- ;Za5i;�
Top 1.,.5,
7: Co'Z "' zli ("4-E) GARAGE FLOORS ZF755-6
7� COW Ir :�05 i'OVT-Nw)
211—l"11-5 * — '3�? -A , — DRAIN TO SE
11-P If loj (w) D.
'o, D" Ir 13 :5 (E)
cp 'r 290 w) CV: MISER -2 So ALL STORM DRAIN AND
D,- 'r ;.,:, 15) Is- CUP AF :8.99 ON-sw)
5 'Ivi-N) Is" CU- IE 27.98 (OUT-NL) TARy SEVAD? LINES AND SERVICES
0 DIP IE 25 PRIVAIE PROPERTY SIRALL BE
rx c8 VA 7E' AND SHALL BE MAINTAINED
_Top 4,5�9j
L,-. PV- ir 33 2r, 'Iw By THE HOMEOWER'S ASSMA77ON
is- cup IE 3, ,1 -sE) OR THE UKE,
71 iOU
is' CUP IE T-NE) -------- __5
F" un
E� -2*,f NOTE_- THE STA77C H)VRAULIC WATER
STAND- Y
2 E.6.STAND GRADE ELEVATION IS 325 FEET.
&6 u rpL BuILDING win uwmG UNITS BEL
1.11� - - - - - - - - - - - - - - izs 777`7_7�7,��_---:: EXEVA 77ON OFF 137 FUErE7 MAY W AN
DEVICE
------------
A PRESSURE REDUCING DEWCE
DOMES77C WATER SERWCE LWE
----- -- ------- AVOID WA TER PRESSURE 0 VER 80 P-T
< THIS MIOULD INCLUDE BUILDINGS I a,
--------- IDE AND THE AMENIT'Y BULDINa
- ------------------
- ---------
-----------
NOTE- THERE' SHALL BE A PUBLIC
Z, WATER EASEMENT THAT FOLLOWS THE
CENTERLINE OF THE LOOP ROAD AND
SPANS TO THE FLOKINE ON EITHER
SID61SHMrAlr ON SEKIER AND
o< 'o�
P
------------- TERS ?HAT FALL
WA
WTHIN THE EXTENWON OF THE ROAD
FLOPUNES SHALL BE INCLUDED WITHIN
THIS EASEMENT. WATER APPUR
THA T VffMD OU TSIDE TWS AREA SHALL
BE ENCOMPASSED WTtffN A 5' PUBLIC
--- ---- 14 - - - s , WA TER EASE14ENT PER WA TER -SERVICE
DETAIL SHErr 22.
F�
NOTE.- LOCATE WATER M IS DIRECTLY
BEHIND THE SIDEWALK
R ING
Nv, DEPENDING ON THE SITE' CONDITIaV.
CWCU
METERS SHAu Nor BE PLACED IN
---- ------------------- -- --- DRIVING SURFACES OR IN SIDEWALKS.
----------------
'SPRM ER
FIRE SERVICE LINE
NOM
4
A
---- ---- ZR7A4a 4914 CONTRACTOR To VERIFY SERWCE LINE
SIZE AND LOCATION OF BUILDING
E 1256137.�M
CONNECTION WTH SPRINKLER DESIGNER
7
PRIOR It) INSTALLING 7EES IN
----------------- I
IN SYSTEW. DESIGN N
WA TERMA
BLDG NO. 5 PPROVED BY
LIC
FN 0 _7F__
1 SANI
LPNRI A T,
7
BY 7,1
0, 7,1
WA
_Y
AN
0
,RJIR
ON THE
To
80 P.
S _a .
THE
7 AND
"HER
7' A D
T F ,
ROAD
V
AN
E S,
A
PUBLIC
SER,JCL
E' �12
SHALL BE
a THE arY PRIOR TO INSTALLATIaN.
LI/PI 84.17 ------------------- SUBMITTED AND A
L I/oPI 8217 PRC 14 5i OJ. N 297414.
e X LT 12 4 -z
9+94.84. 149' --- ---
_'7Q_TE' DOMES
,:4
LI/PI 86.17 1
'rFL,;j7v -------
METER AND
2' DOMESTIC WAZZ I w/ cavc atoamo CONTRACTOR VERIFY
w� 2-V-4' FZRE S-MAYGER SERVICE 92F AND LOCA770M OF
v.,_ I i", 52XVICE Iwr BUILDING
oryDNCV6. WIN I -,FW WrIDRAW ASSY j' CONNECTION M17H PLUMBER
RFa9A PER ary DM PER CITY DOG E7 1 1-4- W aE3VD (UJ) PRIOR To CONNEC77NG TV WATERMAIN
E 24' 4' FIRE smmiaER 3o, 8, pvc
ID AND E7.41 (�YP) IEF (m"v SERVICE LUC 0 a66% SYSTEAL DEVON CHANGES SHALL BE
EV, �,2�, 6' GATE VAL vE (FLOW) 9+74.96. 2aOD* LT
6,_"i 26.65' t T w/ Rc;- SUBMITTED AND APPROVED By 7w ary
_iigmi 1— /7- - cwc- ewaawc -- 5: - --p.Lv.-(e%LDc_p, ..
GOVCREr &OCXV
PW arY D*G E7.1
0
ANGE iL 1?2.9
V14' D I
"C - )-21.76 '
'0180O.-Ifi :�7 _R11A1
DDCVA
S_aOjOO
8+6297, ON
\&
-
1-4' RGV (FL.WJ)
BLDG NO. 8
L1/PI 111.67
,8+29, 1.� L ROAD 1
�00 DRIVEWA Y
W4 r "G
- OIL=
21 4�
11r 11�40.17 L;)WROA
11
8.29' L r 8_1E GCm
12- 7ZT (RL.—FL), (EMSM
E7 10 AAO E7. It
SERVICE LWE
9+212A 14.50'RT
A L V. (BLDC 0)
1.00 DRIVEWAY
==iT
6' (NEV
"GE a- 10145 - ---- -----------
W/ cola, PRIOR TO IN.
SWO
OV NOTE' IRRIGA77ON MEZERSeSWV
112, S,
8'1E 7084 CONTRACTOR TO OBTAIN ME7ER AND
HYDRANT A _j SER LINE 92E AND LOC,4n0JVS
I -FIRC Ssy. -Z FROM THE LANDSCAPE ARCHITECT PRIOR
PER CITY DOC E7.1
1-12',6* ME (FL01) TO CONNEC77NG TO WATERMAIN SYSTEM.
1- 12' ROY (FLWJ)
BLDG NO. 2
I - 12' ADAPTER (FL-UJ)
1-6* GATE vALw (n-vi) LI/PI 74.67
I/
rLA. E
g Ram *qmp
SHEET 23'_
NOME
KEY NA
N07 W SCALE
APPROVED:
CITY OF dOKDS DATE
CITY ENGINEER
02005 TRIAD ASSOCIATE
CL
cc
rx
Lu
rX
Z
%Nil
___ ; �klm _11
OLISTA V It 0SIERSAG" M
PROJM MANAGER
ROD HANWV, PLS
PKDJ= SuHvmR
MARK � REENIVES; PC
PROJEM KNGRM
THOMAS RMUST[W
��LQW�LARAW
FHW SUM9M DATE 7
SCAUL 8=2-- I-JO'
A. R
w I
STAMP NOT V
UNUM SIGNRD AJ
JOB NO. 01.
ISm NO. V
DC'l -ENGINEERS
D'AMATO CONVERSANO INC.
Project
Subject
Project No. Sheet No.
Date
By
gac-�a qt,&�
-2,o,345
K8
6.OG
09
0.10
0.2
,>I, 15
0 1 . 1
-�0(3 Z%-5
I I 1 1
17 22-5
1�,5 30
Mil
9-4
Ll
Lp
110
lb�
loz
I-) �
9H
C�O
-56 — Z
L4
39
34
Point Edwards Building 8
December 19, 2005
DC1 Job # 5-11-263
TA S MOD L
SECTION C
0
LVL Ll
Lvi- P1
5r- /Sm I C_
BAsE
�,Nvk 6 a
(ETA
ABS v8.5.6 - File: bIdg8 - Lower Seismic Base - 12-15-05 - December 15,2005 15:39
) View Point Loads (SOIL) - Kip -in Units
DCI Engineers
C-1
DCI Engineers
A
ETAB S
I— VL L
LIIL- P j
9,ASt'_I_
0(1
I
6-FA RS 3-0 r-�,��OCL VIOW
ETABS v8.5.6 File: bIdg8 - Lower Seismic Base - 12-15-05 December 15,2005 15:13
3-D View - Kip -in Units
DCI Engineers
ETABS
9 FF__
1. 0
TABS v8.5.6 - File: bldg8 - Lower Seismic Base - 12-15-05 December 15,2005 15:12
-D View - Kip -in Units
hy?" a0lit- k:Nft_nvIv_ I-%"%-
L vL- i )
LUt- P )
-- Se�lslLflc -13ASC-
E-f-A&S 3-D �W)CL II1IeL^)
DC1 Engineers
ETABS
ov�,
v
e ` W
v
BS v8.5.6 - File: bldg8 - Lower Seismic Base - 12-15-05 - December 15,2005 15:40
View Point Loads (SOIL) - Kip -in Units
1E T-A B 5
C-4
L-V (_ L
LX u f I
C-
L3 1615-�
DCI Engineers
0
0
ETABS v8.5.6 - File: bIdg8 - Lower Seismic Base - 12-15-05 - December 15,zuub I b:�5,j
Plan View - LVL Ll - Elevation 248.04 Point Loads (SOIL) - Kip -in Units
-at
19
Point Edwards Building 8
December 19, 2005
DC1 Job 5-11-263
LAT RAL
S,TA ILITY
SECTION D
0
.0
ODCI-ENGINEERS Project No. Sheet No.
.00m - I I - Z3
D'AMIATO CONVERSANO INC. 1�s
Project Date
Subject -�L� lh i L- Sf"U.IL-rr� C,H cqc_ By
01,67KAL4- 51-tLuc7\�A-411- 9TA-9)Liry'
f = 779 I�C- ( fEn, Se�-S-L- cAL-,z P& F -1 )
VUJ LDI r,4(i OLr goor
/ _,r
'p-s r
0000 w AL-.S
15
P-W-
pi 000 F-r-oOAJ
2-0
p 3
SO&
P T- SLA13
.5,06, - -5v ( IV 0 00 -1 -2 qD0 + do 7 1) � 13 2 L( r-
ROOF - /s ( 19 '7 --0 ) I I � ( 19 -7DO)
1-3 - -2,0 (11 600) IS (1-2 600)
L 2- 20 (19 00C.�) 15- (19000)
Ll V11- 6 �00c>�
10' WILI-S 12.!� 3 � 2 �- 2--) D 10'
9" /0 6
1-2 /50 6 0
4 P\LC-3 7s 232-) q' 7 U
C �4 L !r 6,�,o FT'b
60,j(-- S-liz-kll
(75D C-F� 00`4 C- e 60 C F -Z I 14'a + B 6 0 C,;- +
2 qLt(R Cr- -r- 2-Li 96 c-F glq c Z. 16o Cr ) /10 Z-Oql
CU LV AA M � 500 ?U=7 ( I �s) '? ?— ') 4
Ic 5zffs.AA(L 0 L,
70 -7 Ll 7
�5 n 0, (-T9 + -7,9 + 6 1 S S t 7-!,�C -3 -7 7 (PCX 4fAL4s
0
� 0
Win DCI -ENGINEERS
M D'AMATO CONVERSANO INC.
Project
Subject PT
'5bOL l_A-MSW_AL_
Project No.
zZ5 -it- 2( S
Sheet No.
Date
J Z - /S, -of
By j-O)l
el�r H r
7-)P NUNIA02 =: _h_ Q�_40E7 Tb 5Q/�a
9 oT N L,,,^A Ex— � r,/F'r Zl,)I(, OU
7,12
�, c -n v iE- F iz E�s un c ?_W 0') + 1-2,e (Z,2') t ?,72 (/-52.) + /, 0_(22)
PA&5JVL- K C_S� Q ILE '�4'(A�5) + 34(2,q) t 60 ( OS)
vr FRiunoA
t- 2-1 q 0 14.
t sl)-7 �,
0.6 D 4- o .-? C k H
0,60(0,Lfe.) qLf�?_ - 0,_1 (-?-7�) - -2�1,40 4 59-7 Fr- K or, &>U1LD)r-4C- i�Jli_L "UT-
SL.�OE'
TERRA ASSOCIATES, Ince
Consultants in Geotechnical Engineering, Geology
and
Environmental Earth Sciences
January 20, 2003
Project No� T-4893
Mr. Ross Woods
Point Edwards, LL. C
2801 Alaskan Way. 2utte 107
Z
Seattle, Washington 98121
Subject: Geolojically Hazardous Areas Review
Point FBwards Condominiums (UNOCAL Site)
Pine Street and Unoco Road
Edmonds, Washington
References: 1. Treliminary Geotechnical Report, UNOCAL Site, Project No. T-4893, prepared by
Terra Associates, Inc., dated November 21, 2001
I
2. Steep Slope Hazard Review, Poin,t.Edwards Condominiums (UNOCAL Site), Project No.
�!4893, prepared by Terra Associates, Inc., dated December 13, 2002
Dear Mr. Woods)
As requested, we have conducted a review of geologically hazardous areas for the Point Edwards Condonfiniums
site. The location of the site is shown on the attached Figure 1. Our scope of work included a. visual site
reconnaissance, the drilling of five test borings to depths ranging from about 31.5 feet to 61.5 feet below the
existing gr6und,surface, and.review of the referenced reports. Our study specifically addresses erosion hazards,
landslide hazards, and seismic hazards. We previously addressed steep slope hazards at the site. Our current
study includeslanalysis of slope stability along five profiles on the steep slopes located down1gradient. from. the
proposed develbpment. The results of these analyses are used to address potential steep slope hazards and
landslide, hazards.
APPLICANT COPY,
SITI?, CONDITIONS
The site is located on the upper portion of a predominantly north7facing hillside. The Preliminary Grading Plan
indicates elevationsk in the planned development area range from about Elev. 170 in the south-central portion to,
about Elev. 70 inithe northeastern portion.. The western and northern margins of the planned develo ment area
IN . . . . � p
are near the top of, a steep natural slope. The topographic information provided to us indicates the slope is
approximately 70 to 90 feet high, with inclinations ranging between about 50 and 80 percent. The areas beyond
the toe of the slope to the north-northwest are relatively flat. Burlington Northern- railroad tracks r . un along,the toe
of the slope to the, west.
RECEWED
12525 Willows Road, Suite 101, Kirkland, Washington 98034,
Phone (425) 821-7777 Fax (425) 821-4334
0 T 2
BUILDING DEPT.
Mr. Ross Woods
January 20, 2003
We did not observe indications of deep-seated instability; however, portions of the slope have been subjected to
shallow erosion and localized sloughing. These conditions are generally limited to. the forest duff and relatively
loose surficial soils mantling the underlying competent soils, and are commonly associated. with natural
weathering occurrences on steep slopes All of the erosional features we observed on the steep slope appear to be
a result of surface water -runoff and shallow interflow from areas above the slope crest.
We observed an area appToximately 100 to 125 feet southwest of Boring B- I where the top of the steep slope has
sloughed, exposing dense to very dense silty sand with gravel in a 7- to 8-foot high, near -Vertical face, just below
the crest of the steep slope. Based on,our observations, it appears that the sloughing at this location also occurred
as a result of concentrated surface water runoff and shallow interflow from areas above the slope crest. We
observed a very ligNt trickle of water flowing into this feature from the relatively flat upland above the slope.
Slope vegetation consists predominantly of young to mature deciduous trees and brush.
GEOLOGIC CONDITIONS
The Geologic Map of the Edmonds East and Part of the Edmonds West Quadrangles, Wtishington by James P.
Minard, 1983, sh6ws the soils at higher site elevations mapped as 'Vashon till, Vashon advance outwas ' h, and
Transitional beds. , Soils at lower site elevations are mapped as medium- to coarse -grained sand of the Whidbey
Formation. Transit , ional bed sediments are described by this publication as massive to. bedded clay, silt, and fine
to ve fine sand.
ry
Our recent test 6brings and the test pits performed as part of our referenced preliminary geotechnical study are
generally consistent with the descriptions of transitional bed deposits. The soils we observed on and immediately
above the steep Islope areas generally consist of silty sand, sandy silts, and laminated to massive, very. dense silt
and/or hard clay ; Native soils observed in the five test borings drilled near the top. of the steep slopes generally
consist of densAo very dense fine-grained silty sand to sand with.silt and very stiff clay/dense silt. The silt and
�A
clay generally appeared massive, with occasional very thin partings of very fine sand.
I
The native soils are generally moist below a depth of about five feet. We observed wet soils to a depth of about
ten feet in Bo; B-S. We did not observe indications of significant groundwater seepage on the slope; however,
g
we observed wet surficial soils in one, isolated area near the top of the steep slope, west of the proposed
development. 'The wet. conditions at this location appear to be from surface runoff from areas above the too of the
steep slope, add.possibly from seasonal. perched groundwater emerging near the top of the slope.
.we also observed'a very light flow of water along the axis of several of the erosional channels running down the
steep slope. The water.we observed in the erosional features flows on top of dense to very dense native soils
exposed on the gpund surface or beneath approximately 4 to 12, inches of duff and topsoil. The source of .the
water in the erosiprial features appears to be surface runoff from areas above the crest of the steep slope.
Detailed descriptions of the subsurface conditions encountered in the test pits.,and test borhigs are presented on the
attached test pit logs and boring logs. The approximate locations. of the test pits and borings are shown on the
attached Figure 2.
Project No. T-4893
Page No. 2
Mr. Ross Woods
January 20, 2003
GEOLOGICALLY HAZARDOUS AREAS
Section 20.15B.060 (A)(3) of the City of Edmonds Community Development Code (ECDC) defines geologically
hazardous areas as those areas subject to potential erosion, landslide, and/or potential seismic instabilities,
including the following:
Erosion Hazard Areas
Section 20.15B.060 (A)(3)(a) of the ECDC defines erosion hazard areas (EHAs) as those areas containing soils
that may experience severe to very severe erosion hazard. These soils include, but are not limited to, the
following when they,occur on slopes of 15 percent or greater:
1. Alderwood. soils (15 to 25 percent slopes)
2.. Alderwood-Everett Series (25 to 70 percent slopes)
3. Everett Serie) 15 to 25 percent slopes)
The Soil Conservation Service (SCS) has mapped the site soils as Alderwood-Urbdn land complex, 2 to 8 percent
.slopes, and Kitsap!silt loam, 8 to 25 percent slopes, in the upper southern portion of the site, and Alderwood-
Everett gravelly sandy loam, 25 to 70 percent slopes, in the area of the former tank farm and the steep slope below
the tank farm area. -The soils we observed in the test pits generally conform w ith the SCS mapping; however,
some of the very dense silt and hard clay we observed in the former tank areas would better correlate with Kitsap
silt loam 25 to 50 percent slopes, due to existing man-made slope gradients.
The erosion hazards for soils classified as Alderwood-Urban land complex, 2 to 8 percent slopes, and Kitsap silt
loam 8 to 25 percent slopes, are classified as slight and moderate, respectively, and do not fall under the
classification ofan erosion hazard area. Aiderwood-Everett gravelly sandy loam, 25 to, 70 percent slopes, is
classified as having a moderate to high erosion hazard. The erosion hazard for soils classified as Kitsap silt loam,
25 to 50 percerivs lopes, is considered high.
Based on the cn'*teria presented above, the portions of the site that are. sloped at inclinations greater than 15 percent
and are -underlain by Alderwood-Everett gravelly sandy loam would.be' considered an EHA. Areas underlain by
Kitsap silt loam that are inclined at a gradient steeper than 25 percent would also be considered EHA's. Based. on
observations, the vast majority of the*site located downgradient from Pine Street would be considered an EHA.
EHAs, based on the SCS mapping, are shown on the attached Figure 3.
We did not observe indications of significant active erosion in the planned development area; however, the. soils
will'be susceptible to erosion when exposed during construction. ln,our opinion, Best Management Practices
(BMPS) used.during construction, will provide adequate mitigation of the erosion hazard at the site. If the erosion
control measures � are properly implemented and- maintained, along with temporary and permanent drainage
improvements,. it is our opinion that the planned development will not Adversely impact the erosion potential for
the site or adjacent, properties. All erosion and sediment control BMPs should conform to City of Edmonds
requirements.
Project No. T4893
Page No. 3
J
Mr. Ross Woods
January 20, 2003
Landslide Hazard Areas
Section 20.15B.060 (A)(3)(b) of the ECDC define's landslide hazard areas (LHAs) as those areasW the city of
Edmonds which, by reason of excessively steep slopes, unsatisfactory foundation support, stability, or
topography, have a risk of earth subsidence and landslide hazard in excess of normal allowances. The ECDC
specifies field criteria for identifying LHAs. We used these criteria, listed below, in,our evaluation of LHAs at
the subject site.
1. Any area with slopes of 15 percent or greater, and impermeable- soils (typically silt, and clay) frequently
interbedded with granular soils (predominantly sand and gravel) and springs or groundwater seepage.
2. Any area tha't includes areas with significant visible evidence of groundwater seepage,. and which also
includes existing landslide deposits, regardless of slopes.
3. Any Area thathas shown movement during the Holocene epoch (from 10,000. years ago to present) or is
underlain by mass wastage debris of that epoch, as determined by a qualified geologist or geotechnical
engineer.
4. Any area potentially unstable as a result of rapid stream incision or stream bank erosion.
5. Any area 16cated on an alluvial fan presently subject to, or-potentiaUy subject to, inundation by debris
flow or deposition of stream -transported sediments.
During our site visit, we did not observe on -site indications of deep-seated instability, springs, or significant
groundwater seepage on the steep slopes. As,discussed, we Pbserved relatively shallow erosional features and
localized shallo17 'slou - ghing at isolated locations on the steep slope located below the proposed development.
Because shallow ground. movements are associated with these erosional features, and considering that near -
surface interflow likely contributed to the soil loss, these areas would be considered LHAs pursuant to Items I
and 3. All of the LHAs we identified at the site ekist on the steep slope hazard area (SSHA) (slope inclinations
greater than 40 percent) located west of Buildings 5, 6, and 7.
Stability Analysis
We performed our stability analyses using the computer. program WINSTABL. The soil parameters used are
shown on the attached analysis plots and output text. These paradieters are based on field and laboratory data,
and our past experience with similar soils. Analyses of the slope -were performed -along five section lines
identified on the attached Figure 2 as Section A -A' through Section E-E'. . Our analyses, of these sections
considered both static and pseudostatic (seismic) conditions for the existing. slopes, and for proposed grading with
associated building loads at grade. This analysis is conservative, considering the buildings located near the top of
the steep slope will be partially or coinpletely supported by deep foundations. A horizontal acceleration of 0.20g
was used in the pseudlostatic analysis to.simulate slope performance under earthquake loadin
.9
Project No. T-4893
PageNo. 4
PrJ
Mr. Ross Woods
January 20, 2003
The lowest safety factors for ea6h condition are presented in the following table:
Section Analyzed
Minimum Safety Factors
Static
Pseudostatic
Section A -A' existing
1.72
1.18
Section A -A' proposed
1.79
1.21
Section B-11'existing
2.09
1.42
Section B-B' proposed
1.56
1.16
Section C-C' existing
2.32
1.53
Section C-C' proposed
1.67
1.26
Section D-D' existing
1.88
1.24
Section D-D' proposed
2.03
1.33
Section E-E' existing
.1.72
1.15
Section. E-V*proposed
1.60
1.26
The results of the stability analyses indicate that existing and proposed slopes are stable with respect to deep-
seated failure under static conditions. The existing and proposed slopes are indicated to be stable to marginally
stable under sevete seismic loading conditions.
Potential impacts to the LHAs due to construction of the buildings and proposed yard grading include increasing
the potential for erosion on and/or adjacent to the slope by exposing. -soils during grading and allowing surface
runoff to flow onto the steep slope, and impacts to slope stability from building surcharges.
In our opinion, potential erosion and sedimentation impacts to the LHAs due to the planned building locations and
yard grading will be eliminiited or significantly reduced by applying BMPs for erosion prevention sedimentation
containment.
A.sdiscussed ab&e, analysis indicates the existing and proposed slope conditions are stable with regard to deep-
seated failure. . In our opinion, supporting building toads with a deep foundation system will further reduce
potential impacts to the stability of the steep slopes due to building surcharges, and mitigate the landslide hazard.
A deep foundation system will at ' so eliminate the potential of adverse impacts to the stability of the buildings in
the event of shallow soil loss adjacent to the buildings. Additionally, drainage systems associated - with the
fi_nished buildings will improve the current stability of the steep s . I I ope.
Seismic Hazard Areas
Section 20.15B.060 (A)(3)(d) of the ECDC defines seisnuc hazard areas as those areas subject to severe risk of
earthquake damage' as a result of seismically induced landslides, earth adjustments, settlement, or soil
liquefaction.
Based. on the soil and groundwater conditions.we observed in our on -site explorations, and the results of our
stability analysis, it is our opinion that the risk for severe damage resulting from seismically induced landstides,
earth adjustments, and settlement is low. It is also our . opinion that the risk for Ii . faction to occur in potential
que
building areas at this site is negligible. Therefore, in our opinion, seismic. hazard areas do not exist on'the subject
site.
Project No., T-4893
Page No. 5
Mr. Ross Woods
January 20, 2003
DISCUSSION
Section 20.15B. 110 (B) of the ECDC (Development Standards — Erosion.Hazard Areas) states that alterations
within identified EHAs will not be authorized without an approved erosion control plan pursuant to Chapter 18.30
ECDC. A licensed engineer will prepare a site -specific erosion control *plan conforming to the requirements of
Chapter 18.30 ECDC.
Section 20.15B. 110 (C) of the ECDC (Development Standards. — Landslide Hazard Areas) states that LHAs
located on slopes greater than 40 percent shall be regulated pursuant to Section 20.15B. 110 (D) of the ECDC
(Development Standards = Steep Slope Hazard Areas). As discussed, the LHAs we identified at the site exist on
the SSHA (slope inclinations greater than 40 percent) located -west of Buildings 5, 6, and 7. We previously
addressed SSHAs in the referenced report. In the SSRA report, we opined that existing site conditions and
applicable project components generally meet the provisions for a. SSRA exemption detailed in Section
20.15B. I 10(1))(2)(a — g). Specifically, this exemption would apply to encroachment into SSHAs by proposed
Buildings 5 and 6, yard grading associated with Buildings 2 and 6, and encroachment into the buffer within about
5 feet of the SSHA by Building 7 and its associated yard grading, We. also opined that a reduction in the buffer
from 50 feet to 10 feet will have no significant impact on the SSHA or adjacent'slopes.
In our opinion, the subsurface information and analytical results presented herein support the findings presented
in our SSHA report, and the request for a SSHA exemption and. buffer reduction.
We trust the information presented is -sufficient for your current needs. If you have any questions or require
additional information, please call.
Sincerely yours,
TERRA ASSOCIATES, I C.
/'0' 1
Encl: M�:Winity Map
E X210
ration Location Plan
Erosion Nazard Area/Soils Map
Vigure 4 — Pqils Classification System
Figures 5 through 9 — Boring Logs
Figures 10 through 18 =Test Pit Logs
WINSTABL Output Data
cc: Mr. Greg Krabbe, Triad Associates
Mr. Richard E. Gifford
Mr. S. Jin Lee, Weber+Tho
mpson
Project No. T-4893
Page No. 6
FHF24' is,'
KITT
PK 187TH
rL Sw 18 IT Sw
ism ST S�
A
MTN 5 yd
ej WE. PL ST �w ST Sw
OiEml ST
"w
13
I
FUtM e
KL
w a
196
ft"T p
MELOOY LN wy
_'v
jf�t
W"NERE KI cm .
DR
C 9;
EMNO-5
J &%MXK
. 1�
kSPEiS ST
ST
K
8
-ATEXWAFrR _
PARK
ST Sw
A 9
LANDIAG
fif4a I A
GUN
Mg
N: 8
IT
HILL PK
ELL- J51 ST .'e
e %-I
AAIN I Iff Is ST_
IL
MRIM
23.
WON
OIL
Sw
sp;= -
SITE
ZISIH ST
V4
RMARDS FAKIM A
pr BENN ?17TH zz
Sw
_q 218TH ST
30,-
ST co Sw a
66D V;
zz
X
REFERENCE: Thomas Guide, King/Pierce/Snohomish Counties, 1999, Page 454 NOT TO SCALE
Terra
VICINITY MAP
POINT EDWARDS CONDOMINIUMS
Associates Inc.
EDM . ONDS, WASHINGTON
Consultants in Geotechnical Nineenng
Geollog
ntay and
Environme Earth Sciences
Proj. No. T -4893
Date JAN 2003
Figure 1
I
A
----------
9TEEP SLOPE
b
HAZARD �ANEA
--------------
------------
------------
B
----------
------------
�-- -- - --------
TP-5
7z
BLDG 6
-----------------
7/
Al.
BLDG 7
. . . . . . . . �K K-K-
TP 8!t
r
lir owns u
::7
NIUE:
THIS SITE PLAN IS SCHEMATIC. ALL LOCATIONS AND L EdEN , D:
DIMENSI.ONS ARE APPROXIMATE. IT IS INTENDED FOR
REFERENCE ONLY AND SHOULD NOT BE USED FOR NTllp-l;APPR'OXtMATE LOCATION OF TEST PIT
'Terra
DESIGN OR CONSTRUCTION PURPOSES. tj
APPROXIMATE LOCATION OFI BORING,
Atsoc
REFERENCE:
STEEP SLOPE HAZARD AREA go"ConWitants In G
SITE PLAN PROVIDED BY TRIAD ASSOCIATES G60
Environme
'\\x
--------------
---- - --------
STEEP SLOPE
HAZARD AREA
—14
W* TPA 5
t:$LWUU
TP-1 b
tt7 4j'
2
6�0iio"j
X
Q 300
APPROXIMATEscALE IN FEET
LL) LLJ
tip
_j
CL
LLJ'
in
V
W
I �
. NN-
LLJ LAj
LL
_j
V)
A41,
LLJ
4
YT
V)
�K
q
A.
V,
11
I%*
%;
q,
N
..........
E
GO
Cj
CL70
7a E *
8 U-)
>
C�
4)
-a co
<
�>
UJ :DO
0_0
o o
c
0
Lum
2
w
5:�
W_ C,4
_j
cc
00
Z X
U_
<,,o
0) — U_
z W� 0
0 2uj
P: LLJ CO
ui
co w
co
0
0
< Z CL
X
U)
LLI'
M
:D CL
0 Z
0
w 00.
=a: 0
(13
(n CL
.
w
Lu
zwz.z
0..
5;
0
:5<..o
0 LU (L)
, LU
x
a- Z c.) cc
POZO
a-
z
v3w z
V5 z cr- (D
Lu
IX
W
5
a.
Ju(/)_UjLU._
U. W
ww
w 0
W
I
.z
. Ix
co
i,L
MAJOR DIVISIONS
LETTER
SYMBOL
TYPICAL DESCRIPTION
Clean
GW
Well -graded gravels, gravel -sand mixtures, little or no
GRAVELS
Gravels
fines.
G.P
Poorly -graded gravels, gravel -sand mixtures, little or
U) a)
(less than
0
More than
5% fines)
no fines.
GM
Silty gravels, gravel -sand -silt mixtures, non -plastic
50% of coarse
a) >
fraction is
larger than No.
Gravels
fines.
GC
Clayey gravels, gravel -sand -clay mixtures, plastic fines.
W — 1)
z ca L
E f
4 sieve
with fines
<
CD
—
-� C:)
0 N
Clean
SW
Well -graded sands, gravelly sands, little or no fines.
u')
6
SANDS
Sands
SP
Poody-graded sands or gravelly sands, little or no
W CZ
U) (a
(less than
Cc -r-
� C:
More than
5% fines)
fines.
co
< a).r_
5 0% of coarse
—
0 0"
fraction is
SM
Silty sands, sand -silt mixtures, non -plastic fines.
0
smaller than
Sands
SC
Clayey sands, sand -clay mixtures, plastic fines.
No. 4 sieve
with fines
ML
Inorganic silts, rock flour, clayey silts with slight
U)
§ILTS AND CLAYS
plasticity.
CL
Inorganic clays of low to medium plasticity, (lean clay).
_j
0 CM
U)
E 6
Liquid limit is less than 50%
0 o Z N
W
0 L
Organic silts and organic clays of low plasticity.
0 C:
Z Lo ca a)
<
MH
Inorganic silts, elastic.
Cl)
SILTS AND CLAYS
as
CH
Inorganic clays of high plasticity, fat clays.
W
E
Z 0 (n
2
Liquid limit is greater than 50%
ILL
OH
Organic clays of high plasticity.
HIGHLY ORGANIC SOILS
PT
Peat.
DEFINITION OF TERMS AND SYMBOLS
U)
U)
Standard Penetration
Density Resistance in Blows/Foot
2* OUTSIDE DIAMETER SPLIT
W
SPOON SAMPLER
z
0
Very loose 0-4
2.4" INSIDE DIAMETER RING SAMPLER
U)
Loose 4-10
OR SHELBY TUBE SAMPLER
W
Medium dense 10-30
X
Dense 30-50
Y WATER LEVEL (DATE)
0
Very dense >50
Tr TORVANE READINGS, tsf
Pp PENETROMETER READING� tsf
Standard Penetration
Consistenc Resistance in Blows/Foot
DD DRY DENSITY, pounds per cubic foot
W
>
U)
Very soft 0-2
LL LIQUID LIMIT, percent
W
Soft 2-4
X
Medium stiff 4-8
PI PLASTIC INDEX
0
stiff 8-16
Very stiff 16-32
N STANDARD PENETRATION, blows per foot
Hard >32
Terra
UNIFIED SOIL CLASSIFICATION SYSTEM
Associates, Inc.
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Proj. No. T-4893
I Dat e JAN 2003
F Figure 4
Geology and
Enviionmental Earth Sciences
Boring No. B-1
Logged by: JCS
Date: 12/13/02 Approximate Elev. 110
Soil Description
Consistency/
Relative
Density
Depth
CL
E
W
U)
(N)
Blows/
ft.
Moisture
Content
N
Grayish -brown silty SAND, fine grained, with occasional
fine gravel. (SM)
Medium
Dense
29
12
Occasional rusty brown stained partings.
-------------------------------------------------------- ----------------- -------------------------
Dense
—10
43
14'
Light brown SILT with sand, fine grained, moist, slightly
mottled. (ML)
------------------------------------------------------------------------- ------------------------
Dense
42
21
Mottled light brown silty SAND to sandy SILT, fine
grained, moist to wet. (SM/MQ
Dense
—20
-
:�E
38
23
Light gray silty SAND to sandy SILT, fine.grained, moist,
with occasional fine qravel. (SM/M�) ----------------
---------
Very
Dense
---------------
60
18
Grayish-brown SAND with silt, fine to medium grained,
moist, with'occasional fine gravel. (SP-SM)
Very
Dense
—30
82
8
Grayish -brown SAND with silt to silty SAND, fine grained,
moist. (&-SM/SM)
Very
Dense
:E
58
15
(Grayish, -.brown hard, moist SILT between 35.5 and 36.0
-
feet)
Light gray silty SAND to SAND with silt, fine grained,
Very
—40
:E
75
10
moist. (SM/SP-SM)
Dense
-
Trace of gravel.
Very
Dense
:E
80
8
Very
Dense
50'
58
6
-------------------------------------------------------------------------
Brownish-gray SAND with silt to silty SAND, fine grained
moist. (SP-SWSM) With a trace of fine black organic
inclusions.
------------ 7 -----------
Very
Dense
82
10
No fine organic inclusions.
Very Dense
F
86
8
Boring terminated at 60 feet.
No significant groundwater encountered.
Terra
Associates, Inc.
BORING LOG
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environmental'Eadh Sciences
Proj. No. T-4893TDate
JAN. 2003
Figure 5
Boring No. B-2
Logged by: JCS
Date: 12/13/02 Approximate Elev. 90
Consistency/
-a
(N)
Moisture
Soil Description
Relative
Depth
E
Blows/
Content
Density
(ft..)
U12
ft.
N
FILL- gray sandy silt, fine grained, moist, with occasional
Loose
5
8
24
fine gravel.
FILL: brown organic silty sand to sandy silt and bluish-
Loose
—10
4
12
gray silty sand, fine grained, moist to wet.
With organics.
Loose
—15
6
10
Very
—20
3
27
Loose
Bluish -gray to light brown SAND with silt to silty SAND,
Medium
—25
20
13
fine grained, moist. (SP-SM/SP)
Dense
--------------------------------------------------------------------------------------------------
Mottled gray sandy SILT, fine grained, moist. (ML)
Medium
-
—30
23
20
--------------------------------------------------------------------------------------------------
Dense
-
-
Gray SAND to SAND with silt, fine grained, moist.
Medium
—35
27
(SP/SP-SM)
Dense
Dense
—40
36
8
Boring terminated at 41.5 feet.
No significant groundwater encountered.
Terra
BORING. LOG
ASSO ci.ates, inc..
POINT EDWARDS CONDOMINIUMS
'
EDMONDS, WASHINGTON
consultants in Geotechnical Engineering
Geology and
Environmental Ear.ffi Sciences
Proj. No. T-4893TDate
JAN 2003
Figure 6
Boring
No. B-3
Logged by: DPL
Date: 12/16/02
Approximate
Elev. 76
Soil Description
Consistency/
Relative
Depth
off
(N)
Blows/
Moisture
Content
Density
ft.
N
Possible FILL: gray sand to silty sand, fine grained, wet,
wiih occasional fine gravel.
Possible FILL: grayish -brown silty sand, fine grained, wet,
---- slight -mottling --------------------------------------------------------------
Medium
Dense ----------
5
11
19
Gray silty SAND, fine grained, moist. (SM)
Dense
—10
31
22
Gray silty SAND to sandy SILT, fine grained, moist.
Dense
—15
36
20
(SM/ML)
---------------------------------------------------------------------------------------------------
-
Grayish-brown SAND with silt, fine grained, dry to moist.
(SP-SM)
Very
Dense
—20.
68
4
Very
Dense
—25
53
5
Grayish- brown SAND, fine grained, dry to moist. (SP)
Very
Dense
30
T_
51
I
5
Boring terminated at 31.5 feet.
Minor groundwater perched at 7 feet.
Terra
BORING LOG.
Assoc i4tes jnc.
POINT EDWARDS- CONDOMINIUMS
EDMONS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environment I al Earth Sciences
Fproi- No. T-4893—IDate
JAN, 2003 1
Figure 7
-I
Boring No. B-4
Logged by: DPL
Date: 12/16/02 Approximate Elev. 90
Soil Description
Consistency/
Relative
Density
Depth
(ft.)
CL
E
(z
co
(N)
Blows/
ft.
Moisture
Content
N
FILL (Old test pit): bluish -gray silty sand, fine grained,
Loose
wet, with a trace of wood particles. Appears disturbed.
7
27
FILL (Old test pit): mottled brown silty sand, fine grained, moist.
Medium
Dense
10
T
17
21
31
FILL (Old test pit): brown silt and clay, moist, with a trace
anic material.
wn R�q�
Very
stiff
7
Bluish -gray SILT to CLAY, low to medium plasticity.
Very
17
28
(MUCL)
stiff
Gray SILT to CLAY, moist, low to mediu . rn plasticity.
(MUCL)
--------------------------------------------------------------------------
Very
stiff
-------------------------
—20
-
30
23
LL 35.5
PI 11.5
Grayish-brown sandy SILT to clayey SILT, fine grained,
moist. (ML) With thin partings of iron -stained, fine- grained
Very
stiff
35
23
sand.
Grayish -brown clayey SILT to silty CLAY, moist. (MUCL)
With thin discontinuous lenses of gray to mottled gray
____�iq"�ained -sand
Very
stiff
—30
30
24
Gray s illy SAND, fine grained, moist. (SM)
Dense
37
15
-----------------------------------------------------------------------------------------------
Gray sandy SILT to clayey SILT, fine grained, moist, low
plasticity. (IVIL to MUCL)
Hard
—40
34
17
Gray clayey SILT, moist, low plasticity. (MUCL)
---- lulgOing-g-rained- sand -------------------------------------------------------------------
Hard
37
20
Gray sandy SILT to silty SAND, fine grained,. moist,
(MUSM)
Dense .-50
32
19
47
18
—60
42
15
Boring terminated at 61.5 feet.
No significant groundwater encountered.
Terra
BORING LOG
Associates, Inc.
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
Proj. No. T-4893
-
FDate JAN 2003
-
Figure 8
Boring No. B-5
Logoed by: DPL
Date: 12/16/02 Approximate Elev. 105
Soil Description
Consistency/
Relative
Depth
W
-a
E
(N)
Blows/
Moisture
Content
Density
(ft.)
C1011
ft.
N
Brown to grayish -brown silty SAND, fine grained, wet,
with faintrnottling. (SM)
------------------------------------------------------------------------- -------------------------
Medium
Dense
:E
19
Gray SILT, medium to high plasticity, moist. (MH)
stiff
—10
13
---------------------------------------------------------------------------------------------------
Gray CLAY and SILT, low plasticity, moist. (CUML)
Very
stiff
:E
25
.26
-
40
--------------------------------------------------------------------------------------------------
Gray silty SAND, fine grained, moist to wet. (SM)
-----------------------------------------------------------------------------------
Dense
--------
—20
-
31
26
Gray CLAY, low plasticity, moist. (CL)
Very
:E
22
27
stiff
42
Gray CLAY, low plasticity, moist. (CL)
Very
—30
22
25
stiff
Gray sandy SILT to silty SAND, fine grained, moist.
(MUSM),
Dense
:E
46
.25
-------------------------------------------------------------------------
Dense
------------------------
—40
-
43
15
Gray sandy SILT to clayey SILT, non -plastic, moist.
(M L to MUCL)
------------------ 7 --------------------------------------------------------------------------------
Dense
31
20
Gray sandy SILT to silty SAND, fine g*rained, dry to moist.
Dense
—50
46
18
Moist to wet.
----------------------------------------------------------------------------------
Medium
Dense
--------
-
28
20'
Brown silty SAND, fine grained, moist. (SM)'
Very
Dense
60
:E
64
13
Boring terminated at 60.5 feet.
No significant groundwater encountered.
Terra
BORING LOG
Associates, Inc.
POINT EDWARDS CONDOMINIUMS'
EDMONDS, WASHINGTON..
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
Proj. No. T-4893
Date JAN 2003,
Figure 9
Logged by: JCS
Date: 10/18/01
Depth
0 FILL: crus
61
10
15
20
�-ogged by: JCS
-Date: 10/18/01
Depth
0— FILL: crus
moist. 4-i
Brown si
5
10
15
Test Pit No. TP-1
Approximate Elev. 104
Moisture
Soil Description Content
hed rock surfacing over brown to gray silty sand to sandy silt, fine grained,
firm, moist. ( WML)
Rusty brown silty SAND fine grained, medium dense, moist, with occasional fine
Gray to mottled gray silty SAND, fine grained, medium dense, to dense,
moist, with occasional fine gravel. (SM)
Becomes light brown at approximately 6 feet.
Gray CLAY, hard, moist, massive. (CL)
26
Pp 4.5+
tons/W
LL 35�8
P, 15.
Test pit terminated at 14 feet.
No groundwater seepage.
Test Pit No. TP'2
Approximate Elev. 124
Moisture
Content
Soil Description (%)
hed rock surfacinp over brown silty sand to sandy silt, fine grained, firm,
nch thick organic ayer at base. (SM/ML) (Old topsoil horizon)
Ity SAND, fine grained, medium dense, moist. (SM)
Mottled grayish -brown silty SAND, fine grained, medium dense, moist.
20
(SM)
Grayish -brown silty SAND, fine grained, medium dense to dense, moist.
(SM)
Gray CLAY, hard, -moist, laminated with light gray silt partings�. (CL)
p 4.5t
tons/fe
37
Test pit terminated at 14 feet.
No groundwater seepage.
20
TEST PIT LOGS.
-CONDOMINIUMS
Terra POINT EDWARDS
A EDMONDS, WASHINGTON
ssociates, Inc.
Geotechnical Consultants
Proj. No.7-4893 Date JAN. 9003 Figure 10
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0— ;:11 1 a h,
5
10
15
20
Test Pit No. TP-3
Approximate Elev. 121
Moistu re
Soil Description Content
own silty sand, fine grained, firm, moist, with occasional fine
gravel and organic material. ( SM) (Hydrocarbon odor)
Dark brown organic silty SAND, fine grained, soft, moist to Wet. (OL)
,�(Old
topsoil horizon)
15
Tan to light gray silty CLAY to clayey SILT, hard, moist. (CUML)
(Hydrocarbon odor)
Gray CLAY, hard, moist, laminated with partings of light gray silt and gray
fine sand. (CL)
Pp 4.5+
32
tons/fe
Test pit terminated at 13 feet.
Light groundwater seepage from point source at 4.5 feet.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0
5
10
15
K41
Test Pit No. TP-4
Soil Description
Approximate Elev. 92
Moisture
Content
FILL: light brown silty sand, fine grained, firm, dry to moist. (SM) 2-inch thick
organic layer at base. (Old topsoil horizon)
Light brown to tan silty SAND, fine grained, medium dense to dense, dry.
(SM)
Mottled grayish -brown silty SAND, fine grained, medium dense to dense,
29
moist. (SM)
LL = 42.7
Light grayish -brown to light brown CLAY and SILT, hard, moist, laminated
'29
P1 = 19.7
with partings of dark gray fine sand. (CUML)
Pp =4.5+
tonsite
Gray CLAY, hard, moist. (CL)
Pp 4 ' 5+
�29
1 tons/fe.—
Test pit terminated at 13 feet.
Trace groundwater seepage at 6 feet.
Terra
Associates, Inc.
Geotechnical Consultants
TEST PIT LOGS.
-POINT E.DWARDS.CONDOMIN.IUMS
EDMONDS, - WASHINGTON
Proj. No. T-4803 Date, JAN 2003 Figure, 11:
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
61
IN
15
Test Pit No. TP-5
Approximate Elev. 11. 0
Moisture
Soil Description Content
6 inches DUFF and -TOPSOIL.
Light brown SAND with silt to silty SAND, fine grained, medium dense,
moist. (SP-SM/SM)
2�
Mottled grayish -brown SAND to SAND with silt, fine grained', medium
dense to dense, moist. (SPjSP-SM)
Becomes wet at approximately 9 feet.
26
34
LL = 44.5
-
Grayish -brown to gray CLAY, hard, moist, generally massive, with
Rl = 21.3
-
occasional thin laminations of gray silt. (CL)
Pp = 4.5+
'tons/fe
-
Test pit terminated at 16 feet.
-
Light groundwater seepage between 9 and 10 feet.
20—
Logged by: JCS
,.p4te: 10/18/01
Depth
R)
0—
FILL: br
10
15
20
Test Pit No. TP-6
Approximate Elev. 150
Moisture
Soil Description Content
own to grayish -brown SILT, CLAY, and fine grained SAND, firm
moist to wet, with'some fine gravel and occasional. organic material.
32
FILL: gray to brownish gray silt, clay, and fine grained sand, firm, moist to
-
wet, with rnoderate organic material (including wood debris) and some
-
gravel. 12-inch thick organic layer. at base. (Oldtopsoiffibrizon)
bray sifty SAND to sandy SILT, fine grained, dense, moist,
with occasional fine to coarse gravel. (SM/ML) (Glacial till -like)
Test pit terminated at 16 feet.
No groundwater seepage.
TEST PIT LOGS
EDWARDS CONDOMINIUMS
Terra.
POINT
EDMONDS, WASHINGTON
Associates, Inc.
Geotechnical Consultants
Proj., No. T-4893 Date JAN 2003 Figure 12
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
5
10
15
20
Test Pit No. TP-7
Approximate Elev. 121
Moisture
Soil Description Content
M
FILL: dark brown organic silty sand, fine grained, firm, moist.
Mottled gray to brown SAND with silt to silty SAND, fine grained, medium
dense to dense, moist. (SP-SM/SM) (Hydrocarbon odor)
20
Tan to light grayish -brown silty CLAY to CLAY, hard, moist, occasional
24
mottling. (CL)
Pp - 4.5+
tons/ft'
31
Test pit terminated at 15 feet.
No groundwater seepage.
Logged by: JCS
D�a-tia: 10/ 18/01
Depth
(k)
0 -
FILL: lig
ic
15
20
Test Pit No. TP-8
Approximate Elev. 121
Moisture
Content
Soil Description
ht brown to gray silty sand, firm, Moist to Wet, with organics.
FILL: dark brown organic silty sand, loose, wet, with significant wood
debris (timbe and branches). 2.5-foot diameter boulder.
—7
bray SILT to SILT with sand, fine grained, dense, moist to wet. (ML)
25
-
7-
Light grayish -brown to tan sandy SILT, fine grained', very'dense, moist,
-
with occasional fine gravel. (ML) (Glacial,till-like)
16
-
Test -pit terminated at 15 feet.
-
Light groundwater seepage at 6 feet.
TEST PIT LOGS
Terra POINT EDWARDS CONDOMINIUMS
EDMONDSj, WASHINGTON
Associates, 1O.C.
Geotechnical Consultants
.1 Date JAN 2003=Figuire 13
Proi. No. T-4893
Test Pit No. TP-9
Logged by: JCS
Date: 10/18/01
Depth
(ft)
0-
5
101
20
Soil Description
Approximate Elev. 150
Moisture
Content
M
-
FILL: crushed rock surfacing over grayish -brown sandy silt and clay, firm,
-
moist. 6-inch thick organic layer at base. (Old topsoil horizon)
Mottled grayish -brown sandy SILT to sandy CLAY, stiff, moist. (MUCL)
Pp 4.5+
30
tons/te
37
Grayish -brown CLAY, hard, moist, massive. (CH)
LL = 58.8
P1 = 30.1
Gray SILT and CLAY, hard, moist, with occasional laminations of gray
Pp = 4.5+
I sand. (ML/CL)
ine'
22
tons/W
Test pit terminated at 15 feet.
No groundwater seepage.
Lodged by: JCS
R
-Da'te': 10/18/01
Depth
(ft.)
0
5
10
15
20
Test No. TP-1 0
Approximate Elev. 157
Moisture
Content
Soil Description (%)
6 inches DUFF and TOPSOIL.
Brown sandy SILT, fine grained', medium dense, rnoist. (ML)
Grayish -brown SILT and.CLAY, hard, moist. (MUCL)
Pp 4.5+
tons/ft'
34
Pray SXT�and CLAY, hard, moist. (MUCL)
-
Test'pit terminated at 15. feet.
-
No groundwater.seepage.
TEST PIT LOGS
Terra POINT EDWAPIDS CONDOMINIUMS
EDMONDS, WASHINGTON
Associates, Inc.
Geotechnical Consultants
-4893 a
Proi. No. T D 200 4
Test Pit No. TP-1 1
Lo' ' Y: JCS
D atTl Ol 18/01
"Depth
(ft.)
0
110
0
ed by: JCS
tb- 10/18/0 1
e th
U
5
1 C
.20
Soil Description
Approximate Elev. 78
Moisture
Content
7
-
-Mottled grayish -.brown SAND to SAND with silt, fine grained, medium
dense, moist to wet. (SP/SP-SM)
25
15.
Ught brown silty SAND to sandy SILT, fine grained, medium dense to
dense, moist. (SM/ML) Increasing silt with depth.
15
22
-
Test pit terminated at 15 feet.
-
No groundwater seepage.
Test Pit No. TP-1 2
Approximate Elev. 76
Moisture
Content
Soil Description (%)
-
6.inches crushed rock surfacing.
Mottled 1. ra ish-brown*SAND, fine t6 medium grained, medium dense, moist, with
g y
-
I
occasion ne gravel. (SP) (Hydrocarbon odor)
Gray SAND with silt to SAND, fine grained, medium dense to dense,
17
moist to, wet, with occasional"fine to coarse gravel. (SP-SWSP)
15
Mottled gray*!s,h-brown silty SAN[� with gravel to . sandy SILT with gravel,
fine.sand, find gravel, dense to very,dense, moist. (SWML)
(Glacial tillmlike between 8 and 10 feet) Increasing gravel with depth.
20
Test pit terminated at, 15 feet.
Trace groundwater seepage at 8.*feet.
TEST PIT LOGS
Term POINT. EDWARDS CONDOMINIUMS
Associates' Inc. EDMONDS,. WASHINGTON
Geotechnical Consultants
Proj. No. T-4893 Date JAN 2010 15'
Logged by: JCS
bate: 10/18/01
Depth
. (ft.)
0 — V), in�h.
5
10
15
2�O
-Logged by: JCS
-.'Date: 10/18/01
413lepth
01
5
1 C
20
Test Pit No. TP-1 3
Approximate Elov. 86
Moisture
Content
Soil Description . (%)
s crushed rock surfacing.
Mottled grayish -brown sifty SAND to sandy_ SILT, very dense, moist. (SM/ML)
(Hydrocarbon odor)
25
31
7
Bluish -gray CLAY, hard, moist, with partings of gray fine sand and light
gray silt. (CL)
Pp 4.5+
tons/ft'
Test pit terminated at 14 feet.
Trace groundwater seepage at 2.5 feet.
Test. Pit No. TP-14
Approximate Elev. 76
Moisture
Content
Soil Description (%)
FILL: bluish -gray silty sand with gravel to sandy silt with gravel, fine sand,
fine gravel, medium dense to dense, moist. (SM/ML)
10
Light b to wn sandy SILT, fine grained, dense, moist, with occasional
fine gravel and thin layers of fine grained silty sand. (ML)
19
15
-
Test pit terminated At 15-feet.
-
No groundwater seepage.
TEST PIT LOGS,
-------- - ------
Terra. POINT EDWARDS CONDOMINIUMS
-Associates, Inc. EDIVIONDS, WASHINGTON
qeotechnical Consultants —
Proj. No. T-4893 Date JAN 20031 Figure 16
10
%
Test Pit No. TP-1.5
Logged. by: JCS
Date: 10/18/01
Depth
(ft.) - -
0— FILL:' sis
�p
.10
Soil Description
Approximate Elev. 86
Moisture
Content
M)
W and t sandy silt,
gray, 0 fine grained, medium.dense, moist, with occasional
(1
fine g . WIVIL)
rave
Dark brown organic sandy SILT, fine grained, firm, moist, with occasional roots. (OL)
(Old topsoil horizon)
Mottled grayish -brown silty SAND with gravel to. SAND with silt and gravel,
Ifine sand, fine to coarse gravel, medium dense to dense, moist.
10
(SM/SP-SM)
Becomes brownish -gray and moist to wet at approximately 8.fee.t.
Brownish -gray silty SAND with gravel to sandy SILT with gravel, fine sand,
fine gravel, dense, moist. (SWIVIL) (Glacial till -like)
18.
Test pit terminated at 15 feet.
Trace groundwater seepage at 11 feet.
-L6jged by: JCS
lb�te: 10/18/01
U
5
10
15
0
Test Pit No. TP-1 6,
Approximate Elev. 68
Moisture
Content
Soil Description I I(%)
FILL: gray, to brown silty sand with gravel, fine grained, firm to loose,
moist to wet. (SM)
FILL: grayish -brown silty sand with gravel, fine grained, firm, moist to wet,
with significant organic soils and wood debris.
23
16
Bluis3ay silty SAND with grqvel to sandy SILT with gravel, fine sand, fine gravel,
dense most. (SM/ML) (Glacial till -like)
Light brown SAND, fine grained, medium dense.to dense, moist. (SP)
15
1
Test pit terminated at 13 feet.
No groundwater seepage.
Tbrra
Assobiatos, Inc.
Geotechnical Consultants
TEST PIT. LOGS
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON,
Proj.. No. T�-4893 Date JAN 2003 Figure 17
J
Test Pit No. TP-1 7
Logged by: JCS Approximate Elev. 82
Date-.10/18/01
Moisture
Depth.
Content
Soil Description N
0- =brown silty SA No with gravel, fine sand, fine to coarse gravel,
m dense. * moist. (SIVI)
M a ' sh-brown silty SAND with gravel, tine sand, fine to coarse gravel,
rh=grenyse to dense, moist. (SM) 13
Grayish brown silty SAND with gravel to sandy SILT with gravel, fine sand,
5 �fine to coarse gravel, dense'to very dense, moist. (SWIVIL)
I (Glacial till -like) Sand content increases with depth.
10-i
Test pit terminated at 9.5 feet.
No groundwater seepage.
15'
TEST. PIT LOGS
Terra,
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Ass*ociates, Inc..
Geotechnical Consultants
PrQj. No� T-4893. Date JAN 2003 Figure 1.8.
V
ir
1-1... � . ' --- - - -vp;fi- , --- - --i -- -
uz� n
PRELIMINARY GEOTECHNICAL REPORT
UNOCAL Site
�4 �',
Pine Street and Chinook Road
Edmonds, Washington
Project.No. T-4893
- , Nv""�
Terra Associates, Inc.
Prepared for:
Triad Point Edwards
Seattle, Washington
November 21, 2001
cff�ffp�ILE RECEIVED
OCT 2
Nib
�f -4- A ?W --'L _3 �661, Jffbt LA
"REET FILE
-77;
TERRA ASSOCIATES, Inc.
Consultants in Geotechnical Engineering, Geology
and
Environmental Earth Sciences
November 21, 2001
Project�No. T-4893
Mr. Ross Woods
Triad Point Edwards
2801 Alaskan Way, Suite 107
Seattle, Washington 98121
Subject: Preliminary Geotechnical Report
UNOCAL Site
Pine Street and Chinook Road
Edmonds, Washington
Dear Mr. Woods:
As requested, we have conducted a preliminary geotechnical engineering study for. the subject project. The
attached report presents our findings and recommendations for the geotechnical aspects -of project design and
construction.
Our field exploration indicates that the site is generally underlain by medium dense to very dense native sand,.
silty sand, sandy silt, and laminated to massive, very dense silt and/or hard clay. Fill has been placed at locations
across the site in thicknesses ranging from about I to 12 feet., The consistency of the' fill soil is variable, but
generally appears to have been derived from the on -site soils. Much of the fill we observed contained organic
material and/or debris. We observed light seepage of perched groundwater in several test pits at depths ranging
from about 2.5 to 11.0 feet below the ground surface.
In our opinion, the subsurface conditions at the site are suitable for the proposed development of the property. In
general, conventional spread footings may be used for supporting the buildings bearing oi i undisturbed native soil
or compacted structural fill. The slopes on the site are generally stable, and the stability is not expected to be
affected by the proposed development. The uncontrolled fill encountered on the site w,ill not be Suitable for
directly supporting structural loads or pavements. Concep tual plans f6r development indicate sign ificant ciits in
the uphill part of the site, adjacent to Pine Str eet. These excavations will most likely need to be provided with
temporary support during construction.
12525 Willows Road, Suite. 101, Kirklan ' d, Washington 98034
Phone (425) 821-7777 * Fax (425) 821-4334-
Mr. Ross Woods
November 21, 2001
Once project plans have been finalized, we will conduct additional detailed analyses to evaluate impacts on slope
stability and prepare final recommendations for the geotechnical aspects of site development.
We trust the information presented is sufficient for your current needs. If you have any questions or require
additional information, please call.
Sincerely yours,
TERRA ASSOCIATES, INC.
110 1/0)
Project No. T-4893
Page No. ii
TABLE OF CONTENTS
Pa,ge No.
1.0
Project Description ........................................................................................................... 1
2.0
Scope of Work ................................................................................................................ 1
3.0
Site Conditions ............................................................................................................... 2
3.1 Surface ............................................................................................................... 2
3.2 Soils .......................................................... ...... 3
3.3 Groundwater ........................................................................................................ 3
4.0
Geologic Hazards ............................................................................................................. 4
4.1 Erosion ................................................................................................................ 4
4.2 Steep Slope ................................................................................... ** ..... * ...... 4
4.3 Landslide ........................................................................................................... 5
4.4 Seisn-dc .................................................................................................................
5
5.0
Discussion and Preliminary Recommendations ............................................... ; ............. 5
5.1 General ..................................................... 7 ........................................................ 5
5.2 Site Preparation and Grading ............................................................................ 6
5.3 Excavations .................. : ..................................................................................... 7
5.4 Foundations ........................................................................................................ 8
5.5 Basement and Retaining Walls ........................................................................... 9
5.6 Slab -on -Grade Floors ........................................................... ..........................
10
5.7 Drainage ..........................................................................................................
10
5.8 Utilities .............................................................................................................
I I
5.9 Pavements ...........................................................................................................
11
6.0
Additional Services .......................................................................................................
11
7.0
Limitations .....................................................................................................................
12
Figures
Vicinity Map .......................................... ................. Figure I
* ... *** ..........
Exploration Location Plan .................................................................................................. Figure 2
General Slope Fill Detail ........................................................................................................ Figure 3
Appendil
Field Exploration and Laboratory Testing ..................................................................... Appendix A
Preliminary Geotechnical Report
UNOCAL Site
Pine Street and Chinook Road
. Edmonds, Washington
1.0 PROJECT DESCRIPTION
We understand the project will consist of a residential development. Detailed building and site development
plans are currently not available. However, a preliminary site plan by GGLO indicates the development will
consist of 15 multi -unit buildings. We understand that the buildings will be three to four stories, with daylight
basements and attached garages. We expect that the buildings will be wood -framed, with lower floors
constructed at grade. We expect structural loads will be about five to seven kips per linear foot for continuous
bearing walls. Column loads may be on the order of 200 kips.
Our review of an unreferenced preliminary grading plan, dated February 20, 200 indicates that the planned site
development will require extensive grading with cuts and fills up to about 20 and 30 feet, respectively. In
addition, it appears that ternporary construction cuts up to about 20 feet will be required along the downgradient
side of Pine Street. Proposed permanent cut and fill slopes are shown with an inclination of 2:1
(Horizontal: Vertical).
The recommendations contained in the following sections of this report are preliminary and are based on the
conceptual.information described above. We should review design drawings as they become available in order to
supplement or amend our recommendations, as required.
2.0 SCOPE OF WORK
On October 18 and 19, 2001, we excavated 17 test pits to depths ranging from 9.5 to 16.0 feet below existing
surface grades. In addition, we reviewed existing subsurface information from previous environmental studies at
the site to augment the. information obtained in our subsurfice investigation. Using this subsurface 'information,
we performed analyses to develop prelimina
ry geotechnical recommendations for project design and
construction. Specifically, this report addresses the following:
Soil and groundwater conditions
Geologic hazards and site stability
Site preparation and.grading
Excavations
Foundations
November 21, 2001
Project No. T-4893
0 Basement and retaining walls
0 Slab -on -grade floors
0 Drainage
Utilities
9 Pavements
3.0 SITE CONDITIONS
3.1 � Surface
The project site is the approximately 15-acre upper yard area of the UNOCAL Edmonds Bulk Fuel Terminal
located approximately between Unoco Road and Pine Street in Edmonds, Washington. The upper yard area was
formerly used as a tank farm having 23 aboveground storage tanks (ASTs). All of the tanks and associated
aboveground piping had been removed prior to our field investigation. The approximate location of the site is
shown on the Vicinity Map, Figure 1.
The site is situated on the upper portion of a predominantly north -facing hillside. An undated site plan by Triad
Associates indicates elevations in the planned development area range from about Elev. 170 in the south-central
portion to about Elev. 70 in the northeastern portion. Surface grades at the site have been significantly altered for
siting fuel tanks. In general,*the fuel tanks were constructed on large excavations cut into the hillside. The cut
slopes are typically 15 to 20 feet in height with inclinations of about 60 to 70 percent. The downgradient sides of
several tank areas are enclosed by a containment,berm. constructed of fill. The heights of the berms are about 6 to
12 feet above the bottom of the tank excavation. We observed a tar -like coating covering the surface of the
berins and most of the interior slopes of -the. tank areas.
The western and northern margins of the planned development area are near the top of a steep natural slope. The
topographic information provided to us indicates the. slope is approximately 70 to 90. feet high, with inclination's
ranging between about 50 and 80 percent. The areas beyond the toe of the slope to the north-northwest are
relatively flat UNOCAL yard and. parking areas. Burlington Northern railroad tracks run along the toe of the
slope to the west. Portions of the slope have been subjected to shallow erosion and localized sloughing; however,
we did not observe indications of deep-seated instability. Slope vegetation consists predominantly of young to
mature deciduous trees'and brush.
The portion of the site located south of Pine Street is undeveloped forest except at the western end, which is
occupied by two small buildings located within a fenced enclosure. This portion of the site slopes down to the
north and northeast at grades of about 20 to 25 percent. Vegetation consists of predominantly of,mature
coniferous and deciduous trees and brush undergrowth.
Page No. 2
November 21, 2001
Project No. T4893
3.2 Soils
The native soils encountered in the test pits consist of medium dense to very dense native sand, silty sand, sandy
silt, and laminated to massive, very dense silt and/or hard clay. The soils we observed in the test pits are
generally consistent with those described in the environinental studies performed at the site by others. We
encountered the very dense silt/hard clay underlying the medium dense to dense sand, silty sand, and sandy silt in
eight of the test pits at depths ranging from about 2.5 to 10.0 feet below the ground surface. Test Pits TP- 11, TP-
12, and TP-14 through TP-17 all terminated in medium dense to very dense sand, silty sand, or sandy silt. These
test pits are all located at lower elevations in the northeastern to eastern portion.of the site. The very dense silty
sand and sandy silt occasionally contained fine gravel and appeared glacial till -like.
We observed fill overlying the native soils in I I of the 17 test pits. The fill soils consist primarily of loose to
firm silty sand, sandy silt, silt, and clay, with varying amounts of organic material and debris. The thickness of
the fill is generally less than about three feet; however, we observed fills of 12 and I I feet in Test Pits TP-6 and
TP-16, respectively. Test Pit TP-6 was located on a berm between two large tank excavations. Test Pit TP-16
was located on the nor-theast4acing slope, below the two large tank areas in the eastern portion of the site. In
general, we observed the original topsoil horizon beneath the fill soils.
The'Geologic Map of the Edmonds East and Part of the Edmonds West Quadrangles, Washington by James P.
Minard, 1983, shows the soils at higher site elevations mapped as Vashon till, Vashon advance outwash, and
Transitional beds. Soils at lowe'r,site elevations are mapped as medium- to coarse -grained sand of the Whidbey
Formation. Transitional bed sediments are described by this publication as massive to bedded clay, silt, and fine
to very fine sand. The soils encountered in the test pits are generally consistent with the descriptions of
transitional bed deposits.
Detailed descriptions of the subsurface conditions encountered in the test pits are presented on the Test Pit Logs
in Appendix A. The approximate test pit locations are shown on Figure 2.
3.3 Groundwater
We encountered light groundwater seepage in 7 of the 17 test pits at depths ranging between about 2.5 and 11.0
feet. The seepage was generally perched on the very dense silt/hard clay, or on the dense to very dense glacial
till -like silty sand/sandy silt.
The groundwater conditions described above are typical for sites underlain by relatively impermeable materials,
such as glacial till and glacially consolidated silts and clays. Surface water will infiltrate through the upper sandy
or weathered soils and become perched on the underl ing, relatively impermeable material. When combined
Yi
with a positive gradient, the groundwater will flow laterally along this contact, emerging at lower. elevations as
seeps and springs. Perched groundwater levels and flow rates will fluctuate seasonally and typically reach their
highest levels during and shortly following the wet winter months (October through May). We did not observe
indications of significant groundwater seepage on the site slopes.
Page No. 3
November 21, 2001
Project No. T-4893
4.0 GEOLOGIC HAZARDS
4.1 Erosion
The Soil Conservation Service (SCS) has mapped the site soils as Alderwood-Urban land complex, 2 to 8 percent
slopes and Kitsap silt loam, 8 to 2.5 percent slopes in the upper southern portion of the site, and Alderwood-
Everett gravelly sandy loams, 25 to 70 percent slopes in.the area of the former tank farm 'and the steep slope
below the tank farm area. The soils we observed in the test pit generally conform with the SCS mapping;
however, the very dense silt and hard clay observed in the former tank areas would better correlate with Ki tsap
silt loam, 25 to 50 percent slopes. The erosion hazards for soils classified as Alderwbod- Urban land complex, 2
to 8 percent slopes and Kitsap silt loam, 8 to 25 percent slopes are classified as slight and moderate, respectively.
Alderwood-Everett gravelly sandy loams, 25 to 70 percent slopes is classified as having a moderate to high
erosion hazard. The erosion hazard for soils classified as Kitsop silt loam, 25 to -50 percent slopes is considered
high.
The City of Edmonds defines erosion hazard areas as those areas containing soils that may experience severe to
very severe erosion hazard. These soils include, but are not limited to, the fol lowing when they occur on slopes
of 15 percent or greater:
i. Alderwood soils (15 to 25 percent slopes)
ii. Alderwood-Everett Series (25 to 70 percent slopes)
iii. Everett Series (15 to 25 percent slopes)
Based on the SCS mapping, much of the site would be considered an erosion hazard area. We did not oibserve
indications of significant active erosion in the planned development area; however, the soils will be susceptible to
erosion when exposed during construction. Best Management Practices (BMPs) must be used during
construction to rmitigate the erosion hazard. If the erosion control measures are properly implemented and
maintained, it is our opinion that the planned development.will not adversely impact the erosion potential for the
site or adjacent properties. All erosion and sediment control BMPs should conform to City of Edmonds
requirements.
4.2 Steep Slope
The City of Edmonds defines steep slope hazard areas as any ground that rises at an inclination of 40 percent or
more within a vertical elevatiort change of at least 20 feet. Based on this definition and the topographic
information provided to us, the.steep slope located below the development area and the cut slopes on the uphill
side of several of the tank areas are considered steep slope hazard areas.
The steep slopes located within the former tank farm area will be graded to inclinations of 2:1 or flatter. -It does
not appear that -site grading will directly impact the steep slope located below the western and northern portions
of the development area. We will evaluate potential impacts regarding the steep slope hazard areas once final
site grading *information is developed.
Page No. 4
November 21, 2001
Project No. T-4803
4.3 Landslide
The City of Edmonds defines landslide hazard areas as. follows:
Any area with slopes of 15 percent or greater and impermeable soils (typically silt and clay) frequently
interbedded with granular soils (predominantly sand and gravel) and springs or groundwater.
Any area that includes areas with significant visible evidence of groundwater seepage, which also
includes existing landslide deposits, regardless of slopes.
Any area that has shown movement during the Holocene epoch (from 10,000 years ago to,present), or is
underlain by mass wastage debris of that epoch, as determined by a qualified geologist or geotechnical
engineer.
4. Any area potentially unstable as a result of rapid stream incision or stream bank erosion.
5. Any area located on an alluvial fan, presently subject to or potentially subject to, inundation by debris
flow or deposition of stream -transported sediments.
Based on our observations of site soil. conditions and the above definition, many of the site slopes would be
.considered landslide hazard areas. We expect that the steep slopes located below, the western and northern
portions of the development area would also be considered a landslide hazard area due to soil conditions. Based
on our field observations, it does not appear that the site slopes have been subjected to deep-seated instability.
An evaluation of potential impacts of development and any necessary mitigation will be made after the site
development plans have been finalized. These evaluations will include additional subsurface exploration by deep
test borings in areas of deep excavations and near the top of the slope.
4.4 Seismic
The Puget Sound area falls within Seismic Zone 3, as classified by the 1997 Uniform Building Code (UBQ).
Based on the soil conditions encountered in our test pits and described in the environmental report by others, a
soil profile type of Sc, from Table 16-J of the 1997 LTBC, should be used in design.
Liquefaction is a phenomenon where there is a reduction or complete loss of soil strength due to an increase in
water pressure induce ' d by vibrations. Liquefaction mainly affects geologically recent deposits of fine-grained
sands that are below the groundwater table. Based on the soil and groundwater conditions we encountered, it is
our opinion that the risk for liquefaction to occur in potential building areas at this site is negligible.
5.0 DISCUSSION AND PRELIMINARY RECOMMEENDATIONS
5.1 General
Based on our *Study, it is bur opinion that the site is suitable for the proposed development. Buildings can be
supported on conventional spread footings bearing on competent native soils below the'surficial topsoil layer
and/or uncontrolled fill, or on structural fill placed and compacted on the competent native soils. Floor slabs and
pavements can be similarly supported.
Page No. 5
a
November 21, 2001
Project No. T4893
The.uncontrolled fill encountered should not be considered suitable for directly supporting foundations or slab -
on -grade floors. The existing fill we observed in the northeastern portion of the site is at least I I feet thick in
locations, contains a significant amount of organic material, and does not appear to have been placed in a
controlled manner on a properly prepared- subgrade. To reduce the potential of unacceptable differential
settlements of the structures and to avoid impacting the stability of the fill slope in this portion of the site, we
recommend transferring building loads to competent native soils beneath the fill using deep foundations. In our
opinion, a foundation system consisting of augercast piles or drilled piers will provide an economical and suitable
building support system. Removing the uncontrolled fill and replacing it with an engineered structural fill pad is
an alternative to using a. deep foundation system. Because of uncertainties in the consistency of the fill, there are
risks that cannot be quantified associated with constructing pavements over the existing fill. Therefore, the
existing fill soils should also be removed from pavement areas and replaced with structural fill. -
Much of the ex isting*fill soils observed at the site will not be suitable for reuse as structural fill because of
excessive organic material, and debris. The native silty sands, silts, and clays are moisture sensitive and will be
difficult to compact as structural fill when too wet. The ability to use the soils from site excavation as structural
fill will depend on the soils' moisture content and the prevailing weather conditions at the time of construction.
If grading activities will take place during the winter season, the owner should be prepared to import free -
draining granular material for use as structural fill and backfill.
The following recommendations should be incorporated into the project design drawings and construction
specifications. These recommendations are preliminary and may be altered or augmented upon review of the
final plans.
5.2 Site PreDatation and Grading
To prepare the site for construction, all vegetation, organic surface soils, and other unsuitable materials including
the existing fills should be stripped and removed from the portions of the site to be developed.
Once clearing and grubbing operations are complete, cuts and fills -can be made to establish design grades. Prior
to placing fill, we recommend proofrolling all exposed surfaces to detennine if any isolated soft and yielding
areas are present. Cut areas that will provide direct support for new construction- should also be proofrolled-. if
excessively yielding areas are observed and cannot be stabilized in place by compaction, they should be cut to a
firm bearing surface and filled to grade with structural fill. If the depth of excavation to remove unstable soils is
excessive, you can consider using a geotextile fabric, such as Mirafi 50OX or equivalent, in conjunction with
structural fill to limit the depth of removal, In general, a minimum of 18 inches of a clean granular structural fill
pl aced over the geotextile fabric should establish a stable bearing surface. A representative of Terra Associates,
Inc., should observe all proofrolling. operations at the time of construction to verify stable subgrades.
Excavations up to about 20 feet below the existing ground surface are proposed along the northern side of Pine
Street in the southern portion of the site. Based on our observations, and considering, the time of year our
investigation was performed, it does not appear that significant drainage efforts will be required to complete the
excavation as proposed. However, this should be verified by. field observations at the time of construction.
Page No. 6
a
4
November 21, 2001
Project No. T-4893
Most of the granular site soils contain a moderate percentage of fines (silt and clay particles), which will make
them sensitive to moisture. The use of silt and clay soils as structural fill may be possible during dry weather.
However, it will be extremely difficult to control their moisture content and to place and compact them
satisfactorily. Some of the site soils are wet and will require drying to reduce their moisture content and facilitate
compaction. Drying can be accomplished by aeration during dry weather conditions or by the use of an additive
such as cement IdIn dust or Portland cement.
If fill activities must take place during wet weather or on a wet subgrade, the owner should be prepared to use
wet weather structural fill. For -this purpose, we recommend using a granular soil that meets the following
grading requirements:
U.S. Sieve Size
Percent Passing
3 inches
100
No. 4
75 maximum
No. 200
-5 maximum*
*Based on the 3/4-inch fraction.
Prior to use, Terra Associates, Inc. should examine and test all on -site or imported materials proposed for use as
structural fill.
Structural fill should be placed in uniform loose layers . not exceeding 12 inches, and then compacted to a
minimum of 95 percent of the soil's maximum dry density, as determined by ASTM Test Designation D-698
(Standard Proctor). The moisture content of the soil at the time of compaction- should be within two percent of its
optimum, as determined by this same standard. In -non-structural areas or for backfill in utility trenches below a,
depth of 4 feet, the degree of compaction could be reduced to 90 percent.
Embankment fills placed on slopes exceeding a grade of 20 percent must be keyed and benched into competent
native soils. A general slope fill detail is shown.on Figure 3. Subsurface drains may also be required. The need for
subsurfice drains should be evaluated in the field at the time of constiuction. The proposed fill areas should be
stripped of topsoil, duff, existing fill soils, and soils containing organic material prior to creating horizontal benches
for the placement of the fill. All pen-nanent cut and fill slopes should be graded with a finished inclination no
greater than 2: 1. Upon completion of grading, the slope face should be appropriately vegetated or provided with
other physical means to guard against erosion. Final grades at the top of the slope must promote surface drainage
away from the slope crest.
5.3 Excavations
All excavations at the site associated with confined spaces, such as utility trenches and lower building levels,
must be completed in accordance with local, State, or Federal requirements. Based on curr ent Occupational
Safety and Health Administration (OSHA) regulations, the upper medium dense to dense granular soils would be
classified as Group C soils. The very dense silt and hard clay soils fall into the Group A category.
Page No. 7
November 21, 2001
Project No. T-4893
Accordingly, for temporary excavations more than 4 feet and less than 20 feet deep, side slopes in Group C soils
should be laid back at a minimurn slope inclination of 1.5:1. Temporary slopes in the Group A soils can be
completed with a gradient of 0.75: 1. If there is insufficient room to complete the excavations in this manner, or if
excavations greater than 20 feet deep are planned, tempo rary shoring may need to be used to support the
excavations. The above information is provided solely for the benefit of the owner and other design consultants
and should not be construed to imply that Terra Associates, Inc. assumes responsibility for Job site safety. Job
site safety is the sole responsibility of the project contractor.
Based on the grading information provided to us, it appears that portions of the temporary excavation along the
northern side of Pine Street will require shoring. We recommend using a cantilevered, soldier pile and timber
lagging shoring system. We will provide design parameters for temporary shoring once more details are known
regarding final site grading.
5.4 Foundations
Spread Footings
The b ' uildings may be supported on conventional spread.footing foundations bearing on competent native soils or
on structural fill placed above competent native soils, as recommended in the Site Preparation. and Grading
section of this report. Perimeter foundations should be placed at least 1.5 feet below final exterior grades for
frost protection. Interior foundations can be constructed at any convenient depth.
On a preliminary basis, foundations can be dimensioned for a net allowable bearing capacity of 3,000 pounds per
square foot (psf) where supported by the medium dense to dense native soils and compact I ed structural fill.
Foundations supported by.the very dense silt and hard clay soils can be dimensioned for a net allowable bearing
capacity of 5,000 psf. For short-term loads, such as wind and seismic, a one-third increase in this allowable
capacity can be used.
With structural loading as anticipated and these bearing stresses applied, estimated total settlements.are about one
inch, with one-half to three -fourth inches differential in nature. These settlements should be immediate in nature,
occurring during and shortly following application -of building loads.
For designing foundations to resist lateral loads, a base friction coefficient of 0.4 can be used. Passive earth
pressures acting on the side of the footing and buried portion of the foundation stem, wall can- also be considered.
We recommend calculating this lateral resistance using an equivalent fluid weight of 300 pounds per cubic foot
(Pcf). We recommend not including the upper 12 inches of soil in this computation because it can be affected by
weather or disturbed by future grading activity. This value assumes'the foundation will be constructed neat
against competent native soil or backfilled with st ructural fill, as described in the Site Preparation and Grading
section of this report. The recommended friction and passive values include a safety factor of 1.5.
Page No. 8
0
November 21, 2001
Project No. T-4893
Drilled Piles
Where footing elevations cannot be readily lowered to the competent native soil, we recommend supporting.
building, wall, and floor loads on augercast piles or drilled pier foundations that penetrate a minimum of five feet
intothe native bearing stratum. Allowable axial and lateral pile capacities for varying pile diameters are as
follows:
Pile Diameter
(inches)
Allowable Axial Load
(to as)
Allowable Lateral Load
(tong
16
30
4
18
35
5
The above allowable axial capacities include a safety factor of 2.0. Full single -pile capacities can be used,
provided pile spacing is at least three pile diameters. For closer spacing, there will be a slight reduction in the
allowable single -pile capacity due to group effects. The amount of this reduction will depend on the number of
piles in the grouping and their spacing. We anticipate that settlements under the p ile foundations will be less
than one-fourth inch.
For augercast piles, the pressure used to inject the grout and construct the pile column will compress the soils
immediately adjacent to the pile. As a result, the amount of grout needed to form the pile ma y be greater than the
theoretical grout volume. Also, piles should be constructed at a minimum spacing of five -diameters. Once the
grout has achieved its initial set, installation between these locations can be completed.
The auger should be extracted slowly and uniformly below a sufficient and consistent head of grout. If the auger
is extracted too quickly, the pile may neck down and soil may collapse into the pile, reducing its structural
integrity. At a point along the injection line, the piling contractor should use a pressure gauge to monitor the
grout pressure during construction. The amount of grout used in forming the pile should also be monitored.
5.5 Basement and Retaining Walls
The magnitude of earth pressures developing on basement or retaining walls will depend on the quality and
compaction of the wall backfill. We recommend placing and compacting wall backfill as structural fill. Below�
improved areas, such as pavements or floor slabs,. the backfill should be compacted to a minimum of 95 percent
of its maximum dry unit weight, as determined by American Society -of Testing and Materials (ASTM) Test
Designation D-698 (Standard Proctor). In unimproved areas, the. relative compaction can be reduced to 90
percent.
To prevent hydrostatic pressure development, wall drainage must be installed. Drainage behind basement walls
can be provided by attaching prefabricated wall drainage panels, such as Miradrain G100W, to the outer side of
the wall, or by backfillmig the wall with a clean granular material, such as, pea gravel. A foundation drain
consisting of a four -inch diameter perforated PVC pipe should be installed at the base of the wall for collection
and removal of the intercepted groundwater. The foundation drain should be surrounded by at least six inches of
pea gravel extending two feet above the pipe. All drains must be routed to an approved point of controlled
discharge. Cleanouts should be installed at appropriate an d easily accessible locations along the drain
alignments. These cleanouts should be serviced at least once each year.
Page No. 9
November 21, 2001
Project No. T-4893
With wall backfill placed.and compacted as recommended and.drainage properly installed, we recommend
designing unrestrained walls for an active earth pressure equiva lent to a fluid weighing 35,pcf For restrained
walls, an additional uniform lateral pressure of 100 psf should be, added. These values assume a horizontal
backfill condition and that no other surcharge loading, such as traffic, sloping embankments, or adjacent
buildings, will act on the wall. If such conditions will exist, then the imposed loading shoul d be included in the
wall design.
Friction at the base of foundations and passive earth pressure will provide resistance to these lateral loads.
Values for these parameters are provided in theYoundations section of this report.
5.6 Slab -on -Grade Floors
Slab -on -grade floors may be supported on subgrades prepared as recommended in the Site Preparation and.
Grading section of this report. Immediately below the floor slab, we recommend placing a four -inch thick
capillary break layer of clean free -draining sand or gravel having less than three'percent passing the No. 200
sieve. This material will reduce the potential for upward capillary movement of water through the underlying
soil. and subsequent wetting of the floor slab. Where moisture by vapor transmission is undesirable, a durable
plastic membrane should be placed over the capillary break material. The membrane should be covered with two
inches of clean moist sand to guard against damage during construction and to aid in curing the concrete.
5.7 Drainage
Surface
Final exterior grades should promote free and positive drainage away from the building areas. We recommend
providing a gradient of at least three percent for a minimum distance of ten feet from the building perimeter,
except in paved locations. In paved locations, a minimum gradient of one percent should be provided unless
provisions are included for collection and disposal of surface Wateradjacent to the structure'.
SU'rface water must not be allowed to flow uncontrolled over the crest of the site slopes and embankments.
Surface water,should be directed away from the slope crests to a point of collection and controlled discharge. If
site grades do not allow for directing surface water away from the slopes, then water should b
e collected and
tightlined to the bottom of the slope in a controlled manner.
Subsu�face
We recommend installing a continuous drain along the outside lower edge of th I e perimeter. building foundations..
The foundation- drains and roof downspouts should be tightlined separately to an approved point of controlled
discharge. Subsurface drains must be laid with a gradient sufficient to promote positive flow to the discharge
point. All drains should be provided with c.leanouts at easily accessible locations. These cleanouts should be
serviced at least once each year.
Page No. 10
SS-132p-
B�2.
SB-217
-"P ll W-203
'T
T1�74
B-213
V
-,SB- 0.'
lmvy.20-al� "I , r
2 221
-232
SB-
-202
P oSB SB
—B-21 -1 SB-216 TP-14
TP16 -3 B-228
231--1
-210
611AI
-W-� 5
mw-io 1, B-2
16
P-13
TP
-7
-SB-229:,
-223
SB
222 .''S6-2 6 -2
0
-208
B
S 23
B-23
TP-17.
SB-
P-8
SB-2 Tp-
SB-20
TP-10
SB
c:I
J
40 TP-
NOTE: LEGEND
TP-1 APPROXIMATE TEST PIT LOCATION (TERRA)
TH IS SITE PLAN IS FOR REFERENCE PURPOSES ONLY AND
IT SH ' OULD NOT BE USED FOR CONSTRUCTION OR DESIGN EMCON EXPLORATORY BORING
PURPOSES.
REFERENCE: 0 200' 400
SITE PLAN PROVIDED BY TRIAD AS80CIATES
-- - 1�. APPROXIMATE SCALE.IN FEET
November 21, 2001
Project No. T4893
5.8 Utilities
Utility pipes should be bedded and backfilled in accordance with American Public Works Association (APWA)
or City of Edmonds specifications. Trench backfill should be placed and compacted as structural fill as described
in the Site Preparation and Grading section of this report. If the granular soils excavated on -site are free of
excessive deleterious material or debris, and are not excessively moist, they should be suitable for use as backfill
material. The very d ense silt and hard clay will not be suitable for use as backfi,11. If the silt and/or clay soils are
exposed in utility trench excavations, or construction takes place during periods of wet weather, it may be
necessary to import structural fill for backfilling purposes.
5.9 Pavements
Pavements should be constructed on subgrades prepared as described in the Site Preparation and Grading section
of this report. Regardless of the relative compaction achieved, the subgrade must be firm and relatively
unyielding before paving. Proofrolling the subgrade with heavy construction equipment should be *completed to
verify this.condition.
The appropriate thicknesses of the various components of the pavement depend on the subgrade soils and the
traffic conditions to which the pavement will be subjected. We expect traffic to mainly consist of light passenger
vehicles with only occasional heavy service vehicles. Based on this information and a properly prepared and
stable subgrade, we recommend the following pavement sections:
0 Two inches of asphalt concrete (AC) over six inches of crushed rock base (CRB)
Two inches of AC over four inches of asphalt -treated base (ATB)
All paving materials should conform to the Washington State Department of Transportation (WSDOT)
specifications for Class B asphalt concrete, ATB, and CRB.
Long-term pavement performance will depend on surface drainage. A poorly drained �pavement section will be
subject to premature failure as a result of surface water infiltrating into the subgrade soils and reducing their
supporting capability. To improve performance, we recommend surface drainage gradients of at least two
percent. Some longitudinal and transverse cracking of the pavement surface should be expected over. time.
Regular maintenance should be planned to seal cracks when they occur.
6.0 ADDITIONA-L SERVICES
Terra Associates, Inc. should review the final design and specifications in order to verify that,earthwork and
foundation recommendations have been properly interpreted and incorporated into project design and
construction. We should also provide geotechnical services during construction in order to observe compliance
with the design concepts, specifications, and recommendations. This will also allow for design changes if
subsurface conditions differ fTom those anticipated prior to the start of construction.
Page No. I I
November 21, 2001
Project No. T-4893'
7.0 MUTATIONS
We prepared this report in accordance with generally accepted geotechnical engineering practices. This report is
the copyrighted property of Terra Associates, Inc. and is intended for specific application to the UNOCAL Site
project. This report is for the exclusive use of Triad Point Edwards and their authorized representatives. No
other warranty, expressed or implied, is made.
The analyses and preliminary recommendations presented in this report are based upon data obtained &orn the
on -site test pits. Variations in soil conditions can occur, the nature and extent of which may not b ecome evident
until construction. If variations appear evident, Terra Associates, Inc. should 'be requested to reevaluate the
recommendations in this report prior to proceeding with construction.
Page No. 12
WSW
ilr-17
mffr i I
PL Y
S. ST SO
PK. s rH
PL j8Z ST Sw
ez 4p 18M ST Sw
unTH Sw
R F4 AKE- ST Sw $I Sw
CHEW ST
I
yze,
OR
I
-Xf196T
ma
LN
PU
.13
HIND
21MOMIX
OR
EWLM
00
p
BROOMCK
ALSO
YNOERVA rER
flb�
----
ST
I
PARK
V[ rA�: BN
wi—
VISTA
200TH
ST Sw 63tj
BRACKETTS
WI—ST 1
q+
LA
GIN
24
I-ST
A,
HILL FK
ST"
S �7
ST.
DAYTON
2im FL
WLE
m
ZDM p-
23
:3;
WON.
7w,
'0 15
lz zlzm
OIL
HOKLL
AM
IL ST Sw
ell
SITE
OR.
Elm ST
Nzi -
7
IL Z.
Zli"
,j 'A
1L
. i
21
LFOWARDS MKIM W— -M
PT BEAM p"M " . "I'll, �*
I 7T H T SW
PC,-- MK AH
ST Sw
UV51 - I 30
9
COOIJ , 9, .. F
LLA ST E ST 2� TNH ST zi -1 sw
An
T Sw
4 ZZIST PL
rw
00 FIN R
T
X
SOURCE:
Thomas Guide, Pierce, King and Snohomish County, 1999. Page 454.
NOT TO SCALE
VICINITY MAP
UNOCAL SITE
EDMONDS, WASHINGTON
IfflTerra
AWS-7sociates, Inc.
Geotechnical Consultants
1 Proj. No. T-4893 I
Date NOV 200ITFigure
1
STRUCTURAL FILL
REVERSE SLOPE TO DRAIN
2
TOE OF
NEW SLOPE 2' 6-
�— 6- ---4
7— 1--6- -4
KEYWAY AND DRAIN
(SEE NOTE 1)
I
I
6' "--TYPICAL SLOPE BENCH (MAY
A
REQUIRE SUBDRAIN IF SEEPAGE
CONDITIONS ARE INDICATED)
\—TOE BENCH CUT AND
DRAIN (SEE NOTE 1)
NOT TO SCALE
NOTES:
1) DRAINS SHALL CONSIST OF 6- DIAMETER PERFORATED PVC PIPE ENVELOPED
IN I cu. ft. OF WASHED 3/4* MINUS DRAINAGE GRAVEL
2) TOPSOIL REMOVAL.THICKNESS BETWEEN KEYWAY AND BENCHES.
,(IF NECESSARY)
VERTICAL ELEVATION DIFFERENCE BE TWEEN TOP OF LOWER BENCH
BACKCUT AND UPPtR BENCH ELEVATION.
9MTerra
Associates, Inc.
Geotechnical Consultants
GENERAL SLOPE FILL DETAIL
UNOCAL SITE
EDMONDS, WASHINGTON
Proj.No. T-4893 I Date NOV 2001. 1 Figure 3
APPENDIX A
FIELD EXPLORATION AND LABORATORY TESTING
UNOCAL Site
Edmonds, Washington
On October 18 and 19, 2001, we performed our field exploration using a track -mounted excavator. We explored
subsurface soil conditions at the site by excavating 17 test pits to a maximum depth of about 16 feet below
existing surface grades. The test pit locations are shown on Figure 2. The test pit locations were approximately
determined by pacing from existing surface features. The Test Pit Logs are presented on Figures A-2 through A-
10.
An engineering geologist from our office maintained a log of each test pit as it was excavated, classified the soil
conditions encountered, and obtained representative samples. All soil samples were visually classified in
accordance with the Unified Soil Classification. System. A 'Copy of this classification is presented as Figure A- 1.
Representative soil samples obtained from the test pits were placed in sealed plastic bags and taken to our
laboratory for further examination and testing. The moisture content of each sample was measured and is
reported on the Test Pit Logs. The Atterberg limits of four samples were, determined and are reported on the Test
Pit Logs. Grain size analyses were performed on I I of the samples, the results of whicL are shown on Figures A-
I I through A- 16.
Project No. T-4893
0 ,
MAJOR- DIVISIONS
LETTER
SYMBOL
TYPICAL DESCRIPTION
Clean
GW
Well -graded gravels, gravel -sand mixtures, little or no
GRAVELS
Gravels
fines.
GP
Poody-graded gravelsi gravel -sand mixtures, little or
j 0)
L_
(less than
a
0
N
More than
5% fines)
no fines.
GM
Silty gravels, grave I -sand -silt mixtures, non -plastic
@
50% of coarse
fraction is
C)
LU
.0
= 4)
4) >
larger than 'No.
Gravels
. .
with. fines
fines.
Z_
co -o
E (n
4 sieve
GC
Clayey gravels, gravel -sand -clay mixtures, plastic fines.
<
cc
0 C\l
LO
SANDS
Clean
Sands
SW
Well -graded sands, gravelly sands, little or no fines.
W
6
a Z
ca
-_
(less than
SP
Poody-graded sands or gravelly sands, liftle or no
I r-
4-
More than
5% fines)
fines.
<
ca
a)
50% of coarse
0
L_
0
fraction is
Sands
SM
Silty sands, sand -silt mixtures, non -plastic fines.
0
smaller. than
SIC
Clayey sands, sand -clay mixtures, plastic fines.
No. 4 sieve
with fines
U)
ML
Inorganic silts, rock flout, clayey sifts with slight
J
SILTS AND CLAYS
plasticity.
CL
inorganic clays of low to medium plasticity,* (lean clay).
0)0
0 co Cj
E 0 (D
Liquid limit is less than 50%
OL
Organic silts and organic clays of low plasticity.
0 0 Z.N
W 0-
z
0 C
Lo ca
MH
Inorganic silts, elastic.
>
a)
SILTS AND CLAYS
CH
Inorganic clays of high plasticity, fat clays.
ca
0 E
Z
CO
Liquid limit is greater than 50%
[z
'OH
Organic clays of high plasticity.
HIGHLY ORGANIC SOILS
PT
Peat.
DEFINITION OF TERMS AND SYMBOLS
Standard Penetration
Density Resisia�c_e -in- 916,ws/Po-ot
2*- OUTSIDE DIAMETER SPLIT
W
_j
SPOON SAMPLER
z
0
Very loose 0-4
2.4* INSIDE DIAMETER RING SAMPLER
(n
Loose 4-10-
OR SHELBY TUBE SAMPLER
W
Medium dense 10-30
0
Dense 30-50
3! WATER LEVEL (DATE)
Very dense >50
Tr TORVANE READINGS, tsf
Pp PENETROMETER READING, tsf
Standard Penetration
W
Consistenc Resistance in Blows/Foot
DD DRY DENSITY, pounds per cubic foot
>
Fn
Ve soft 0-2
ry
LL LIQUID LIMIT, percent
W
Soft 2-4
M
0
Medium stiff 4-8
PI PLASTIC INDEX
stiff 8-16
Very stiff 16-32
N STANDARD PENETRATION, blows per foot
Hard >32
Terra
UNIFIED SOIL CLASSIFICATION SYSTEM
UNOCAL SITE
Associates, Inc.
EDMONDS, WASHINGTON
Geotechnical Consultants
Proj. No. T-48,93
Date NOV 2001 j
Figure A-1
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0 . FILL: crus
5
10
15
20
Test Pit NO. TP-1
Soil Description
Approximate Elev. 104
Moisture
Content
hed rock surfacing over brown to gray silty sand to sandy silt, fine grained,
firm, moist (SMIML)
Rusty brown silty SAND
(, fine grained, medium dense, moist, with occasional fine
\gravel and fine roots. M)
Gray to mottled gray silty SAND, fine grained, medium dense to dense,
moist, with occasional fine gravel. (SM)
Becomes light brown. at approximately 6 feet.
26
Pp 4.5+
Gray CLAY, hard, moist, massive. (CL)
tons/fe
LL 35.8
PI 15
Test pit terminated at 14 feet.
No groundwater seepage.
Logged by: JCS
Date: 10/18/01'
Depth
(ft.)
0 `_ FILL: crust
5
10
15
20
Test Pit No. TP-2
Approximate Elev. 124
Moisture
Soil Description Content
-
ed rock surfacing over brown silty sand to sandy silt, fine grained, firm,
moist. 4-inch thick organic layer at base. (SM/ML) (Old topsoil horizon)
Brown silty SAND, fine grained, medium dense, moist. (SM)
-
Mottled grayish -brown silty SAND, fine grained, medium dense, moist.
(SM)
20
Grayish-brdwn silty SAND, fine grained, medium dense to dense, moist.
(SM)
Gray CLAY, hard, moist, I amin,ated with light gray silt partings. (CL)
Pp 4.5+
tons/fe
37
Test pit terminated at 14 feet.
No groundwater seepage.
TEST PIT LOGS
Terra UNOCAL SITE
Associates,inc. EDMONDS, WASHINGTON
Geotechnical Consultants
Proj. No. T-4893 I Date NOV 2001 1 Figure A-2
Test Pit No. TP-3
Log I byjCS Approximate Elbv. 121
Date�e loll 01
Depth Moisture
Soil Description Content
N
0— FILL: brown silty sand, fine grained, firm, moist, with occasional fine
gravel and organic material. (SM) (Hydrocarbon odor)
Dark brown silty SAND, fine grainea, son, moist to wet. (OL)
\.(Old topsoil
15
5 Tan to light gray silty CLAY to clayey SILT, hard, moist. (CUML)
(Hydrocarbon odor)
10 Gray CLAY, hard, moist, laminated with partings of light gray silt and gray I
fine sand. (CL) Pp = 4.5+
32 1 tonsfit'
� Test pit terminated at 13 feet.
15 Light groundwater seepage from point source at 4.5 feet.
20
Test Pit No... TP-4
Logged by: JCS Approximate Elev. 92
Date: 10/18/01
Depth Moisture
Soil Description Content
N
0— FILL: !ight brown silty sa-nTfine rainedfiffn,dry I tomoist. (SM) 2-inchthick
016 topsg
-,,organic layer at base. 0 1 hori on)
- Light brown to tan silty SAND, fine grained, medium dense to dense, dry.
(SM)
51 Mottled grayish -brown silty SAND, fine-grained, medium dense to.dense, , 29
1QRA%
- LL = 42.7
- Light grayish -brown to light brown CLAY and SILT, hard, moist, laminated 29 - PI = 19.7
- with partings of dark gray fine sand. (CUML) Pip = 4.5+
tons/te
1.0—
. Gray CLAY, hard, moist. (CL) PP =
29 ton
- Test pit terminated at 13 feet.
15 ---! Trace groundwater seepage at 6 feet.
20
TEST PIT LOGS
erra UNOCAL SITE
Associates, Inc. EDMONDS, WASHINGTON
Geotechnicai Consultants
Proj. No. T-4893 Date NOV 20 A-3
Logged by: JCS
Date:1 0/18/01
Depth
(ft.)
0-
5
10
15
20
Test Pit No. TP-5
Soil Description
Approximate Elev. 110
Moisture
Content
6 inches DUFF and TOPSOIL.
Light brown SAND with sift to silty SAND, fine grained, medium dense,
moist. (SP-SM/SM)
23
Mottled grayish -brown SAND to SAND with silt, fine grained, medium
dense to dense, moist. (SP/SP-SM)
Becomes wet at approximately 9 feet.
26
34
LL - 44.5
Grayish -brown to gray CLAY, hard, moist, generally massive, with
P1 = 21.3
occasional thin laminations of gray silt. (CL)
Pp = 4.5+
tons1W
-
Test pit terminated at 16 feet.
-
Light groundwater seepage between 9 and 10 feet.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0—
r
1 C
15
20
Test Pit No. TP-6
Approximate Elev. 150
Moisture
Content
Soil Description 1%)
-
FILL: brown to grayish -brown SILT, CLAY, and fine grained SAND, firm
-
moist to wet, with some fine gravel and occasional organic material.
32
.
FILL: gray to brownish gray silt, clay, and fine grained sand, firm, moist to
-
wet, with moderate organic material (including wood debris) and sorn I e
.
gravel. 1.2-inch thick organic layer at base. (Old top soil horizon)
-
-
Gray silty SAND to sandy SILT, fine grained, dense, moist,
with occasional fine to coarse gravel. (SM/ML) (Glacial till -like)
-
Test pit terminated at 16 feet.
-
No groundwater seepage.
Terra TEST PIT LOGS
UNOCAL SITE
EDMONDS, WASHINGTON
Associates, Inc.
Geotechnical Consultants
Date NOV 2001 1 Figure A-4
Proj. No. T-4893 .1
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
10
15
20
Test Pit No. TP-7
Soil Description
Approximate Elev. 121
Moisture
Content
FILL: dark brown organic silty sand, fine grained, firm, moist.
Mottled gray to brown SAND with silt to silty SAND, fine grained, medium
dense to dense, moist. (SP-SWSM) (Hydrocarbon odor)
20
Tan to light grayish -brown silty CLAY to CLAY, hard, moist, occasional
24
mottling. (CL)
Pp - 4.5+
tonstfe
31
-
Test pit terminated at 15 feet.
-
No groundwater seepage.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
1 C
15
20
Test Pit No. TP-8
Soil Description
Approximate Elev. 121
Moisture
Content
(OM
FILL: light brown to gray silty sand, firm, moist to wet, with organics.
FILL: dark brown organic silty sand, loose, wet, with significant wood
debris (timbers and branches). 2.5-foot diameter boulder.
Gray SILT to SILT with sand, fine grained, dense, moist to wet. (ML)
25
-
Lig ht grayish -brown to tan sandy SILT, fine grained, very dense, moist,
-
with occasional fine gravel. (ML) (Glacial till -like)
16
-
Test pit terminated at 15 feet.
-
Light groundwater seepage at 6 feet.
erra
Associates, Inc.
Geotechnical Consultants
TEST PIT LOGS
UNOCAL SITE
EDMONDS, WASHINGTON
I I Proj. No. T-4893 I Date NOV 20011 Figure A-5, I
Logged by: JCS
Date: 10/18/01
Depth
. (ft.)
0—
A
10
15
20
Test Pit No. TP-9
Soil Description
Approximate Elev. 150-
Moisture
Content
I(%)
-
FILL: crushed rock surfacing over grayish -brown sandy silt and clay, firm,
-
moist. 6-inch thick organic layer at base. (Old topsoil horizon)
Mottled grayish -brown sandy SILT to sandy CLAY, stiff, moist. (MUCL)
Pp = 4.5+
30
tomw
37
Grayish -brown CLAY, hard, moist, massive. (CH)
LL = 58.8
PI = 30.1
Gray SILT and CLAY, hard, moist, with occasional laminations of gray
Pp = 4.5+
fine sand. (MUCL)
22
1 tons/ft'
Test pit terminated at 15 feet.
No groundwater seepage.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
5
10
15
20
Test Pit No. TP-1 0
Soil Description
Approximate Elev. 157
Moisture
Content
6 inches DUFF and TOPSOIL.
Brown sandy SILT, fine grained, medium dense, moist. (ML)
40
Grayish -brown SILT and CLAY, hard, moist. (MUCL)
Pp = 4.5+
tonsife
34
Gray SILT and CLAY, hard, moist. (MUCL)
Test pit terminated at 15 feet.
No groundwater seepage.
Terra
Associates, Inc.
Geotechnical Consultants
TEST PIT LOGS
UNOCAL SITE
EDMONDS, WASHINGTON
I I Proj. No. T-4893 I Date NOV 20011 Figure A-6 I
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0—
R
10
15
K11
Test Pit No. TP-11
Soil Description
Approximate Elev. 78
Moisture
Content
M
Mottled grayish -brown SAND to SAND with silt, fine grained, medium
dense, moist to wet. (SP/SP-SM)
25
15
Light brown silty SAND to sandy SILT, fine grained, medium dense to
dense, moist. (SM/MQ Increasing silt with depth.
15
22
-
Test pit terminated at 15 feet.
-
I
No groundwater seepage.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0
1C
15
20
Test Pit No. TP-1 2
Soil Description
Approximate Elev. 76
Moisture
Content
( % I
nc es crushed rock surfacing.
Mottl4ad grayish -brown SAND fine to mediuTprained, medium dense, moist, with
occasional fine gravel. (SP) �Hydrocarbon 0)
Gray SAND with silt to SAND, fine grained, medium dense to dense,
17
moist to wet, with occasional fine to coarse gravel. (SP-SWSP)
15
Mottled grayish -brown silty SAND with gravel to sandy SILT with gravel,
fine sand, fine gravel, dense to very dense, moist. (SM/MQ
(Glacial fill -like between 8 and 10 feet) Increasing gravel with depth.
I
20
Test pit terminated at 15 feet.
Trace groundwater seepage at 8 feet.
- - - - - - . . . . . . . . . . . rra
Associates, Inc.
Geotechnical Consultants
TEST PIT LOGS
UNOCAL SITE
EDMONDS, WASHINGTON
Proj. No. T-4893 I Date NOV 20011 Figure A-7
Logged by: JCS
Date: 10/18/01
Depth
(ft.) ,
0 — 113.n^k.
5
10
15
20
Test Pit No. TP-1 3
Soil Description
Approximate Elev. 86
Moisture
Content
s crushed rock surfacing.
Mottled gra ish-brown silty SAND to sandy SILT, very dense, moist. (SM/ML)
(Hyd ocarbon odor)
25
31
Bluish -gray CLAY, hard, moist, with partings of gray fine sand and light
gray silt. (CL)
Pp 4.5+
tons/fe
Test pit terminated at 14 feet.
Trace groundwater seepage at 2.5 feet.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0—
E
1 C
15
�zl
Test Pit No. TP-1 4
Soil Description
Approximate Elev. 76
Moisture
Content
(%I
-
-
FILL: bluish -gray silty sand with gravel to sandy silt with gravel, fine sand,
fine gravel, medium dense to dense, moist. (SM/ML)
10
.
Light brown sandy SILT, fine grained, dense, moist, with occasional
-
fine gravel and thin layers of fine grained silty sand. (ML)
19
15
-
Test pit terminated at 15 feet.
-
'No groundwater seepage.
TEST PIT LOGS
Terra UNOCAL SITE
Associates, Inc. EDMONDS, WASHINGTON
Geotechnical Consultants
Proj. No. T-4893 Date NOV 2 A-8
Log �ejd by: JCS
Date 0118/01
Depth
0 FILL: gra
5
10
15
20
Test Pit No. TP-1 5
Soil Description
Approximate Elev. 86
Moisture
Content -
I[%) I
to
y sil sandy silt, fine grained, medium dense, moist, with occasional
(�IrMnd
fine ravel. L)
org
Dark brown anic sandy SILT, fine grained, firm, moist, with occasional roots. (OL)
(Old topsoil hor n)
zo
Mottled grayish -brown silty SAND with gravel to SAND with silt and gravel,
fine sand, fine to coarse gravel, medium dense to dense, moist.
10
(SM/SP-SM)
Becomes brownish -gray and moist to wet at approximately 8 feet.
V
Brownish -gray silty SAND with gravel to sandy SILT with gravel, fine sand,
fine gravel, dense, moist. (SWIVIL) (Glacial till -like)
18
-
Test pit terminated at 15 feet.
-
Trace groundwater seepage at I I feet.
Test Pit No. TP-1 6
Logged by: JCS Approximate Elev. 68
Date: 10/18/01
Depth moisture
(ft.) Soil Description Content
FILL gray to brown silty sand with gravel, fine grained, firm to loose,
moist to wet. (SM) I I
5— FILL: grayi ' sh-brown silty sand with gravel, fine grained, firm, moist to wet,
with significant organic soils and wood debris.
23
10-1 16
1-5 �Test pit terminated at 13 feet.
No groundwater seepage.
20
Terra TEST PIT LOGS
UNOCAL SITE
EDMONDS, WASHINGTON
Associates, Inc.
Geotechnical Consultants Proj. No. T-4893 I Date NOV 2001 1 Figure A-9
Test Pit No.- TP-17,
Logged by: JCS Approxi I mate Elev. 82
Date: 10/18/01
Depth Moisture
Soil Description Content
N
0- =brown silty SAND with gravel, fine sand, fine to coarse gravel,
m dense. moist. (SM)
- Mottled aysh-brown =13 with gravel, tine sand, fine to66iise gravel,
medium gdr ense to dens (SM) 13-
Grayish-brown silty SAND with gravel to sandy SILT with gravel, fine sand,
5 -�fine to coarse gravel, dense to very dense, moist. (SWIVIL)
(Glacial till -like) Sand content increases with depth.
10
15
20-
Test pit terminated at 9.5 feet.
No groundwater seepage.
rra
Associates, Inc.
Geotechnical Consultants
TEST PIT LOGS
UNOCAL SITE
EDMONDS, WASHINGTON
Proj. No. T-4893 I Date NOV 20011 Figure A-10 I
.101,-K g6n 9BO34
12525 Willow's Road' e irklandjWz�hin
(425) 821-77 Fax.(425) -821
Mr. Ross Woods
December 20, 2005
Comment No. 8, Paize 2:
*Provide a letterfrom the geotechnical engineer of record that he has reviewed the building plans for Building 8
andfinds them consistent with the recommendations in his report and supplemental letters.
We reviewed structural drawings for Building 8 to verify that the plans conform to our geotechnical
recommendations. We were provided the following plans for our review:
9 Structural Sheets SI.,.1 through S7.1, prepared by DCI Engineers, dated November 18, 2005
The plans indicate foundation support for Building 8 will be provided by conventional spread footings. Design
soil values outlined in the Soils and Foundations section of the Structural General Notes on Sheet SLI indicate
that structural design used allowable foundation pressures of 5,000 pounds per square foot (psf) for native soil and
3,000 psf for structural fill. However, based on our conversation with DC1 Engineers, we understand that all
foundations for Building 8 were dimensioned for a net allowable bearing capacity of 5,000 psf
In our referenced preliminary geotechnical report, we recommended dimensioning foundations for a net allowable
bearing capacity of 5,000 psf where supported by very dense silt and hard clay soils. Our site explorations in the
area of Building 8 (Boring B- 103) indicate that that much of the foundation excavation for the lower building
levels (PI and LI) will expose dense silv'hard clay. However, foundation excavations for floor level L2 (Elev.
131) on the southern side of the building will likely expose medium dense native silty sand above Elev. 120.
Foundations bearing on these native soils should be dimensioned for an allowable bearing capacity of 3,000 psf
In addition, Cross Sections B-B, C-C, and D-D on Sheet 4D of the civil plans prepared by Triad Associates, Inc.,
dated July 28, 2003 (revised October 14, 2005) indicate that the lower floor level of the building will be supported
by structural fill approximately 7 to 12 feet above existing grade at the perimeter of the building. If foundations
in this area are not lowered to bear on the native dense silt/hard clay, they should be dimensioned for an allowable
bearing capacity of 3,000 psf.
Based on our review with the above discussion taken into consideration, it is our opinion that the plans are in
general conformance with our geotechnical recommendations.
Foundation Issues Including Lateral Loid Considerations, Comment No. 1. Page 2:
I don't recall seeing anyjustification in the other soils reports by the engineer'sfor the Y4 to I slopes and a 4-high
(sic) temporary vertical cuts as shown in Section Views A -A and B-B on Sheet 4D of the Triad Associates plans.
As discussed in Section 5.3 of our referenced preliminary geotechnical report, the denselhard transitional bed silt
and clay, such as that observed below approximately Elev. 120 in the area of Building 8, can be sloped at
temporary inclinations of 0.75:1 (Horizontal:Vertical) or flatter. The lower four feet of the excavation can be
made vertical where the densdba�d transitional bed soils are exposed. This temporary slope geometry is
supported by the results of computer stability analysis, which yielded adequate factors of safety.
Project No. T-4893
Page No. 2
Mr. Ross Woods
December 20, 2005
Foundation Issues Including Lateral Load Considerations, Comment No. 2, age 2:
The Lock and Load wall shown on Sheet 4 of the Triad Associates Plans needs to be providedfor review. The
engineer has to use the criteria in ICC Evaluation Report # 5893.
The Lock+Loae wall design is in general conformance with the criteria presented in ICC Evaluation Report #
5893. Ile design calculations and results of global stability analyses are attached.
We trust the information presented is sufficient for your current needs. If you have any questions or require
additional -information, please call.
Sincerely yours,
TERRA ASSOCIATES, INC.
John C.
Project
12--2-0— V6--
Theodore
Principal
Encl: SheAl Retaining Walls
-"—IID Calculations
TV a,
ME, �BM_'r
cc: Mr. Jeff Brink DCI Engineers
Project No. T-4893
Page No. 3
IN
I ril
I . � " "�
;u =;,:,A
- --.�--M 2
Ir R= l-..T
TYPICAL WALL SECTION
.� V.r
GENERAL NOTES
ILI'
I
F
90'CORNER-ELEVATION
90*CORNERASSEMBL
REINFORCING SCHEDULE
M. - w
mw
c� INIU 00
-PM
31
31
IM
3. Mm
I.D
11. o-m
in
RADIUS CORNER DETAIL PLAN
0
z
10
z z
E z
e, o: (6
a
89 z
� 0 0
+ Lu 2
L x �- 0
) K uj
0
0
(L
a
LOCK+LOAD RETAINING WALL DESIGN CALCULATIONS
POINT EDWARDS CONDONM41UMS
PROJECT NO. T4893
PREPARED BY TERRA ASSOCIATES, INC.
DECEM13ER 2003
A,— Rp� I
4"'
L
9
�VO // 01701
4Q
FAWA - 5A -cle,-O
Lock + Lop�ot 1Zv4,,'r,;rLj Wall I zOO
TERRA
.-,ASSOCIATES'
Geotechnical Consultants
PROJECT Fo,?4-r a_0WAf-_D _S
F
BY SrY,
SHEET
LOCATION
CHECKED
T
cL1EN L-LC
DATE 17_.2-03:
12525 Willows Rd., Ste. 101 Kirkland, WA 98034 (425) 821-7777
JOBNO_
cm-
340 o,283
C>-Z83
130P.; 346
Fc.%, "cic��or\ Sol 15 1 -sop,+ 34' 29MLI LA1.0(p
Walt �rlc.-6fN
W ct-6, *mlole— 'celow �mse- cr� 4* WCk Lk.
Fvlly Ckf-aif%ea Uxwti-kons-
to Y-T -T-,A+. -
F)(TE1ZMhL �6rA-SILI-r-/ CALC(.)LA7M0W5--
Wei&A R -&e Lnit qocl-14, "ol4t
hc--4;�,e- = -7 1 �3 ci "4,+_
L,4-mi svr-6"r- I Li
R�5!5&"O-
Fkc-rop- QF!SA-'FVi-rY
(Tan .3'6
(lq50 'k4 )
> 1.5 V/
Over+vrn;r!� FS. +04SO 1641)� 10L.-I-4)(4)
>
Beaf-; p �y U4; -otkc
C.=,pcLc� 4-y.
PROJECr
BY
SHEEr
TERRA
CHECKED
LOCATION
ASSOCIATES
CLIENT
DATE
Geotechnical Consultants
12525 willows Rd., Ste. 101 Kirkland, WA 98034 (425) 821-7777
JOB NO.
L
+
P—
c = 8 - 4-5�
===> L- . ZG7
--� =
4 2. (- rl
4, L-
4t*
Ul+iM-�- 9mriv,5 CAPOL641/
Q.,+ = 0- /q. + 1 '6 e>'14 -f y 1) tib
2a
-------------
+ + 030P,4)(7-57-�'t)(79,,jq)
cg",.= sLi5l 1141W
+ (7-f-0
'44,471 "0/01
12,89
PROJEC-F
BY
SHEEr
7*7-
.,—.'TERRA
LOCATION
CHECKED
ASSOCIATES
CLIENT
DATE
Geotechnical Consultants
12525 Willows Rd., Ste. 101 Kirkland, WA 98034 (425) 821-7777
L
JOB NO.
CN 7
6EEC,6p-)Z� —IaNS1014 :
Ge,c%f-Ick
6eotr1A
Geotmii Tensioe, -4crvi
W-Hl- 9"-55,dre- ('6/;,)
Gec.54'10\ -ren-4160\ V—%
Kinimorej
,o IV\
F. :5.
F. Sr
6-G(o
ez, a
11 cl r"I. 01
A -c�
Ict 'cl
3, z45
'31(P.Z
12 L(
32t.,3
1z--z
I Z - -2-
vjejoke
6.91
'579?-9
569,7
(a A
IM4.1
8.8
10-01
-ren-5"Of�
e-5-21
sqzli
Lqz2.2
q 6
5�72,-6
(o -q
Li's
397-9
3.7
6cl.8'(p
S-7
--T
13--18
-392-9
3
Z. 1
8 9z, 41
q,
PROJECT
BY
SHEET
Z`777' TERRA
CHECKED
7:7-77� j��77701
LOCATION
CLIENT
DATE
ASSOCIATES
Geotechnical Consultants
12525 Willows Rd., Ste. 101 Kirkland, WA 98034 (425) 821 -7777
JOB NO.
U LL OU -r 0 T= Pkm M A1,1 f.� Z�-O&z I b
F76f-ce
P'ests-��
in
Coer-or-
--0qA
Geotr-,4
j.-A
-3
r73(,.B
8'e
Z.&Z
07).S-
103'3,0)
S,25
521.2
/6,33.7
-3,1
6.540
637.1
q26. rl
-:3.0
`766*3,0
"711H8.b
91
7.87
7qct.?
3.0
cl, 19
656.0
zo3
Z.9
10.!5c)
c1553
0-786-7
2.01
//.a/
/OWIZ
300.3
2.1
(0 q.
1(0*380.q
13,12
31- (p
.33Yq,"7
lq,q3
/zm(o
361W
3.0
152ZSr
9ZO317Y
IL1.5
0:75
/30Z
38470,?
-3.0
17,0(o
/ 3 75,Z
1158.,q
-3.0
17'75,r7
z8qq3.ci
1(.. 1
lg,-3,7
IqAIZ6
q,123. q
j
q, 70
0 -6
-4�66,q
s.1
2OZe-7
3 5 7q3. S
PROJECT
BY
ERRA
5
LOCATION
CHECKED
L""" ASSOCIATES
5
CLIENT
TSHEET
DATE
Geotechnical Consultants
2525 Willows Rd., Ste. 101 Kirkland, WA 98034 (425) 821-7777
F
JOB NdO
JO
WINSTABL OUTPUT DATA
41
33,
25.
16.
Global Static
U. JU 25.13 33.50 41.88 50.25 58.63 67.00
Safety Factors
2.40
2.55
2.56
2.97
3.77
3.80
3.88
3.97
4.00
4.03
** PCSTABL6 **
by
Purdue University
modified by
Peter J. Bosscher
University of Wisconsin -Madison
--Slope Stability Analysis --
Simplified Janbu, Simplified Bishop
or Spencer's Method of Slices
PROBLEM DESCRIPTION Global Static
BOUNDARY COORDINATES
7 Top Boundaries
11 Total Boundaries
Boundary
X-Left
Y-Left
X-Right
Y-Right
Soil Type
No.
(ft)
(ft)
(ft)
(ft)
Below Bnd
1
3.00
5.00
11.00
8.00
4
2
11.00
8.00
15.50
10.00
4
3
15.50
10.00
17.50
11.00
3
4
17.50
11.00
34.00
19.00
2
5
34.00
19.00
44.00
19.00
2
6
44.00
19.00
45.00
27.00
1
7
45.00
27.00
67.00
27.00
2
8
44.00
19.00
51.00
19 * 00
2
9
51.00
19.00
67.00
27.00
2
10
17.50
11.00
67.00
11.00
3
11
15.50
10.00
67.00
10.00
4
ISOTROPIC SOIL PARAMETERS
4 Type(s) of Soil
Soil Total Saturated Cohesion Friction Pore Pressure Piez.
Type Unit Wt. Unit Wt. Intercept Angle Pressure Constant Surface
No. (pcf) (pcf) (psf) (deg) Param. (psf) No.
1 125.0 125.0 0.0 34.0 0.00 0.0 0
2 126.0 120.0 100.0 34.0 0.00 0.0 0
3 120.0 125.0 100.0 34.0 0.00 0.0 1
4 110.0 110.0 2000.0 0.0 0.00 0.0 0
I PIEZOMETRIC SURFACE(S) HAVE BEEN SPECIFIED
Unit Weight of Water = 62-40
Piezometric Surface No. 1 Specified by 2 Coordinate Points
Point
X-Water
Y-Water
No.
(ft)
(ft)
1
17.50
11.00
2
67.00
11.00
Searching Routine Will Be Limited To An Area Defined By 2 Boundaries
of Which The First 0 Boundaries Will Deflect Surfaces Upward
Boundary
X-Left
Y-Left
X-Right
Y-Right
No.
(ft)
(ft)
(ft)
(ft)
1
44.00
19.00
51.00
19.00
2
51.00
19.00
52.00
27.00
A Critical Failure Surface Searching Method, Using A Random
Technique For Generating Circular Surfaces, Has Been Specified.
100 Trial Surfaces Have Been Generated.
10 Surfaces Initiate From Each Of 10 Points Equally Spaced
Along The Ground Surface Between X = 11-00 ft.
and X = 20.00 ft.
Each Surface Terminates Between X = 55.00 ft.
and X = 67.00 ft.
Unless Further Limitations Were imposed, The Minimum Elevation
At Which A Surface Extends Is Y = 2.00 ft.
3.00 ft. Line Segments Define Each Trial Failure Surface.
Following Are Displayed The Ten Most Critical of The Trial
Failure Surfaces Examined. They Are Ordered - Most Critical
First.
* * Safety Factors Are Calculated By The modified Janbu Method * *
Failure Surface Specified By 19 Coordinate Points
Point
X-Surf
Y-Surf
No.
(ft)
(ft)
1
17.00
10.75
2
19.99
10.51
3
22.99
10.41
4
25.99
10.46
5
28.98
10.65
6
31.96
10.99
7
34.92
11.47
8
37.86
12.10
9
40.76
12.86
10
43.62
13.76
11
46.43
14.81
12
49.19
15.98
13
51.89
17.29
14
54.53
18.73
15
57.09
20.29
16
59.57
21.97
17
61.97
23.78
18
64.28
25.69
19
65.70
27.00
2.405
41
33.
25.
16.
91
Global Pseudostatic
u 0.00 '110. to ;eo. 13 33-50 41-88 50.25 58.63 67.00
Safety Factors
1.20
1.26
1.27
1.50
2.01
2.04
2.14
2.17
2.17
2.18
** PCSTABL6 lt*
by
Purdue University
modified by
Peter J. BoSscher
University of Wisconsin -Madison
--Slope Stability Analysis --
simplified Janbu, simplified Bishop
or Spencer's Method of Slices
PROBLEM DESCRIPTION Global Pseudostatic
BOUNDARY COORDINATES
7 Top Boundaries
11 Total Boundaries
Boundary
X-Left
Y-Left
X-Right
Y-Right
Soil Type
NO.
(ft)
(ft)
(ft)
(ft)
Below Bnd
1
3.00
5.00
11.00
8.00
4
2
11.00
8.00
.15.50
10.00
4
3
15.50
10.00
17.50
11.00
3
4
17.50
11.00
34.00
19.00
2
5
34.00
19.00
44.00
19.00
2
6
44.00
19.00
45.00
27.00
1
7
45.00
27.00
67.00
27.00
2
8
44.00
19.00
51.00
19.00
2
9
51.00
19.00
67.00
27.00
2
10
17.50
11.00
67.00
11.00
3
11
15.50
10.00
67.00
10.00
4
ISOTROPIC SOIL PARAMETERS
4 Type(s) of Soil
Soil Total Saturated Cohesion Friction Pore Pressure Piez.
Type Unit Wt. unit Wt. Intercept Angle Pressure Constant Surface
go. (pcf) (pcf) (psf) (deg) Param. (psf) No.
1 125.0 125.0 0.0 34.0 0.00 0.0 0
2 120.0 120.0 100.0 34.0 0.00 0.0 0
3 120.0 125.0 100.0 34.0 0.00 0.0 1
4 110.0 110.0 2000.0 0.0 0.00 0.0 0
I pIEZOMETRIc SURFACE(S) HAVE BEEN SPECIFIED
Unit Weight of Water = 62-40
Piezometric surface No. I Specified by 2 Coordinate Points
Point
X-Water
Y-Water
No.
(ft)
(ft)
1
17.50
11.00
2
67.00
11.00
A Horizontal Earthquake Loading Coefficient
OfO.300 Has Been Assigned
A Vertical Earthquake Loading Coefficient
OfO.000 Has Been Assigned
cavitation Pressure = 0.0 psf
Searching Routine Will Be Limited To An Area Defined By 2 Boundaries
Of Which The First 0 Boundaries Will Deflect Surfaces Upward
Boundary
X-Left
Y-Left
X-Right
Y-Right
No.
(ft)
(ft)
(ft)
(ft)
44.00
19.00
51.00
19.00
2
51.00
19.00
52.00
27.00
A Critical Failure Surface Searching Method, Using A Random
Technique For Generating Circular surfaces, Has Been Specified.
100 Trial Surfaces Have Been Generated.
.4 1 1 .
io Surfaces Initiate From Each Of 10 Points Equally Spaced
Along The Ground Surface Between X = 11-00 ft.
and X = 20.00 ft.
Each Surface Terminates Between X = 55.00 ft.
and X = 67.00 ft.
Unless Further Limitations were Imposed, The Minimum Elevation
At Which A Surface Extends Is Y = 2.00 ft.
3.00 ft. Line Segments Define Each Trial Failure Surface.
Following Axe Displayed The Ten Most Critical Of The Trial
Failure Surfaces Examined. They Are Ordered - Most Critical
First.
- - Safety Factors Are Calculated By The Modified Janbu Method * *
Failure Surface Specified By 19 Coordinate Points
Point
X-Surf
Y-Surf
No.
(ft)
(ft)
1
17.00
10.75
2
19.99
10.51
3
22.99
10.41
4
25.99
10.46
5
28.98
10.65
6
31.96
10.99
7
34.92
11.47
8
37.86
12.10
9
40.76
12.86
10
43.62
13.76
11
46.43
14.81
12
49.19
15.98
13
51.89
17.29
14
54.53
18.73
15
57.09
20.29
16
59.57
21.97
17
61.97
23.78
18
64.28
25.69
19
65.70
27.00
1.198
TERRA ASSOCIATES, Inc.
Consultants in Geotechnical Engineering, Geology
and
Environmental Earth Sciences
July 30, 2003
Project No. T-4893
Mr. Ross Woods
Point Edwards, LLC
2801 Alaskan Way, Suite 107
Seattle, Washington 98121
Subject: Supplementary Subsurface Exploration
Point Edwards Condominiums
Pine Street and.Unoco Road
Edmonds, Washington
References: 1. Geologically Hazardous Areas Review, Point Edwards Condominiums (UNOCAL
Site), prepared by Terra Associates, Inc., dated January 20, 2003 1
2. Preliminary Geotechnical Report, UNOCAL Site, Project No. T-4893, prepared by
Terra Associates, Inc., dated November 21, 2001
Dear Mr. Woods:
As requested, we have completed supplementary subsurface exploration at the subject site. The purpose
of our study is to evaluate the need for temporary shoring during construction of the proposed buildings,
and to provide recommendations for temporary shoring design and construction where needed. We
previously performed geotechnical studies for the project and presented our findings in the referenced
reports; however, since that time, building locations and site grading have been refined. Triiad
Associates provided us with a current topographic site plan dated July 21, 2003 that shows existing.
topography and proposed site grading --
Our current study focused on areas where significant site excavations will be required adjacent the
downgradient (northern) side of Pine Street, in the areas 'of Buildings 3, 4, and 8, and the area of
Building 5, located north of Building 8 and the private loop road. Pine Street is currently oqeof two
roadways that access the community of Woodway, south of the site. This report summarizes the results
of our recent subsurface exploration and discusses supplementary shon recommendfM48VNED
project. OCT 2 C "005
ST"`6!,-"T6-.T FILE S"'
BUILDING DEPT.
12525 Willows Road, Suite 101, Kirkland, Washington 98034,
Phone,(425) 821-7777 e Fax (425) 821-4334 * terra@terra-associates.com
Mr. Ross Woods
July 30, 2003
PROJECT DESCRIPTION
The project will consist of the construction of ten condorminiurn buildings. The proposed structures will
be three to four stories with daylight basements and one to two levels of undergrou nd parking. We
expect that perimeter load -bearing walls and isolated spread. footing loads. will be as indicated, in the
referenced report. The excavation depths required for construction of the lower parking levels will
approach a maximum of about 27 feet below existing grades along Pine Street.
The recommendations contained *in the following sections of this report are based on our understanding
of the above design features. If actual, features vary or changes are made, we should review them in
order to modify our recommendations, as required. We should review final design drawings and
specifications to verify that our recommendations have been properly interpreted and.incorporatdd into
project design.
SUBSURFACE CONDITIONS
We previously investigated subsurface conditions at the site by excavating 17 test pits (Test Pits TP-1
through TP-17) and drilling 5 test borings (Bonings B-1 through B-5). Our current exploration included
drilling three additional test bonings (Borings B-101 through B-103) on June 18, 2003.
The recent bonings were drilled on the north side of Pine Street, where significant expavations will be
required for construction of the lower parking levels of Buildings 3, 4, and 8. These. test borings were
advanced to a maximum depth of approximately 51.5 feet below the ground surface. The a:pproximate
locations of the recent test borings, and nearby test pits/test borings from our previous studies, are
shown on Figures I and 2. The boring logs and test pit togs are shown on Figures 4 through 9., We
performed grain size analyses on three representative soil samples obtained from the test borings. The
test results are presented on Figures 10 and 11.
The soils encountered in Borings B-101, B-102, and B-103 consist of I to 13 feet a6f very loose to
,medium dense uncontrolled fill overlying medium dense, native silty sand with -varying amounts of
gravel to depths between approximately 7 and 13 feet below the ground surface. The fill and silty sand,
soils are underlain by very stiff to hard, lean play with thin partings of light gray silt and/or very fine-
grained silty sand seams to the maximum. exploration depths of the borings. These soil conditions are
generally consistent with the soils we observed in nearby test pits.
The Geologic Map of the Edmonds East and Part of the Edmonds . West Quadrangles, Washington by
James P. Minard, 1983, shows the soils at higher site elevations mapped as Vashon till, Vashon advance
outwash, and Transitional beds. Transitional bed sediments are described by this publication as massive
to bedded- clay, silt, and fine to very fine sand. The clay and silt soils observed at depth in the test pits
and encountered in the test bonings are generally consistent with the descriptions of transitional bed
deposits.
Project No. T-4893
Page No. 2
Mr. Ross Woods
July 30, 2003
We encountered perched groundwater in all three of the recent borings near the interface of the surficial
fill/silty sand soils and the underlying very stiff to hard clay, and in thin sand layers within the, very stiff
to hard clay. We also observed indications of localized light seep age from the face of the existing slope
between proposed Buildings 4 and 8.
The perched groundwater encountered in Borings B-101 and B-102 occurs at elevations at least 15 feet
below the lower elevations of Bdildmigs 3 and 4 (Elev. 10 1. 17 and Elev. 100.66, respectively). Boring
B-103 (drilled in the area of Building,8) encountered two levels of perched groundwater.. The upper
perched groundwater level is approximately 8.5 feet below the ground surface (approximately Elev.
120.5), and the lower level is approximately 22 feet below the ground surface (approximately Elev.
107). The proposed elevation of the lower level for Building 8 is Elev. 111.67.
Fluctuations in groundwater seepage levels should be expected on a seasonal and annual basis.
Typically, groundwater seepage reaches maximum levels during and following- the wet winter months,
and diminishes or is completely absent during the dry summer months. We did not observe
groundwater seepage in Test Pits TP-1 and TP-2 (located in the areas of Borings B-101 and B-102,
respectively), which were.excavated to a depth of about 14 feet in mid -October 2.00 1.
DISCUSSION
Based on our review of existing topography, proposed grades, and the planned building elevations, it
appears that temporary shoring will be required to complete the southwestern portion of the excavation
for Building 4. Soils encountered in Boring B-102, in the southwestern portion of.Building 4, consist of
approximately 13 feet of very loose to medium dense fill and medium.dense native silty sand overlying
very stiff to hard clay. As discussed in our referenced geotechnical report, the loose to'niedium. dense.
fill and native silty sand soils should be laid back at a , minimum slope inclination of 1-5:1
(Horizontal:Vertical). Ternporary slopes in the very stiff to,hard clay can be completed with a gradient
of 0.7S: 1. Based on the depths that we encountered these.soils in Boring B-102, excavations completed
to these temporary, inclinations at the southwestem comer of, Building 4 would encroach about 40 feet
into the Pine Street night -of -way and about 16 feet into the existing paved roadway.
Excavation to the proposed lower floor elevation in the southwestern portion of Building 3 will expose
primarily medium dense silty'sand with varying amounts of gravel. Temporary excavations in these
soils that are graded to an inclination of LS- I will extend about 27 feet into the Pine Street right-of-way
at the southwestern comer of the building, but would not encroach into the existing roadway.
the soils in the area of Building 8 consist of existing fill, native silty sand, and very stiff clay/dense- silt.
Based on the information provided to us, it appears that temporary excavations for Building . 8 that are
sloped to an inclination of 1.5:1 will not encroach into the Pine Street- night -of -way. - We expe ct that the
lower portion of the excavation for Building 8 will exposed very stiff clay/dense silt, and may be graded
to a temporary inclination of 0.75: 1.
Project No. T-4893
Page No.3
d.� �.
Mr. Ross Woods
July 30, 2003.
I
Subsurface information obtained from our previous geotechnical studies indicates that the soils near the
western side of Building 5 consist of existing fill and native, medium dense silty sand to approximately
Elev. 86. The soils below this elevation are very stiff to hard clay/de*nse silt. Based on the iiftformation
provided to us, it appears that the. major portion of the excavation for. Building 5 will expose granular
silty sand soils. Temporary excavations sloped to an inclination of 1.5:1 will encroach very near the
centerline of the proposed loop road located immediately south of the building, and would extend about
five feet over the centerline near the'southwestem comer of the building. We understand that there will
be some flexibility with excavating'� into the' loop road during site development however, if
encroachments into the proposed roadway of this magnitude cannot be tolerated, temporary shoring will
be needed.
The excavation for Building 8 is -likely to encounter minor groundwater seepage at various levels below
8.5 feet. Considering the fine-grained nature -of the on -site soils, we do not believe the amount of
seepage will be excessive. ' In addition, if adequately protected ftom erosion, we do not expect that
seepage will adversely affect the stability, of the temporary slope. However, the contractor should be
prepared to provide clewatering measures for. the excavation. In our .. opinion, conventional sump
pumping procedures should be capable of maintaining a relatively dry.conclition for the excavation.
Temporary shoring will be, required where site constraints do not allow sloping of temporary
excavations to the inclinations * discussed above. Temporary shoring' systems 'include a. tied -back or
cantilever soldier pile wall and soil -nailing 'with top -clown. wall construction. Considering the presence
of as much as 13 feet of loose, uncontrolled fill near the southwestern comer of Building 4, and the
proximity to a public right-of-way,. it is our opinion that temporary shoring should consist of a tied -back
or cantilever soldier pile wall. Descriptions of the shoring method and detailed desigri parameters are
presented below.
The following sections provide detailed recommendations regarding these issues and other geotechnical
design considerations. These recommendations should be incorporated *into the final design drawings
and construction specifications.
Shorin2
As discussed, temporary- shoring will be required where there is insufficient room to complete an open
excavation to the inclinations discussed in the preceding section. Overconsoliclated clay/silt will be
encountered befow-the fill and granular native soils. During the excavation, soil e'xp ansion resulting
from release of locked -in stresses combined with horizontal planes lacking cohesion may -cause-
horizontal slippage at a newly opened excavation.. - Based on our e xperience, the newly opened vertical
face should not be left open more than.48 hours. Tirnber lagging should be installed within 48 hours to
prevent horizontal slippage. Detailed re . commendations for conventional soldier pile walls with timber
lagging are provided below.
Project No. T4893
Page No. 4
Mr. Ross Woods
July 30, 2003
Soldier Pile Shoring
Tied -back or cantilever soldier walls should be designed to resist lateral loads imposed by soils, as well
as the vertical load component. Vertical loads may be carried by the soldier piles as end bearing and as
pile shaft fr iction below the base of the excavation. Pile shaft friction should not be used above the base
of the.excavation. The following infon-nation is applicable to soldier pile walls:
Bearing materials:
-.1 hard lean clay
Minimum depth of embe* dment below excavation base: 10 feet
Allowable end bearing capacities for soldief piles: 20 kips per square foot (ksf)
Skin friction below excavation base:
1.0 ksf
We recommend soldier piles have a maxiinum.center-to-center spacing of eight feet. To account for
arching effects, lateral loads on the lagging. can be reduced by 50 percent. Design parameters for the
,recommended temporary shoring are presented on Figures 12 and 13.
Tieback Anchors
Tieback anchors should be installed in the soil behind the excavation to a sufficient d - istance to allow
mobilizing the desired lateral load resistance. The soils in the anchor zone are expected to consist of
very stiff to hard lean clay. We recommend. the use of the following de . sip adhesion values for
properly installing non -pressure grouted anchors.
Allowable Adhesion: 1.0 ksf, along the bonded length
The bonded length is the portion of the anchor that extends beyond the no-load zone, as shown on
' I figure 14. Within the no-load zone, anchors should be sleeved and left ungrouted to prevent load
pickup in this region.
All anchors should be tested to verify design capacities. As a minimum, all anchors should be. stressed
to 130 percent of their design capacity and then locked. off at the design load. . At least 10 percent of the
anchors, with a minimum of 2 anchors, should be prooftested and stressed to 200 percent of'the design
pullout capacity. The gebtechnical engineer should select the locations of these test anchors.
Groundwater seepage may be encountered during the installation of the anchors. The presence of water
could result *in some caving of the anchor holes. Drilling with continuous flight augers or the'use of
casing Would reduce the potential for ground loss.
The contractor should particularly note the presence of existing facilities adjacent to the subject site,
including buried utilities, as they may affect the location or extent of the anchor holes.
Project No. T-4893
Page No. 5
Mr. Ross Woods
July 30, 2003
Monitoring Program
A monitoring program must be implemented to verify the perfonnance of the shoring system. Utilities
within a distance of 1.6 H (where H is the depth of excavation) from the shoring wall should be
protected from damage due to the lateral and vertical movement occ urring around the excavation area.
Monitoring of the shoring system should include measurements of horizontal and vertical movements at
the top of soldier piles. All reference points on the existing ground surface should be installed and read
prior to commencing the excavation.
Monitoring of the shoring system should be performed twice a week as the excavation proceeds, and
% then every other week upon completion of the excavation. A registered land surveyor should be
retained to perform the monitoring. Monitoring should continue until the basement walls are adequately
6raced at the ground surface level. Themonitoring data should be reviewed weekly by the project's
structural and geotechriical engineers.,
All recommendations presented in out earlier report should also be incorporated *into project design'and
construction.
We trust the information presented is sufficient for your current needs. If you have any questions or
require additional information, please call.
Sincerely yours,
TA/JCS/AB -aVWVVVv
�E_;T;FIES IM/
. . . ...... n c).
. gures I ana 2_ — Exploration Location Plans
Figure 3 -- Unified Soil Classification System
Figures 4 through 9 — Boning and Test'Pit Logs
Figures 10 and I I — Grain Size Analyses
Figure 12 —Earth Press ure Diagram
Figure 13 _* Earth..Pressure Diagram
Figure 14 — Load/No Load Zone Diagram
Figure 15 — Earth Pressure Diagram -Basement Walls
cc: Ms. Beth Jensen, DO Engineers
Project No. T-4893
Page No. 6
-1
"b
.EV.
�4075= -
f.7 BLDG I
APPROXIMATE PERIMETER
OF LOWER LEVEL
LOWER LEVEL ELEV/��.67
BLDG. 4
x\1 LOWER LEVEL ELEV. 100.66
TP 2
. . . . . . . . . .
0\
APPROXIMATE PERIMETER
OF LOWER LEVE
z7-
\'�-BLDG3\
LOWER LEVEL ELEV. 101.17
-101
BLDG, 10E,
LOWE LEVEL ELEV. 134.84
.......... ":�
J64AJLX]�� N�-
M, 1111
77-
NOTE:
THIS SITE PLAN IS SCHEMATI ' C. ALL LOCATIONS AND
DIMENSIONS ARE APPROXIMATE. IT IS INTENDED FOR
REFERENCE ONLY AND SHOULD NOT BE USED FOR
DESIGN OR CONSTRUCTION PURPOSES
REFERENCE:
SITE PLAN PROVIDED BY TRIAD ASSOCIATES, DATED 7-21-03
LEGEND:
S B-1 APPROXIMATE LOCAT ION OF BORING
IS TP-1 APPROXIMATE'LOCATION OF TEST PIT
0 50 100
APPROXIMATE SCALE IN FEET
___ 0_2
Z - - - - - -
- - - -- - - - - - -- - - - - - - - - -
- - - - - - - - - - - -
777
TP-1 B-C -----------
j
APPROXIMATE PERIMETER
------------- OF* LOWER LEVEL-
BLDG. 5 -7z.
----------
LOWER LEVEL ELEV. 82.17
----------
Z_
Z \pl�\Dq 2\
0( LOWER LEVEL ELEV. 74.66
T
APPROXIMATE PERIMETER A
OF LOWER LEVEL
BLDG.8
-LOWER LEVEL ELEV. 111.61f
4
APPROXIMATE PERIMETER
\BLDG.4/
OF LOWER LEVEL
J; TP LOWER LEVEL ELEV. 100.66
2
ga- a v&
aw
>
IN
'APPROXIMATF;
NOTE: LEGEND:
THIS SITE PLAN IS SCHEMATIC, ALL LOCATIONS AND
DIMENSIONS ARE APPROXIMATE IT IS INTENDED FOR
REFERENCE. ONLY AND SHOULD NOT BE USED FOR B-1 APPROXIMATE LOCATION OF TEST BORING EXPLORATION. LOCATION PLAN
DESIGN OR CONSTRUCTIONPURPOSES. IN TP-1 APPROXIMATE LOCATION OF TEST PIT Terra POINT EDWARDS CONDOMINIUMS
REFERENCE:' 0 50 100 Associates Inc. EDMONDS, WASHINGTON.
G;;;;;g Consultants in Geotechnical Ingineering
SITE PLAN PROVIDED BY TRIAD ASSOCIATES, DAED 7-21-03 Geology and Proi. No. -=4893Date JULY 2003' Figure 2
APPROXIMATE SCALE IN FEET Environmentil Earth Sciences
MAJOR DIVISIONS
LETTER
TYPICAL DESCRIPTION
SYMBOL
Clean
GW
Well -graded gravels, gravel -sand mixtures, little or no
GRAVELS
Gravels
fines.
GP
Poorly -graded -gravels, gravel -sand mixtures, little or
0)
(less than
.0
" (D
n N
More than
5% fines)
no fines.
—
GM
Silty gravels, gravel -sand -silt mixtures, non -plastic
U) Z-5
50% of coarse
fraction is
0
W
a)
>
�.a)
larger than No
Gravels
with fines
fines.
z
Fn
E
4. sieve
GC
Clayey gravels, gravel -sand-clay mixtures, plastic fines.
<
C)
-0 C:)
0 C14
Clean
SW
Well -graded sands, gravelly sands, little or no fines:
LC) 6
SANDS
Sands
SP
Poorly -graded sands or gravelly sands, litde or no
W r-Z
60 cu
(less than
-C C:
More than
5% fines
fines.
<
5 0% of coarse
0
0
fraction is
SM
Silty sands, sand -silt mixtures, non -plastic fines.
smaller than
Sands
SIC
Clayey sands, sand -clay mixtures, plastic fines.
No. 4 sieve
with fines
ML
Inorganic silts, rock flour, clayey silts with slight
C:)
SILTS AND CLAYS
plasticity.
CL
Inorganic clays of low to medium plasficity, (l,ean clay).
C
0 �N
M
W
E
Liquid limit is less than 50%
0
W
Z
Z N
OL
Organic silts and organic clays �of low plasticity.
U-)
<
CU
MH
Inorganic silts, elastic.
(n
SILTS AND CLAYS
1
W
CU
'. f=-
CH
Inorganic clays of high plasticity, fat clays.
Z
0 (n
Liquid limit is greater than 50%
ILL
OH
Organic clays of high plasticity.
HIGHLY ORGANIC SO] LS
PT
Peat.
DEFINITION OF TERMS AND SYMBOLS
Standard Penetration
Density Resistance in Blows/Foot
2" OUTSIDE DIAMETER SPLIT
W
SPOON SAMPLER
_j
z
0
Very loose 0-4
2.4" INSIDE DIAMETER RING SAMPLER
Loose 4-10
OR SHELBY TUBE SAMPLER
W
Medium dense 10-30
M,
0
Dense 30-50
WATER LEVEL (DATE)
Very dense >50
Tr TORVANE READINGS, tsf
Pp PENETROMETER READING, tsf
Standard Penetration
W
Consistenc Resistance in Blows/Foot
DID DRY DENSITY, pounds per cubic,foot*
>
co
Very soft 0-2
LL LIQUID LIMIT, percent
W
Soft 2-4
0
Medium stiff 4-8
PI PLASTIC INDEX
stiff 8-16
-Very stiff 16-32
N STANDARD PENETRATION, blows per foot
Hard >32
Terra
UNIFIED SOIL CLASSIFICATION 'SYSTEM
Associates, Inc.
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
P roj. No. T-4893
Date JULY 2003
Figure 3
Geology and
Environmental Earth Sciences
Boring No'. B-101
4
Logged by: TA
Date: 6/18/03 Approximate Elev. 105
Soil Description
Consistenby/
Relative
Depth
CL
E
(N)
Blows/
'Moisture
Content
Density
U)
0
ft.
- N
FILL: dark brown silty sand with gravel, moist. (SM)
Dense
30
10
Brown silty SAND, trace gravel, with oAdized stained,
moist. (SM)
Brown mottled gray between 2.5 to 4.0 feet.
Medium
Dense
5
17
11
12
15
Gray, lean CLAY, trace subrounded gravel, moist. (CL)
7
?0
—10
Medium
-
22
27
stiff
to
Occasional ligh . t gray silt seams below 15 feet.
Hard
—15
20
35
44
26
25
Gray silty SAND, wet. (SM)
Dense
Gray, lean CLAY with light gray SILT seams.
Hard.
—25
32
.29
Boring terminated at 26.5 feet.
Groundwater seepage encountered at 21 feet.
Terra
BORING'LOG
'Assodates, Inc.
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
POINT EDWARDS CONDOMINIUMS
EDMONDS; WASHINGTON
Proj. No. T-4893,
Date JULY 2003
Figur
Boring No. B-102
Logged by: TA
Date: 6/18/03 Approximate'E.lev. 125
Soil Description
Consistency/
Relative
Depth
-a
E
(N)
Blows/
Moisture
Content
Density
(ft.)
ft.
N
15
19
FILL: brown silty sand, trace gravel/clayey silt, moist.
(SM/ML)
Medium
Dense
to
Very
Loose
—10
13
9
3
2
24
5
7
11
10
23'
Gray, lean CLAY, occasional light gray silt and sandy
silt seams (1 to 2 mm), moist. (CL)
20
22
31
0.5 inches light gray sandy silt seam at 26 feet.
Very
stiff
29
36
0.5 inches sand seam at 30.5 feet.
30
33
26
29
27
38
25
Gray SAND with silt, free water. (SM)
Dense --40
Gray, lean CLAY, moist. (CL)
37.
27
50
32
25
Boring terminated at 51.5 feet.
Groundwater encountered at 40 feet.
Terra
BORING LOG
Associates, Inc
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
POINT EDWARDS CONDOMINIUMS
EbMONDS, WASHINGTON
Proj. No. T-4893
Date JULY 20031
�igure 5
Boring :No. B-103
Logged by: TA
Date: 6/18/03
Approximate Elev. 129
Soil Description,
Consistency/
Relative
Density
Depth
-a
E
U)
10
(N)
Blows/
ft.
Moisture
Content
N
Notes
CRUSHED GRAVEL
Dense
36
11
15
2
17
28
FILL: dark gray clayey SILT/silty SAND,
trace gravel, moist. (MUSM)
Medium
Dense
Brown silty SAND to SAND with silt,
free . water. (SM)
Medium
Dense
T
10
1.6
22
24
36
Gray lean CLAY, moist. (CL)
Brown lean CLAY with oxidized stained
between 15.0 to 15.5 feet.
Very
—15
31
28
............
Wet soils encountered at 21.5 feet.
stiff
to
— 20
V...
30
24
.............
........
.......
Hard
Occasional light gray silt and silty sand seams
encountered below 25 feet.
25
28
32
.............
.............
...
.............
I ......
: ............
........
....
—
.
4 inches sand seam at 31 feet.
30
35
23
.........
. .........
.........
..............
.......
.......
.
.
35
.........
T
41-
29
............
.........................
.
.......
Boring terminated at 36.5 feet.
Groundwater seepage encountered at 8.5 feet.
Water level at 22.15 feet on June 19, �003.
Terra
BORING LOG
Associates. Inc.
9
POINT
EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
Proj. No. T-4893.
Date JULY 20031
Figure 6
Boring No. B-4
Logged by: DPL
Date: 12/16/02 Approximate Elev. 90
Soil Description
Consistency/
Relative
Depth
CL
E
(N)
Blows/
Moisture
Content
Density
(ft.)
UM)
ft.
M
FILL (Old test pit): b.luish-gray silty sand, fine grained,
wet, with a trace of wood particles. Appears disturbed.
Loose
7
27
FILL (Old test pit): mottled brown silty sand, fine grained, moist.
Medium
Dense
1.0
T
17
21
31
FILL (Old test pit): brown silt and clay, moist, with a trace
of brown organic material.
--------------------------------------------------------------
Very
Stiff
_T
:T
Bluish-gray SILT to CLAY, low to medium plastici ty.
(MUCL)
Very
stiff
17
28
Gray SILT to CLAY, moist, low to medium plasticity.
(MUCL)
Very
stiff
20
30
23
LL = 35.5
PI = 11.5
.Grayish -brown sandy SILT to clayey SILT, fine grained,
moist. (ML) With thin partings of iron -stained, fine-grained
sand.
Very
stiff
35
23
Grayish -brown clayey SILT to silty CLAY, moist. (MUC L)
With thin discontinuous lenses of gray to mottled gray
ined sand.
-------------------------------------------------------------------------------------
Very
stiff
—30
30
24
Gray silty SAND, fine grained, moist. (SM)
Dense
37
15
------------------------------------------------------------------------- --------------------------
Gray sandy SILT to clayey SILT, fine grained, moist, low
plasticity. (ML to MUCL)
Hard
—40
34
17
Gray clayey SILT, moist, low plasticity. (MUCL)
---- Trace fine-gc@i0_Qd_ sand
Hard
37
20
Gray sandy SILT to silty SAND, fine grained, moist,
(MUSM).
Dense
—50
32
19
47
18
60
42
15
Boring terminated at 61.5 feet.
No significant groundwater encountered.
Terra
BORING LOG
Associates, lnc.�.
POINT. EDWARDS CONDOMINIUMS.
EDMONDS, WASHINGTON
Consultant in Geotechnical Engineering
Geology and
Environmental Earth Sciences
Proj. No. T-4893
Date JULY 2003 1
Figure 7
Test Pit -No. TP-1
Logged by: JCS Approximate Elev. 104
Date: 10/18/01
Dep . th Moisture
(ft.) Soil Description Content
0- N
FILL: crushed rock surfacing over brown to gray silty,sand to sandy silt, fine grained,
firm, moist. (SIVI/IVIL)
Rusty brown silty SAND fine grained, medium dense, moist, With occasional fine
\gravel and fine roots. (W)
Gray to mottled. gray silty'SAND., fine grained, medium dense to dense,
5 moist, With occasional fine gravel. (SIVI)
Becomes light brown at approximately 6 feet.
10 Gray CLAY, hard, moist, massive. (CL) 26 1 PP = 4.5+
tons/ft'
LL 35.8
P, 15
15-1 Test pit terminated. at 14 feet.
No groundwater seepage.
20
Test Pit No. TP-2
Logged by: JCS Approximate Elev. 124
Date: 10/18/01
Depth Moisture
Content
Soil Description
0 FILL: crushed rock surfacin over brown silty sand to sandy silt, fine grained, firm,
moist. 4-inch.thick organic Ver at base. (SM/ML) (Old topsoil horizon)
Brown silty SAND, fine grained, medium dense, moist. (SM)
Mottled grayish -brown silty SAND, fine grained, medium dense, moist. 20
(SM)
5
Grayish -brown silty SAND, fine grained, medium dense to dense, moist.
I (SM)
10 1 Gray CLAY, ha rd, moist, laminated with light gra y silt partings. (CL)
15 Test pit terminated at 14 feet.
No groundwater seepage.
20
Terra
Associates, Inc.
Geotechnical Consultants
Pp = 4.5+
tons/ft'
37
TEST PIT.LOGS
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Proj. No. f-4893 Date JULY 2003 1 Figure 8
Test Pit No. TP-4
Logged by: JCS Approximate Elev. 92
Date: 10/18/01
Moisture
Depth Content
. (ft.) Soil Description N
0 '1 FILL: liqht brown silty sand, fine grained, firm, dry to moist. (SM) 2-inch thick I
Light brown to tan sitty SAND, fine grained, medium dense to dense, dry.
(SM)
Mottled grayish -brown silty SAND, fine grained, medium dense to dense, 29
5— moist. (SM)
LL = 42.7
Light grayish -brown to light brown CLAY and SILT, hard, moist, laminated 29 PI = 19.7
with partings of dark gray fine sand. (CUML) PP = 4.5+
tonsife
.10-
- Gray CLAY, hard, moist. (CL) PP = 4.51
29 tons/fe
151 Test'pit terminated at 13 feet.
Trace groundwater seepage at 6 feet.
TEST PIT LOGS
Terra POINT EDWARDS CONDOMINIUMS
Associates, Inc. EDMONDS, WASHINGTON
Geotechnical Consultants
Proj. No. T-4893 I Date JULY 2003 1 Figure 9_
\1
CANTILEVER SOLDIER PILE WALL OR
SINGLE ROW TIEBACK WALL
H
Pass I ve Earth
Pressure = 400 pcf
taken over 2 pile
diameters
Note:
Value ncludes
Safety Factor of
1.5. D
40* pcf + 75 psf
Traffic Surcharge
Where Applicable
40(H)* psf taken over pile diameter
NOT TO SCALE
* INCREASE PRESSURE BY 20 PERCENT WHERE WALL IS
SURCHARGED BY BACKSLOPE� OF 2:1. (HORIZONTAL:VERTICAL)
OR FLATTER.
Terra' EAR - TH PRESSURE DIAGRAM
POINT EDWARDS CONDOMINIUMS
Associates, Inc. EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences Proj. No. T-4893 I Date JULY 2003 Figure 12
SOLDIER PILE WALL WITHTWO
OR MORE TIEBACKS
400 pcf/ft PASSIVE EARTH
PRESSURE APPLIED OVER 2(D)
NOTE:
VALUE INCLUDES SAFETY
FACTOR OF 1.5
0. 2' (H)
15' —,.,,,-75 psf UNIFORM
PRESSURE TRAFFIC
H SURCHARGE WHERE
APPLICABLE
23 (H)* psf APPLIED OVER PILE SPACING
23 (H)* psf APPLIED OVER PILE DIAMETER
d, D �--
NOT TO SCALE
* INCREASE PRESSURE BY 26 (H) WHERE WALL IS
SURCHARGED BY BACKSLOPE OF. 2:1 (HOR IZO NTAL:VERTI CAL)
OR FLATTER.
Terra EARTH PRESSURE DIAGRAM
POINT EDWARDS CONDOMINIUMS
Associates, Inc. EDMONDS, WASHINGTON,
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences Proi. No. T-41893 Date JULY 2003 Figure 13
IF
it
TIEDBACK SOLDIER PILE/LAGGING SHORINGWALL
NO LOAD ZONE
15-(TYPICAL)
ANCHOR
ZONE
TIEBACKS NOT GROUTED
IN THIS ZONE
H/3 --] ^,,' 60-
TIEBACKS GROUTED
IN THIS ZONE
ALLOWABLE TIEBACK
ADHESION CAPACITY IN
ANCHOR ZONE=1000 psf
NOTE:
TIEBACK CAPACITIES ARE BASE ON INSTALLATION
USING TREMIE GROUT METHOD
NOT TO SCALE
Terra LOAD/NO LOAD ZONE DIAGRAM
POINT EDWARDS CONDOMINIUMS
Associates, Inc. EDMONDS,. WASHINGTON
Consultants in Geotechnical Engineering
Geology and Date JULY 2003 Figure 14
Environmental Earth Sciences Proj. No. T-4893F I
. N
H
EARTH PRESSURE DIAGRAM FOR BASEMENT WALLS
-IC .
HARGE
E
CABLE
Sf
NOT TO SCALE
*INCREASE PRESSURE TO 26 (H) WHERE WALL IS SURCHARGED
BY BACKSLOPE OF 2:1 (HORIZONTALMERTICAL) OR FLATTER.
Terra. EARTH PRESSURE DIAGRAM -BASEMENT WALLS
POINT EDWARDS CONDOMINIUMS
Associates, Inc. EDMONDS, -WASHINGTON
Consultants in Geotechnical * Engineering
Geology and
Environmental Earth Sciences Proj. No.T-4893 I Date JULY �003. Rpre 15
TERRA ASSOCIATES, Inc.
Consultants in Geotechnical Engineering, Geology
. and
Environmental Earth Sciences
July 30,'2003
Project No. T-4803
Mr. Ross Wdods
Point EdwarUs, LLC
1
2801 Alaskan Way, Suite 107
Seattle, WagLngton 98121
Subject- Supplementary Subsurface Exploration
Point Edwards Condominiums
P�ne Street and Unoco Road
Edmonds, Washington
References: 1. Geologically Hazardous Areas Review, Point Edwards Condominiums (LNOCAL
Site), prepared by Terra Associates, Inc., dated January 20, 2003
2. Preliminary Geotechhical Report, UNOCAL Site, Project No. T-4893, prepared by
Terra Associates, Inc., dated November 21, 2601
D Mr. V
ear Woods:
As requested, we have completed supplementary subsurface exploration at the subject site. The purpose
of our study is to evaluate the needf5r temporary shoring during construction of theproposed buildings,
and to Provide recommendations for temporary shoning design and construction where needed. We
previouslyA performed geotechrucal studies for the project and presented our findings in the referenced
ho
reo . orts; ? wever, since that time, building locations and site grading hav e been refined. Triad
Associates provided us with a current topographic site plan dated July 21, 2003 that shows existing.
topography and proposed site grading.
Our cu7ffent study focused on areas where' significant site. excavations will be required adjacent the
downgfadient (northern) -side of Pine Street, in the areas of Buildings 3, 4, and 8*, and the area of
Building 5 located north of Building 8 and the private loop road. Pine Street is curren . fly one . of two
road�waykqtiiat -access the community of Woodway, south of the site. This report summarizes the results
of our, recent subsurface exploration and discusses supplementary, shoring recommend.4R
EeEi
VED
project.
0 C T 2 C
STREET FILE
BUILDING bEPT.
12 ' 525 Willows Road, Suite 101, Kirkland, Washington 98034,
Phone,(425) 821-7777 - Fax (425) 821-4334 * terra@terra-associates.com
Mr. Ross Woods
July 30, 2003
PROJECT DESCRIPTION
The project will consist of the construction of ten condominium buildings. The proposed structures will
be three four stories with daylight, basements and one to two . levels' of underg . round parking. We
expect fhat pen -meter load -bearing walls and isolated spread footing loads will be as indicated. in the
for construction of the lower parking levels. will
referenced report. The excavation depths required
appro dch a: maximum of about 27 feet below existing grades along Pine Street.
The recommendations contained in'the. follow mig sections of this report are based on ourunderstanding
of' the allove design features. If actual features vary or changes are made, we should review them in
iL
order to M, odify our -recommendations, as required. We should review final -design drawings and
specifications to verify that.our recommendations have been properly interpreted and, incorporated into
ign.
project des' I
CONDITIONS
iously investigated subsurface conditions at the site by excavating 17 test pits (Test Pits TP-1
We previ
AP
through �P-.l 7) and drilling 5 test borings (Bonings B- I through B-5): - Our current exploration'included
drilling three additional test borings (Borings B401 through B-103) on June 18, 2003.
W
The'rece*nt borings were drilled on the north side of Pine Street, where significant. excavations will be
required for construction of the lower parking levels of Buildings 3, 4, and 8. These.test bonings were
advancea. to a maximum depth of approximately 5 1.5 feet below the ground- surface. The approximate
r
locations of the recent test borings, and, nearby -test pits/test borings from our previous studi.es, are
shown onVFigures I and 2. The boring logs and test pit togs are shown on Figures 4 through 1 9. We
performed grain size . analyses on three representative soil samples obtained from t.he test borings. The
test results are presented on Figitres 10 and 11.
The soils encountered in Borings B-101, B-102, and B-103 consist of I to .13 feet -of very loose. to
mediiii-Odense uncontrolled fill overlying medium dense, native silty sandwith varying amounts of
gravel t epths betwe n approximately, 7 and 13 feet below the ground surface. The fill and- silty sand
soils are underlain by. very stiff to hard, lean clay with thin partings of light gray silt and/or very fine-
grained silty sand searris to the: maximum exploration depths of the borings. These soil conditions are
a
generall
Jy consi�tdnt with the soils we observed in nearby test pits.
'The Gjologhq Map of the Edmonds East and Partof the Edmonds West Quadran&s, Washington. by
James P. Minard,'1983, shows the soils at higher site elevations mapped as Vashon till, Vashon.advance
outwast and Transition . al . beds. Transitional -bed sediments are described by this ive
publication,as mass'
to bedded clay, silt, and fine to very fine sand. The clay and silt soils observed at depth in, the test pits
and encountered in the test bonngs are generally consistent with 'the descriptions of transitional bed
deposits.
Project No. T-4893
Page No. 2
A
Mr. Ross Woods
July 36, 2003
We encountered per ched groundwater in all three of the recent bonings near the interface of the surficial
fill/silty sand soils and the underlying very stiff to hard clay, and in thin sand layers within the very stiff
to hard clay. We also observed indications of localized light seepage from the face of the existing slope
between proposed Buildings 4 and 8.
The perched groundwater encountered in Borings B-101 and B-102 occurs at elevations at least 15 feet
below the lo . wer elevations of Buildings 3 and 4 (Elev. 101.47 and Elev. 100.66, respectively). Boring
B-103 (drilled in the area of Building 8) encountered two levels of perched groundwater.. The upper
perched groundwater level Is approximately 8.5 feet below the ground surface (approximately Elev.
120.5), and the lower level is approximately 22 feet below the ground surface (approximately Elev.
107). The proposed elevation of the lower level for Building 8 is. Elev. 111,67.
Fluctuations in groundwater seepage levels should be expected on a seasonal' and annual basis.
Typically, groundwater seepage reaches maximum levels during and following- the wet winter months,
and diminishes or is completely absent during the dry surnmer months. We did not observe
groundwater seepage. in Test Pits TP-1 and TP-2 (located in the areas of Borings B-101 and B-102,
respectively), which were excavated to.a depth of about 14 feet in mid -October 200 1.
DISCUSSION
Based on our review of existing topography, proposed grades, and the planned building elevations, it
appears that temporary shoring will be required to complete the southwestem portion of the excavation
for Building 4. Soils encountered in Boring B- 102, M* the southwestern portion of Building 4, consist of
approximately 13 feet of very loose to medium dense fill and niedium dense native silty sand overlying
very stiff to hard clay. As discussed in our. referenced geotechnical report, the loose t6medium dense.
fill and native silty sand soils should be laid back at a minimum slope inclination of 1.5:1
(Horizontal: Vertical). Temporary slopes in the very stiff to hard clay can be completed with a gradient
of 0.75: 1. Based on the depths that we encounteredthese soils in Boring B-102, excavations:completed
to these temporary inclinations at the southwestern comer of Building 4 would encroach about 4,0 feet
into the Pine Street night -of -way and about 16. feet into the existing paved roadway.
Excavation to the proposed lower floor elevation in the southwestern portion of Building.3 will expose
primarily medium dense silty'sand with varying amounts of gravel. Temporary excavations in the . se
soils that are graded to an inclination of 1.5:1 will extend about 27 feet into the Pine Street right-of-way
at the southwestern comer of the building, -but would not encroach into the existing roadway.
The soils in the are -a of Building 8 consist of existing fill" native silty sand, and very stiff 6 lay/dense-silt.
Based on the. information provided to us, it appears that' temporary excavations for Building 8 that are
sloped to an inclination of 1.5:1 will not encroach into the Pine, Street- right-O'f-way. - We expect that the
lower portion of the. excavation for Building 8 will exposed very stiff clay/dense silt, and may be graded
to a temporary inclination of 0.75: 1.
P.roj* ect No. T-4893
Page No. 3
Mr. Ross Woods
July 30, 2003
Subsurface information obtained from our previous geotechnical studies indicates that the soils near the
western side of Building 5 consist of existing fill and native, medium. dense silty sand, to. approxiniately
Elev. 86. The soil's below this elevation are very stiff to hard clay/de'nse. silt. Based on the information
provided to us, it appears that the major portion of the excavation. for Building 5 will, expose granular
silty sand soils. Temporary excavations sloped to an . inclination of 1. 5: 1 * will encroach very near the
centerline' of the proposed loop road located inu-nediately south of the building, and would extend about
five feet over the centerline near the southwestem comer of the building. We understand that there will
be some, flexibility with excavating into the loop road during site d6velopmeint; however, if
encroachments 'into the proposed, roadway of this magnitude cannot be tolerated, temporary shoring will
be needed.
The excavation for Building 8 is likely to encounter minor -groundwater seepage, at various levels. below
8.5 feet. Considering the fine-grained nature of the, on -site soils, we do not believe the amount of
seepage will be excessive. _ In addition, if adequately protected from erosion, we do not expect that.
seepage will adversely. affect the stability, of the temporary slope. , However, the 'cohtractor.sh�ould be
prepared to provide dewatening measures for the excavation. In our opinion, conventional sump
pumping procedures should be capable of maintaining a relatively dry.conditi6n f6r the excavation.
Temporary shoring will be- required where site constraints do not - allow 'sloping of temporary
excavations to the inclinations discussed above.. Temporary shoring systems '-include a.tied-back or
cantilever soldier pile wall and soil nailing with top -down wall construction. Considering the p resence
of as much as 13 feet of loose, uncontrolled fill near the southwestern comer of Building 4, and the
proximity to a public right-of-way, it is ouropinion that temporary shoring should consist of a tied -back
or cantilever soldier pile wall. Descriptions of the shoring method and detailed design 'parameters are
presented below.
The following sections provide detailed recommendations regarding these is.sues.�and other geotechnical.
design considerations. These recommendations should be incorporated intothe final design drawings
and construction specifications.
Skoring
As discussed, temporary shoring will be required where there is insufficient room.tb complete an open
excavation to. the inclinations discussed in the preceding section. -OVerconsolidated clay/silt.Will . be
encountered below the fill and granular native soils. During the excavation, soil -expansion r . esulting
from release. of locked -in stresses combined with horizontal planes 'lac'king cohesion may cause
horizontal slippage at a newly opened excavation.. Based on our experience, the newly opened vertical
face should not be left open more than 48 hours. Timber. lagging should be installed within 48 hours . to
prevent horizontal slippage. Detailed re I cornmendations for conventional soldier pile, walls with timber.
lagging are provided below.
Project No..T-4893-
Page -No. 4
I
Mr. Ross Woods
July 30, 2003
Soldier Pile Shoring
Tied -back or cantilever soldier walls should be designed toresist lateral loads imposed by. soils, as, well
as the vertical load component. Vertical loads may be carried b the, soldier piles as end bearing and as
Y.
Pile shaft friction below the base of the excavation. Pile shaft friction should not be used above the base
of the excavation. The following information isapplicable to soldier pile walls:
Bearing materials: hard lean clay
Minimum depth of embedment below excavation base' 10 feet
Allowable end bearing capacities for soldier piles: 20 kips per square foot (ksf)
Skin friction 'below excavation base: 1 ..0 kif
We recommend soldier piles have a maximum center -to -center spacing of eight f�et. To account for
arching,tffects, lateral loads on the lagging, can be reduced by.5.0 percent. Design parameters for the
recommended temporary shoring are presented on Figures 12 and 13.
Tieback Anchors
Tieback anchors should be installed in the soil behind the excavation to a sufficient distance to allow
mobilizing the desired lateral load resistance. The soils -in the anchor zone are ex * cted to consist of
pe
very stiff to hard lean clay. We recommend the use of the following- design adhesion values for
proper�y installing non -pressure grouted anchors.
!Allowable Adhesion: 1.0 ksf, along the bonded length
The bonded length is the portion.of the -anchor that extends beyond the no-load zone, as shown on
Figure 14. Within the no-load zone,'anchors should be sleeved. and left ungrguted to prevent load
pickup in this region.
All anchors should be tested to verify design capacities-. As a minimum, all anchors should be. stressed.
to 130'p.ercent of their design capacity and then locked. off at the. d0tgn load. . At least 10 pe.rcent:6f the
anchors, with a minimum of 2 anchors, should be prooftested and stressed to 200 percent of'the design
pullout capacity. The geotechnical engineer should select the locations of these- test anchors.
Groundwater seepage may be encountered during the installation,of the anchors. The presence of water
could result ii-i some caving of the anchor holes.. Drilling with continuous flight a gets. of- the use of
u
casing w"ould reduce the potential, for ground- loss.
The contractor,*should particularf
y note the,presence of existing fiLcilities adjacent to the subject site,
including buried utilities, as they may affect the location orextent of the anchor holes.
Project No. T4893
Tage No. .5
Mr. Ross Woods
July 30, 2003
Monitoring Program
A monitoring program must be implemented to verify the performance of the shoring system. Utilities
within a distance of 1.0 - H (where H is the depth of excavation) from the shoring wall should be
protected from damage due to.ihe lateral and vertical movement occurring around the excavation area.
Monitoring of the shoring system should include measurements of horizontal and vertical movements at
the top of soldier piles. All reference points on, the existing ground surface should be installed and read
prior to commencing the excavation.
Monitoring of the shoring system should be performed twice a week as the excavation proceeds, and
then every other week upon completion of the excavation. A registered, land, surveyor should be
retained to perform the mo nitoring. Monitoring should continue until the basement walls are adequately
braced at -the ground surface level. The monitoring. data should be reviewed weekly by the project's
structuraliand geotechnical engineers.,
All recommendations presented in out earlier report should also be incorporated 'into pr ject design and
01
construction.
We trust the information presented is sufficient for your,current nee . ds, If you have any questions or
require additional information, please call.
Sincerely yours,
TERRA ASSOCIATES, INC.
John
Proje
-7/0-0/Q3
TA/JCS/AB`a1Z..
t.�j
Encr i ures I ana Z p_ oration Location Plans
Figure 3 Unified Soil Classification -Systeni
Figures 4 through 9 — Boring and Test'Pit Logs
Figures 10 and I I —.Grain Size. Analyses
Figure 12 — Earth'Pfess u-re Diagram.
Figure 13 — Earth.Pressure Diagram
Figure 14 — L9ad/No Load Zone Diagram
Figure 15 — Earth Pressure Diagram7Basement Walls
cc: Ms. Beth Jensen, DO Engineers
"'S
a.
.EV. 111 .6f
2i; �1_
BLDG I
APPROXIMATE PERIMETER
OF LOWER LEVEL LOWER LEVEL EL ��4.67
BLDG.,4
LOWER LEVEL ELEV. 100.66
TP.;
02
NN
94
...... APPROXIMATE PERIMETER
OF LOWER LEVEL
t5LUU J
7--
-'-LOWER LEVEL ELEV. 10 .1
011
TP-1
BLDG OE.
LOWE LEVEL ELEV.
f
.............
� T_
NOTE:
THIS SITE PLAN IS SCHEMATIC. ALL LOCATIONS AND
DIMENSIONS ARE APPROXIMATE. IT IS INTENDED FOR
REFERENCE ONLY AND SHOULD NOT BE USED FOR
DESIGN OR CONSTRUCTION PURPOSES.
REFERENCE: -
SITE PLAN PROVIDED BY TRIAD ASSOCIATES, DATED 7-21-03
LEGEND:
B-1 APPROXIMATE LOCAT ION OF BOR ING
dy
TP-1 'APPROXIMATE'LOCATION OF TEST PIT
0 50 100
m W=9
APPROXIMATE SCALE IN FEET
N�
TP-1 B-k -----------
---APPROXIMATE PERIMETER
-OP LOWER LEVEL
BLDG. 5
-----------
LOWER LEVEL ELEV. 82.1
2\
LOWER LEVEL ELEV. 74.66
0
L__j
V,
APPROXIMATE PERI E R
z
OF LOWER LEVEL.
z-
0,
BLDG.8 0"
\\'LOWER LEVEL ELEV. 111.67"
V
\7
B-1 3
A PPROXIMATE PE IM,ETER -------
OF LOWER LEVEL
BLDG., 4
LOWER LEVEL ELEV. 100.66
V\\
>
. . . . . . APPRC)XIMATF;
NOTE: LEGEND:
THIS SITE PLAN IS SCHEMATIC. ALL LOCAT16NS AND
DIMENSIONS ARE APPROXIMATE. IT IS INTENDED FOR 19 B-1 APPROXIMATE LOCATION OF TEST BORING EXF
REFERENCE. ONLY AND SHOULD NOT BE USED FOR X Terra
DESIGN OR CONSTRUCTIONPURPOSES. 19 TP-1 APPROXIMATE LOCATION OF TEST.PIT POIN
0 50 100 Associates Inc.
REFERENCE: Consultants in Geotechnical Inginee...q,
Geology and
Fm Proj.
Y No. T
SITE PLAN PROvibED B TRIAD ASSOCIATE S,.DAE D 7-21-03 APPROXIMATE SCALE IN FEET nmenfal Earth Sciences
Enviro
MAJO R DIVISIONS
LETTER.
SYMBOL
TYPICAL DESCRIPTION
Clean
GW
Well -graded gravels, gravel -sand mixtures,. little or no
GRAVELS
Gra.vels
fines.
GP.
Poorly- . graded gravels gravel -sand mixtures, little or
-J 2)d)
(less than.
0
M N
More than
5% fines). -
no fines.
'GM
Silty gravels, gravel-sand;.silt mixtures, non -plastic
Fn
.50% of coarse
C),
a)
a) >
fraction is
larger than No
Gravels
fines.
�GC
Clayey gravels, gravel -sand-clay mixtures, plastic fines.
W
z E f
4 sieve
with fines'
<
C)
�00, q
ON
Clean
SW
.
Well -graded sands, gravelly sands, little or no fines.
LO 6
SANDS
Sands'
Sp
Poorly -graded sands or gravelly sands, little or no
W r- Z
(less than..
More than
5% fines).
fines.
50% of �coarse
0
0
fraction is
SM
-Silty sands,. sand -silt mixtures, non -plastic fines.
0
s I maller-, than
Sands
SC
Clayey sands, sand -clay mixtures, plastic fines.
No. 4 sieve
with fines
ML
Inorganic silts, rock flour, clayey silts with slight
C:)
SILTS AND CLAYS
plasticity.
CL
Inorganic clays of low to medium, plasticity, (lean clay)..
0 cu 0
N
E 6 a),
Liquid limit is less than 50%
W
110,Z.r-4'
OL
Organic -silts. and organic clays.'o f low plasticity.
Z
U.S. M 0)
. r- >
a a)
MH
Inorganic silts, elastic.
0
SILTS AND CLAYS
cu
E
CH'
Inorga,nic clays of high plasticit)4 fat. clays.
z
0 ch
Liquid limit is greater than 50%
LL
-OH
Organic clays of high plasticity.
HIGHLY ORGANIC SOILS
PT
Peat.
DEFINITION. OF TERMS; AND �SYMBOLS
U)
Standard Penetration
Density Resistance in Blows/Fbot
2" OUTSIDE DIAMETER'SPLIT
W
SAMPLER
_j
z
0
Very. -loose 0-4
..SPOON
214" INSIDE DIAMETER RING SAMPLER
U)"
Loose 4-10
0 R,SHELBY TUB E SAMPLER
w
-Medium dense .10-3.0
:E'
0
Dense 30-50
T :WATER LEVEL (DATE)
.0
Veiy dense
-TO
Tr RVANE READINGS, tsf
Pp PENETROMETER READING, tsf
Standard Penetration
Consistenc Resistance in -Blows/root
DD 'DRY DENSITY, pounds per cubic, foot
>
U)
yery soft 0-2
LL LIQUID. LIMI T, percent
W
Soft 24
Medium stiff 4-8,
PI PLASTIC INDEX
0
0
stiff
very stiff 1'6:-32
N STANDARD PENETRATION, blows per foot
Hard :,!32
Terra
UNIFIED, SOIL CLASSIFICATION SYSTEM
Assodates, Inc
POINTEDWARDS'CONDOMINIUMS'
EDMONDS,
Consultants in Geotechnical Engineering
Pr9j.. No. T-4893
D te, JULY 2003
a
Figur e 3
Geology and
Environmental Earffi Sciences
Roring No,.,,B-1 01
Logged'b': TA-.
Y
Date- 6/18/0,3-, Approximate Elev. 105
Sbil-'DesCription -
Consistency/
Relative
Depth
CL
E
(N)
Blows/
Moisture
Content
Density'
FILL: dark brown silty -san'd-w*ith gravel, moist. (SM)
Dense
.30.
10
Brown silty -SAND, trace gravel,with oyidized stained,
moist. (SM)
Brown mottled gray between 2.5 to 4.0 feet.
Medium
Dense
5
17
12
Gray, lean CLAY, trace subrounded gravel, moist. (CL)
7
.20
Medium
22
27
stiff -
td
Occasional light gra y sil t seams.below 15 feet.
Hard
—15
20 V
35
44
.26
25
Gray silty SAND, wet (SM)
Dense
Gray, lean -CLAY With lighigray SILT's.eaims'.
Hard.
—25
32
29
Boring terminated at 26.5 feet..
Groundwater seepage encountered, at.21 feet.
Z
Ter'r;'a'
BO.RING'LOG.
Associa0ps',inc...
Uns.ultants-in Geotechnical Enbineering
Ge6logy and
Environr�ental Earth Sciences
POINT -EDWARDS -CONDOMINIUMS
EDMONDS., WASHINGTOW
Pr 9j. No. T-4893T
Date JULY 26 3
0
Figure 4
Boring No. B-102
Logged by: TA
Date: 6/18/03 Approximate, Elev. 125
Soil Description
Consistency/
Relativ6.
Depth
E:.
(N)
Blows/
Moisture
Content
Density
ft.
N
15
19
FILL: brown silty sand, trace grivel/clayey silt, moist.'
(SM/ML)
Medium
Dense
to
Ve ry
Loose
—10
13
9
3
-2
24
5
7
11
.10
23
Gray, lean -CLAY, occasional light. gray silt and sandy
silt.seams (Vto 2 mm), moist,.'(CL)
—20
22
31
L
0.5 inches light gray sandy silt seam a*t.26 feet.
Very
stiff
29
36,
0.5 inches sand seam at 30.5 feet.
—30,
33
26
29
27
—40
T
38
25
Gray SAND with *silt, free water. (SM)
Dense
Grayjean moist. (PL)
37
27
—50
32
25
Boring terminated.at 51.5 feet.
Groundwater encountered at 40 feet.
TerrA
BORING LOG.
Assodates.,Ift.
Consulta.nts in Gdotechnical Engineering
Geology and
Environmental Earth Sciences . .
. 1i -�
POINTEDWARDS, CONDOMINIUMS
.EDMONDS, WASHINGTON
Proj. No—T-4893
I I
Date JULY 2003
Figure
Bori.ng 'No. 13-103
.Logged by* TA.
D,ate:, 6[ 1 18/03
Approkimate Elev.. 129
Soil Description,.
Consistency/
Relative
Density
Depth
-a
E
U)
(N)
Blows/
IMbi'sture
Content
Notes
-CRUSHED GRAVEL
Dense
36
11
15
2
17
28
FILL:.dark gray clayey SILT/silty SAND,
.trace gravel, moist. (MUSM)
Medium
Dense
Brown silty SAND to SAND with silt,
free I water. (SM)
Medium
Dense
F
—10
1.6
22
24
36
Gray lean CLAY, moist. (CL)
Brown lean CLAY with oxidized stained
between 15.0 to'l 5.5 ieet.*
Very,
15,
31
28
lie
.....
........
..........
........ :::::
..........
...........
..............
Wet soils encountered at 21 �5 feet.
stiff
to
—20
30
24
........
...........
: ..... : ......
...... ......
.....
:
..............
....... ! .......
........
. ? .......
........
Hard'
Occasional light gray silt and silty sand seams
encountered below 25 feet.
25-1
28
32
........
..............
..............
............. v
..............
1
4 inches sand seam at 31 feet.
30
35
.23
.......
...............
.........
..............
.......
......
............
.......
.........
35
............
41...
29
.........
................
...........
..........
Boring terminated at 36.5 feet.
Groundwater seep'age-enc . ountered at 8.5 feet.
Water. level at 22.15 feet on June 19, 2003.
Ter ra,
BORING LOG
'
Astociate's, Inc.
P . OINTEDWARDS'CONDOMINIU
M8
EDMONDS, WASHINGTON
Consultzints in Geotechnical Engineering
Geology and
Enyji��Tnental Earth Sciences
FProj No. T-4893,
Fbate JULY 2003
Figure 6
Boring No'. B-4
Logged by: DPL
Date: 12/16/02. Approximate Elev. 90
Consistency/ (N) Moisture
Soil -Description Relative Depth E Blows/ Content
ft.
Density (ft,.) U)
FILL (Old test pit): bluish -gray silty sand, fine grained. Loose
wet, with a trace of wood particles. Appears disturbed.
7 27
,FILL (Old test pit): mottled brown silty sand, fine grainedi moist. Medium
Dense 17 -31
FILL (Old test pit): brown'silt and clay, moist, with a trace
Very.
f brown organic material. Stiff 21
------------------- --------------------------------------------------------------------------
bluish-gray SILT to CLAY, low to medium plasticity. Very 17 28
(MUCL) stiff
Gray Sl LT to CLAY, moist, low to medium plasticity.
Very 30 23
(MUCL) stiff LL � 35.5
P1 = 11.5
---------------------------------------------------------------------------------------- r ----------
'Grayish-brown sandy SILT. to clayey SILT, fine grained, Very 35 23
moist. (ML) \/Vith thin partings of irpil-stained, fine-grained stiff
sand.
.,Grayish -brown clayey SILT to silty CLAY, moist. (MUCL) Very 30 30 24-
With-thin discontinuous lenses of gray to mottled gray stiff
iq�t-_q!ained sand.
------------------------------ --------------------------------------------------------
Gray silty SAND, fine drained; moist. (SM) Dense 37 15
----------------------------------------------------------------------------------------------------
Gray sandy SILT to clayey SILT, fine grained, moist, low Hard —40 34 17
plasticity. (ML to MUCL)
.Gray clayey SILT, moist, low plasticity. (MUCL) Hard 37 20
Trace fine-gLcai ed sand.
------------------------------------------------- -------------------------
Gray sandy SILT to silty SAND, fine.grained, moist,' Den r se 50 32 .19
(MUSM),
47 18
—60 4 15
2
+
Boring terminated at 61.5 feet.
No,significant groundwater encountered.
Terra BORING,LOG_
7 POINT EDWARDS CONDOMINIUMS
Associates,, l.nc.,. EDMONDS, WASHINGTON-
Consultants in debtechnical Engineei-ing
Geology and
Environmental Eaft Sciences P roj. N o. T-4893 -:7
I Date JULY 20031. Figure
lest Pit No. TP-1
Logged by: JCS A�pproxirnate Bev. 1'04
Date' 10/18/01
Depth Moisture
Soil Description Content
0— NO)
FILL: crushed rock surfacing over brown to gray silty sand tosandy silt, fine grained,
firm, moist. (SWML)-
Rusty brown silty, SAND fine grained, medium dense, moist, with- occasional fine
gravel and fine roots. (�M)
Gray to mottled, gray silty SAND, fine grained, medium dense to dense,
moist, with occasional fine gravel. (SM)
5 Becomes light brown at appro) dmately 6 feet.
10 Gray CLAY, hard, moist, massive. (CL) 26 1 Pp = 4.5+
tons/ft'
LL 35.8
P1 15
15 Test pit terminated at.1 4 feet.
No groundwater seepage.
20
..Test Pit No. TP=2
Logged by: JCS Approximate-Elev. 124
Date: 10/18/01
Moisture
Depth Content
Soil Description
0 FILL: crushed rock surf0ng over brown silty sand to sandy silt, fine grained, firm,
moist. 4-inch thick organic layer at base. (SM/ML) (Old topsoiVhdrizon)
Brown silty SAND, fine grained; medium dense, moist. (SM)
Mottled grayish -brown silty SAND, fine grained, medium dense, moist. 20
(SM)
Grayish -brown silty SAND, fine grained, medium dense to dense, moist.
(SM)
10— Gray CLAY, hard, moist, laminatedwith light gray silt. partingsi (CL) PP 4.5+
tonsIft,
37
15— Test. pit terminated at 14 feet,
No groundwater seepage.
20
TEST PIT LOGS
Terra POINT EDWARDS CONDOMINIUMS
Associates, Inc. EDMONDS, WASHINOTOW.
Geotechnical Consultants
Proi. No. T4893TDate JULY 20*03 Figure 8'
Test Pit No. TP-4
Logged by: JCS Approximate Elev. 92
Date: 10/18/01
Depth Moisture
Content
Soil Description
N
0 FILL: ligh n silty sand, fine grlined, firm, dry to moist. (SIVI) 2-inch thick
organic layer at base.- (Old topsoil horizon)
Light brown to tan silty SAND, fine grained, medium dense to dense, dry.
(SM)
Mottled grayish -brown silty SAND, fine grained, medium dense to dense, 29
5—
moist. (SIVI)
LL = 42.7
Light grayish -brown to light brown. CLAY and SILT, hard, moist, laminated 29 P1 = 19.7
with partings of dark gray'fine sand. (CUIVIL) PP = 4.5+
tons/fe
10—
y CLAY,. hard, moist. ((jL) PP = 4.5+
- Gra 29 1 tons/fe
- Test'pit terminated at 13 feet.
Trace groundwater seepage at 6 feet.
TEST PIT. LOGS
Terr'a.. POINT EDWARDS CONDOMINIUMS
Associates-, -Inc. EDMONDS, WASHINGTON
Geotechnical Consultants
Proj. No.'T-4893. Date JULY: 2003 Figure 91
dR
CANTILEVER SOLDIER PILE WALL OR
SINGLE ROW TIEBACK WALL
H 40* pcf + 75 psf
Traff ic S.urcharg'e
Where Appkable,
:Pass Ive Earth 40(H)* psf taken over pile diameter
Pressure = 400 pcf
taken � over 2 pile'
diameters
Note:
Value includes
Safety Factor of
1.5.
D
NOT TO SCALE
INCREASE PRESSURE BY 20. PERCENT WHERE- WALL IS
SURCHARGED BY BACKSLOPE OF 2: 1 (HO.RIZONTAL:VERTICAL)
OR FLATTER.
Terr'a' E�%RTH, -PRESSURE" DIAGRAM
-POINTEDWARDS CONDOMINIUMS
Associates,. Inc. EDMONDS., w.AsHI.NG,TON . .
9M.Consultzin.ts in Geotechnical Engineering
Pr0j;; No. T-48 3 Date JULY 2003 'Figurd
EnvironrnentalZarh Sciences
Geologyand 9
SOLDIER PILE WALL WITHTWO
OR MORETIEBACKS
.0.2 (H)
75 psf UNIFORM
PRESSURE TRAFFIC
X/
H SURCHARGE WHERE
APPLICABLE
2.3 (H)* psf APPLIED OVER PILE SPACING
400 pcf/ft PASSIVE. -EARTH
.23 (H)* psf APPLIED OVER PILE: DIAMETER
PRESSURE APPLIED OVER 2(D)
NOTE:
VALUE INCLUDES SAFETY
FACTOR OF 1.5
D.
NOT TO SCALE
INCREASE PRESSURE BY 26 (H) WHERE WALL IS
SURCHARGED BY BACKSLOPE OF 2:1 (HO RI ZONTAL:VERTI CAL)
OR FLATTER.
Terra EARTH PRESSURE'DIAGRAV
POINT'EDWARDS CONDOMINIUMS.
Associates, Ini.c. EDMONDS, WASHINGTON
Consultants in Geotechnical Engi,npering'�
G6ology and Figure 13,
Environmental Earth Sciences Pr.0j.N T-4,89qlDate_�ULY2003
H
TIEDBACK SOLDIER PILIE/LAGGING SHOR-IN.G WALL
NO LOAD ZONE
15-(TYPICAL)
ANCHOR
ZONE
TIEBACKS NOT GROUTED
IN THIS 'ZONE
TIEBACKS GROUTED
IN THIS ZONE
60'
ALLOWABLE TIEBACK
ADHESION CAPACITY IN
ANCHOR ZONE=1000 psf
NOTE:
TIEBACK CAPACITIES ARE BASE ON INSTALLATION
USING TREMIE GROUT METHOD
NOT TO SCALE
Terra LOA[)/NO LOAD, ZONE DIAGRAM
POINT EDWARDS. CONDOMINIUMS
'As,qociates, I'nc.- LDIVION�'DS,V ASHINGTON
Consultants in Geotechnical.Engineehn'g
Geology and
Proj.:Nlo. T4893. Date JULY 20 3 -.figure 14
Environmental Earth Scienges-
o7
H
EARTH PRESSURE DIAGRAM, FOR BASEMENT WALLS
_IC .
HARCE
E
CABLE
5f
NOT TO'SCALE'
*INCREASE PRESSURE TO '26 (H) WHERE. WALL IS SURCHARGED
BY BACKSLOPE O�'2:1 (HO RI ZONTAL:VER'TI CAL) OR -FLATTER.-
Term' TEARTH PRESSURE.DiAGRAM-13ASEMENT WALL*S'
PO.INT EDWARDS CONDOMINIUMS.
-s n' c. :'EDMOND8, WASH I NGTON
Ast.qqi4te
iZ:onsuitants inGeotechnical. Engineering
Geology and
Environmental Earth Science� Proj. No.T-4893 .'Date.JuLy. �003 figur6.115
Z 1�'Z
Mr. Ross Woods
Point Edwards, LLC
2801 Alaskan Way, Suite 107
Seattle, Washington 98,121
TERRA ASSOCIATES, tnc�
Consultants in Geotechnical Engineering, Geology
and -
Environrnental Earth Sciences
January 20, 2003
Project No. T-4893
Subject: Geologically Hazardous Areas Review
Point Edwards Condominiums (UNOCAL Site)
Piirfe Street and Unoco Road
Edmonds, Washington
References: 1. Preliminary Geotechnical Report, UNOCAL Site, Project No. T-4893, prepared by
Terra Associates, Inc., dated November 21, 2001
2. Steep Slope Hazard Review, Point Edwards Condominiums (UNOCAL Site), Project,No.
. T-4893, prepared by Terra Associates, Inc., dated December 13, 2002
Dear Mr. Woods:
As* requested, we have conducted a review of geologically hazardous areas for the Point Edwards Condominiums
site. The location of the site is shown on the attached Figure 1. Our scope of work included a. visual site
reconnaissance', the -drilling of five test borings to depths ranging from about 31.5 feet to 61.5 feet below the
existing ground surface, and -review of the referenced reports. Our study specifically addresses erosion hazards,
landslide. hazards, and seismic hazards. - We previously addressed steep slope hazards at the site. Our current
study includes analysis of slope stability along five profiles on the steep slopes located downgradient, from the
proposed development. The.result s of these analyses are used to address potential steep slope hazards and
landslide hazards.
SITE CONDITIONS
f"REET FILE
01
The site is located on the upper portion of a predominantly nortli-facing hillside. The Preliminary.Gr*ading Plan
indicates elevations, in the planned development area range from about Elev. 170 in the south-central 'portion to*.
about Elev. 70 in the northeastern' portion. The western and northern margins of the'planne'd deVe lop"ment area
are near the top of a steep natural slope. The topographic information provided to us indicates the slope is.
p
approximately 70 to 90 feet high, with inclinations ranging between about 50 and 80 percent. The areas beyon . d
the toe of the slope to the north-northwest are relatively flat. Burlington Northern railroad tracks run along the toe
of the slope to the west.
RECE11VED
0 CT- 2 -005.
12525 Willows Road, Suite 1,01, Kirkland, Washington 98034
Phone (425) 821-7777 a Fak (425) 821-4334 BUILDING DEPT.
Mr. Ross Woods
January 20, 2003
We did not observe indications of deep-seated instability; however, portions of the slope have been subjected to
shallow erosion and localized sloughing. These conditions are generally limited to. the forest duff and relatively
loose surficial soils mantling the underlying competent soils, and are commonly associated. with natural
weathering occurrences on steep slopes. All of the erosional features we observed on the.steep slope appear to be
a result of surface water runoff and shallow interflow from areas above the slope crest.
We observed an area approximately 100 to 125 feet southwest of Boring B-1 where the top of the steep slope has
sloughed, exposing dense to very dense silty sand with gravel in a 7- to 8-foot high, near -vertical face, just below
the crest of the steep slope. Based on our observations, it appears that the sloughing, at thi's location also occurred
as a result of concentrated surface w ater runoff and shallow interflow from areas. above the slope prest. We
observed a very light trickle of water flowing into this feature. from the relatively flat upland above the slope.
Slope vegetation consists predominantly of young to mature deciduous, trees and brush.
GEOLOGIC CONDITIONS
The Geologic Map of the Edmonds East and Part of the Edmonds West Quadrangles, Wtishington by James P.
Minard, 1983, -shows the soils at higher site elevations mapped as Vashon till, Vashon advance outwash, and
Transitional beds. Soils at lower site elevations are mapped as medium- to coarse -grained sand of the, Whidbey
Formation. Transitional bed sediments are described by this publication as massive to bedded cl ay, silt, and fine
to very fine sand.
Our recent test borings and the test pits performed as part of our referenced preliminary geotechnical study are
generally consistent with the descriptions of transitional bed deposits. The soils we observed 6n'and immediately
above t ' he steep slope areas generally consist of silty sand, sandy silts, and lanuinated to massive, very dense silt
and/or hard clay. Native soils observed in the five test borings drilled near the too. of the steep slope s generally
consist of dense to very dense fine-grained silty sand to sand with silt, and very stiff clay/dense silt. The silt and
clay generally appeared massive, with occasional very thin partings of very. fine sand.,
The native soils are generally moist below a depth of about five feet. We observed wet soils to a depth of about
ten feet in Boring B-S. We did not observe indications of significant. grgundwa"ter seepage . on the slope; however,
we observed wet surficial soils in one. isolated area near the top of the steep slope; west of the proposed
development. The wet conditions at this location appear to be fron�i surface runoff from areas abo ve the too of the
steep slope, and possibly from seasonal perched groundwater emerging near the top of the slope.
We also observed a very light flow of water along the axis of several of the erosional channels running downth ee
steep slope. The water we observed in the erosional features flows on top of densd.to very -dense native soils
exposed on the ground surface or beneath approximately 4 to 12. inches of duff and topsoil. The source of..the
water in the erosional features appears to be surface' runoff from areas above the crest of the steep slope.,
Detailed descriptions of thesubsurface conditions encountered in the test pitsand testborings are presented on the
attached test pit logs and boring logs. The approximate locations of the test pits and borings are shown on the
attached Figure 2.
Project No. T-4893
Page No. 2
Mr. Ross Woods
January 20, 2003
GEOLOGICALLY HAZARDOUS AREAS
Section 20.15B.060 (A)(3) of the City of Edmonds Community Development Code (ECDC) defines geologically
hazardous areas as those areas subject to potential erosion, landslide, and/or 'potential seismic instabilities,
including the following:
Erosion Hazard Areas
Section 20.15B.060 (A)(3)(a) of the ECDC defines erosion hazard areas (EHAs) as those areas containing soils
that may experience severe to very severe erosion hazard. These soils include, but are not limited to, the
following when they occur on slopes of 15 percent or greater:
1. Alderwood soils (15 to 25 percent slopes)
2. Alderwood-Everett Series (25 to 70 percent slopes)
3. Everett Series (15 to 25 percent slopes)
The Soil Conservation Service (SCS) has mapped the site soils as Alderwood-UrbAn land complex, 2 to 8 percent
slopes, and Kitsap silt loam, 8 to 25 percent slopes, in the upper southern. portion,of the site, and Alderwood-
Everett gravelly sandy loam, 25 to 70percent slopes, in the area of the former tank farmaind the steep slope below
the tank farm area. The soils we observed in the test pits generally conform with the SCS mapping; however,
some of the very dense silt and hard clay we observed in the former tank areas would better correlate with Kitsap
silt loam, 25 to 50 percent slopes, due to existing man-made slope gradients.
The erosion hazards for soils classified as Alderwood-Urban land complex, 2 to 8 percent slopes, and Kitsap silt
loam, 8 to 25 percent slopes, are classified as slight and moderate, respectively, and do not fall under the
classification of an erosion hazard area. Alderwood-Everett gravelly sandy loam, 25 to, 70 percent slopes, is
classified as having a moderate to high erosion hazard. The erosion hazard for soils classified as-Kitsap silt loam,
25 to 50 percent slopes, is considered high.
Based on the criteria presented above, the portions of the site that are- sloped at inclinations greater than 15. percent
and are underlain by Alderwood-Everett gravelly sandy loam would.be considered an-EHA. Areas underlain by
Kitsap silt loam that are inclined at a gradient steeper than 25 percent would also. be considered EHAs. Based on
observations,.the vast majority of the site located downgradient from Pine Street would be considered.an E14A.'.
EHAs, based on the SCS mapping, are shown on the attached Figure 3.,
We did not observe indications of significant active erosion in the planned development area; however, the soils
will be susceptible to erosion when exposed during construction. In, our opinion, Best Management Practices
(BMPs) used during construction will provide adequate mitigation of the erosion hazard at the site. .1f the erosion
control measur es -are properly implemented and maintained, .!long with temporary and permanent.Araitinage
improvements,. it is our opinion that the planned development will not adversely impac't the erosion potential for
p
the site or adjacent proper I ties. All erosion and -sediment control BMPs should conform to City of Edmonds
requirements.
Project No. T4893
'Page No*. 3
Mr. Ross Woods
January 20, 2003
Landslide Hazard Areas
Section 20.15B.060 (A)(3)(b) of the ECDC defines landslide hazard areas (LHAs) as those areas'of the city of
Edmonds which, by reason of excessively steep 'slopes, unsatisfactory foundation support, stability, or
topography, have a risk of earth subsidence and landslide -hazard in excess of normal allowpices. The ECDC
specifies field criteria for identifying LHAs. We used these criteria, listed belowl� in,.our evaluation of LHAs at
the subject site.
1. Any area with slopes of 15"percent or greater, and impermeable- soils (typically silt. and clay) frequently
interbedded with granular soils (predominantly sand and gravel) and, springs or groundwater seepage.
2. Any area that includes areas with significant visible evidence of groundwater. seepage, and which also
includes existing.landstide deposits, regardless of slopes.
3. Any area that has shown movement during the Holocene epoch (from 10,000 yearsago I to present) or is
underlain by mass wastage debris of that epoch, as determined by a qualified geologist or geotechnical
engineer.
4. Any area potentially unstable as a result of rapid stream incision or stream bank erosion.
5. Any area located on an alluvial fan presently subject to, or potentially subject to, inundation by debris
flow or deposition of stream -transported sediments.
During our site visit, we did not observe on -site indications of deep-seated instability, springs, or.significant
groundwater seepage on the steep slopes. As,discussed, we observed relatively shallow erosional features and
localized shallow sloughing at isolated locations -on the steep slope. located below the proposed development.
Because shallow ground movements are associated with these erosional features, and considering that near-
s urface interflow likely contributed to the soil loss, these areas would be considered LHAs'pursuant to Items I
and 3. All of the LHAs we identified at the site ekist on the steep- sl ope hazard area (SSHA) (slope inclinations
greater than 40 percent) located west of Buildings 5, 6, and 7.
Stability Analysis
We performed our stability analyses using the computer program WINSTABL The soil parameters. used are
shown on the attached analysis plots and output text. These parameters are based on field and laboratory . data,
and our past experience with similar soils. Analyses of the slope were performed -along five section lines
identified on the attached Figure 2 as Section A -A' through- Section E-E'. , Our analyses of these sections
considered both static and pseudostatic (seismic) conditions for the existin& slopes, and for proposed grading with
associated building loads at grade. This analysis is con.servative, considering the buildings located near the to of
p
the steep,slope will be partially or completely supported by deep foundations. A horizontal. acceleration of 0.20g
was used in the pseudostatic analysis to.simulate slope performance under earthquake loading.
P�cject No. T-48193
PageNo. 4
Mr. Ross Woods
January 20, 2003
The lowest safety factors for each condition are presented in the following table:
Secti6n Analyzed
Minimum Safety Factors
Static
Pseudostatic
Section A -A' existing
L72
1.18
Section A -A' proposed
1.79
1.21
Section B-11'exiAing
2.09
1.42
Section 13-13' proposed
1.56
1.16
Section C-C' existing
2.32
1.53
Section C-C' proposed
1.67
1.26
Section D-D' existing
1.88
1.24
Section,D-D' proposed
2.03
1.33
Section E-E' existing
1.72
1.15
Section. E-E' proposed
4.60
.1.26
The results of the stability:analyses indicate that existing and proposed slopes are stable with respect to deep-
seated failure under static conditions. The existing and proposed slopes are indicated to be stable to marginally
stable under severe seismic loading conditions.
Potential impacts to the LHAs due to construction of the buildings and proposed yard grading include increasing
the potential for erosion on and/or adjacent to the slope by exposing. soils during grading and allowing surface
runoff to flow onto the steep slope, and impacts to slope stability from building surcharges.
In our opinion, potential erosion and sedimentation impacts to the LHAs due to the planned building locations and
yard grading will be eliminated or significantly reduced by applying BMPs for erosion prevention sedimentation
containment.
As discussed above, analysis indicates the existing and proposed slope conditions are stable with regard to deep-
seated failure. In our opinion, supporting building'loads with a deep foundation system will further reduce
potential impacts to the stability of the steep slopes due to building surchar
. ges, and mitigate the landslide hazard.
A deep foundation system will also eliminate the potential of adverse impacts to the stability of the buildings in
the event of shallow soil loss adjacent to the buildings. Additionally, drainage systems associated, with the
finished buildings will improve the current stability of the steep slope.
Seismic Hazard Areas
Section 20.1513.060 (A)(3)(d) of the ECDC defines. seismic hazard areas as those areas subject,to severe risk of
earthquake damage' as a result of seismical.ty induced -landslides,- earth adjustments, settlement, or soil
liquefaction.
Based on -the soi * I and groundwater conditions, -we observed in our on-�site explorations, and the results -of our
stability analysis' it is our opinion that the risk for severe damage resulting from seismically induced landslides,
earth adjustments, and -se . ttlement is low. It is also our'*opinion that the risk for liqu. . efaction to occur in.potential
building�areas at this site is negligible. Therefore, in our opinion, seismic hazard areas do not exist on.the subject
site.
Project No. T4893
Page No. 5
Mr. Ross Woods
January 20, 2003
DISCUSSION
Section 20.15B. 110 (B) of the ECDC �Development Standards - Erosion -Hazard Areas) states that alterations.
within identified EHAs will,not be authorized without an approved erosion control plan pursuant to Chapter 18.30
ECDC. A licensed engineer will prepare, a site -specific erosion controlplan conforming to the requirements of
Chapter 18.30 ECDC.
Section W.1513.110 (C) of the ECDC (Development Standards, - Landslide Hazard Areas) states that LHAs
located on. slopes greater than 40 percent shall be regulated Pursuant to Section 20.15B. 110 (D) of the ECDC
(Development Standards - Steep Slope Hazard Areas). As discussed, the LHAs we identified at the site. exist on
the SSHA.(slope inclinations greater than 40 per I cent) located -west of Buildings 5, 61 and 7. We previously
addressed SSHAs in the referenced report. In the S.SHA report, we opined that existing site conditions'and
applicable. project components generally meet the provisions for a. SSHA exernp tion detailed in Section
20.15B. I 10(D)(2)(a - g). Specifically, this exemption would apply to encroachment into SSHAs by proposed
Buildings 5 and 6, yard grading associated with Buildings 2, and 6, and encroachment into the buffer within about
5 feet of the SSHk by Building 7 and its as I soc - iated yard grading, We also opined that a reduction in the buffer
from 50 feet to 10 feet will have no significant impact -on the SSHA. or adjacent *slopes.
In our opinion, the subsurface information and analytical results presented herein support the findings presented
in our SSHA report, and the request for a SSHA exernp.tion.and buffer reduction.
We trust the information presented is,sufficient for your current needs. If you have any questions or require
additional information,'please call.
-Sincerely yours,.
TERRA ASSOCIATES,
i 100 10-3
FM&AW1%r-T_W' inity Map
"*"V- EX lotation Location Plan
on azard Area/Soils Map
ig'_�
ligg" Erosi * X
e ni ie 'Soils Classification System
Figures 5. through 9 - Boring Lo . gs
Figures 10 through'18 - Test Pit Logs
WINSTABL Output Data
cc: Mr; Greg Krabbe, Triad Associates
Mr. Richard E * Gifford
Mr. S. Jin Lee, We I ber+Thp.mpson
Project No. T4893
Page No. 6
-r,
1 6 SIR-
1dfrT PL
PK 18rFH
PL Sw ST Sw
I 8BTU ST SbiII"
I
189TH ;
S SW
w IV 190TH ST Sw
CH 'ST
14, 011
IS,
cc
1
S,T Sw
MELODY LA NGET p
0
6
IT I
'w", III L V
ERE
IT
06AND ZZ WY
e M. .
a a:
EDIM'S
p
ks E T
ST _1h
PARK
VISTA
LN
40 a WY 2"
ST Sw
I AG
< 20la-
- GLEN
4 ST
TV
TV
SPRAGUE 15- §11r
--ro—Wim
RJR
E
ilf"', PIT 11
ELL 2�
IT
A,
I [AIN ST
_T
j 14 FQA;TM
WLE
MRIA4
F3
PL
4*1
&s� 7t;
V.00 jwL0-_
�c
OIL
y
'i
ARK
itz "
% FS Sw
sr
1,1
je: � :
swnmw[ if
SITE
W.,
AE
ZI T"
M ST S,
E Z
ZISTH ft
ELWFOS MWINA
PT BEACH
217TH
MWAH
Ff If
ff
A fI F R 218TH
26 4j
f2Z
5 30;
BELLA CDOLA
E ST TH -v ST .81 Zl
OID
96
A, , 1. & M
1. ST IT
UI
Rijn
41
.1� s.
REFERENCE: Thomas Guide, King/Pierce/Snohomish Counties, 19,99, Page 454 NOT TO SCALE
Terra'
Associates Inc..
VICINITY MAP
POINT EDWARDS CONDOMINIUMS
EDM ONDS, WASHINGTON
Consultants in Geotechnical Lgineering
-Geology and
Environmental Earth Sciences
roi.
P No. T-4893
Date JAN 2003
Figure 1
NOM:
THIS SITE PLAN IS SCHEMATIC ALL LOCATIONS AND
DIMENSIONS ARE APPROXIMATE. IT IS INTENDED FOR
REFERENCE ONLY AND SHOULD NOT BE USED FOR
DESIGN OR CONSTRUCTION PURPOSES.
REFERENCE:
SITE PLAN PROVIDED BY TRIAD ASSOCIATES
EG, END:
..&,Ti"�p-l;AP�R,OXtMATELOCAT'ION' 6FTE'&PIT
APPROXIMATE LOCATIoN O� BbRING.
�fEEPSLOPE,HAZA RD,A:REA
------------ --- - ------
.STEEP.SLOPE
HAZARD AREV
TP-11 4
p 15
IG 1 -
ft.TP 16
P-17
i llll"1'117:�'. W,
X
1.50 30,0.
po
APPROXIMATE SCALE IN FEET
N�
LU Lj
CL
IS
LJ
..cn m.,
LLI
CL
CL
Lu
LLJ N
V) m
Al
X,
N.,
8
LLI
w
LL
Z
w
9
W
0
(L
a.
0
E
CO
C-4
E
> to
1! -0 C', 4)
tm c 0
E
w
.0
0 0=
do lco .0
m 0
0.
z (D
-0 all
X
00
Z X
LL.
0
tL
W
ZOO
OZW
W
UJ CO
D
W,
w
0 U) W LU
S
.J �- (n
-1 0 0
0
(0
J-z a.
w ir
U)
p a-
0 z
HXXO
w OP
cr 0 C-)
CL Z
co
cn CL <
0
w
0
Zl%Z z
>
<00
0 W. (-)
0
a:
a- z 0 m
WOZO
Z
CL
z
!= V5 uj z
(1) z M (!)
Lu
ce
5
tL
O.uj W —
LL CO
ww
W
U.
'w
w a
z
w
MAJOR DIVISIONS
LETTER
SYMBOL
TYPICAL DESCRIPTION
Clean
GW
Well -graded gravels, gravel -sand mixtures, little or no
GRAVELS
Gravels
fines.
Gp
Poorly -graded gravels, gravel -sand mixtures, little or
_j 0)
(less than
N
More than
5% fines)
no fines.
GM
Silty gravels, gravel -sand -silt mixtures, non -plastic
V5
ca
50% of coarse.
fraction is
L3 .*= a)
(D >
W a)
larger than No.
Gravels
with fines
fines.
z as
E
4 sieve
GC
Clayey gravels, gravel -sand -clay mixtures, plastic fines.
<
C)
I
8_0
jr - 0
0 b C\1
Clean
SW
Well -graded sands, gravelly sands, little or no fines.
Lo 6
SANDS
Sands
SP
Poorly -graded sands or gravelly sands, little or no
W q z
ca
(less than
-r- C:
More than
9% fines)
fines.
a) �c
50% of coarse
0 L_ 4-
0
fraction is
SM
Silty sands, sand -silt mixtures, non -plastic fines.
C)
smaller than
Sands
SIC
Clayey sands, sand -clay mixtures, plastic fines.
No. 4 sieve
with fines
ML
Inorganic silts, rock flour, clayey silts with slight
U) .50
SILTS AND CLAYS
plasticity.
CL
Inorganic clays of ow to medium plasticity, (lean clay).
_j
a) 0
0 � C\1
cz
U) E 0'
Liquid limit is less than 50%
0 Cn
OL
Organic silts and organic clays of low plasticity.
0 C:
-a)
z LO co
< C (D
MH
Inorganic silts, elastic.
cc co
C,3 = U)
SILTS AND CLAYS
W (D Ca
" E
CH
Inorganic clays of high plasticity, fat clays.
Z .0
Liquid limit is greater than 50%
LL
OH
Organic clays of high plasticity.
HIGHLY ORGANIC SOILS--[
PT
Peat.
DEFINITION OF TERMS AND SYMBOLS
U)
Standard Penetration
Density Resistance in Blows/Foot
2" OUTSIDE DIAMETER,SPLIT
W
SPOON SAMPLER
z
0
Very loose 0-4
2.4" INSIDE DIAMETER RING SAMPLER
U)
Loose 4-10
OR SHELBY TUBE SAMPLER
W
Medium dense 10-30
a:
0
Dense 30-50
WATER LEVEL (DATE)
Very dense >56
Tr TORVANE READINGS, tsf
Pp PENETROMETER READING� tsf
Standard Penetration
Consistenc Resistance in 1316ws/Foot
DID DRY DENSITY, pounds per cubic foot
W
>
W
Very soft 0-2
LL LIQUID LIMIT, percent
W
Soft 2-4
X
Medium stiff 4-8
PI PLASTIC INDEX
0
stiff 8-16
Very stiff 16-32
N STANDARD PENETRATION, blows per foot
Hard >32
Terra
UNIFIED SOIL CLASSIFICATION SYSTEM
Associates, Inc.
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Proj. No. T-4893
FDate JAN 2003
Figure 4
Geology and
Environmental Earth Sciences
Boring No. B-1
Logged by: JCS
Date: 12/13/02 Approximate Elev. 110
Soil Description
Consistency/
Relative
Density
Depth
(ft.)
cL
E
U10)
(N)
Blows/
Moisture
Content
N
Grayish -brown silty SAND, fine grained, with occasional
fine gravel. (SM)
Medium
Dense
29
12
Occasional rusty brown stained partings.
-------------------------------------------------- : ----------------------------------
Dense
7 --------------
—10
43.
14'
Light brown SILT with sand, fine grained, moist, slightly
mottled. (ML)
-------------------------------------------------------------------------
Dense
--------------------------
42
21
Mottled light brown silty SAND to sandy SILT, fine
grained, moist to wet.. (SM/MQ
Dense
—20
38
23
Light gray silty. SAND to sandy SILT, fine grained, moist,
---.-with occasional fine qravel._(SM/M�) -----------------------------------
Very
Dense ---------
60
18
Grayish-brown SAND with silt, fine to medium grained,
moist, with occasional fine gravel. (SP-SM)
Very
Dense
—30
82
8
Grayish -brown SAND with silt to silty SAND, fine grained,
moist. (SP-SM/SM) .
Very
Dense
58
15
(Grayish -brown hard, moist SILT between 35.5 and 36.0
-
feet)
Light gray silty SAND to SAND with silt, fine grained,
Very
—40
75
10
moist. (SM/SP-SM)
Dense
Trace of gravel.
Very
Dense
80
8
Very
Dense
50'
58
6
------------------------------------------------------------------------
Brownish-gray SAND with silt to silty SAND, fine grained
moist. (SP-SWSM) With a trace of -fine black organic
inclusions.
------------------------
Very
Dense
-82
10
No fine organic inclusions.
Very Dense
86
1 8
Boring terminated At 60 feet.
No significant groundwater encountered.
Terra
BORING LOG
Associates, Inc.
POINTEDWARDS CONDOMINIUMS
EDMONDS, WASHI NGTON
Consultants in Geotechnical Engineering
Geology and
Environmbntal Earth Sciences
Proj. No. T-4893
I Date JAN. 2003*
Ti
Boring No. B-2
Logged by: JCS
Date: 12/13/02 Approximate Elev. 90
Soil Description
Consistency/
Relative
Depth
E
(N)
Blows/
Moisture
Content
Density
(ft.)
ft.
N
F ILL gray sandy silt, fine grained, moist, with occasional
fine gravel.
Loose
5
8
24
FILL: brown organic silty sand to sandy sil t and bluish-
gray silty sand,,fine grained, moist to wet.
Loose
—10
4
12
With organics.
Loose
—15
6
10
Very
Loose
—20
3
27
Bluish -gray to light brown SAND with silt to silty SAND,
fine grained, moist. (SP-SM/SP)
Medium
Dense
—25
20
13
--------------------------------------------------------------------------------------------------
Mottled gray sandy SILT, fine grained, moist. (ML)
--------------------------------------- 7 ----------------------------------------------------------
Medium
Dense
-
—30
-
-
23
20
Gray SAND to SAND with silt, fine grained, moist.
(SP/SP-SM)
Medium
Dense
—35
27
10
Dense
40
:E
36
8
Boring terminated at 41.5 feet.
No significant groundwater encountered.
Terra
BORING LOG
Associates, Inc.
POINTEDWARDS CONDOMINIUMS
EDIVIONDS WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
Proj. No. T-48931
Date JAN 2003
Figure.6
Boring
No. B-3
Logged by: DPL
Date: 12/16/02
Approximate
Elev. 76
Soil Description
Consistency/
Relative
Depth
'E:'-
(N)
B o ws
Moisture
Content.
Density
(ft.)
U)
ft
N
Possible FILL: gray sand to si Ity sand, fine grained, wet,
with occasional fine gravel.
Possible FILL: grayish -brown silty sandi fine grained, wet,
slight mottling.
- ---------------------- 7 --------------------------------------------------------
Medium
Dense
5
T
11
1 9
Gray silty SAND, fine grained, moist. (SM)
Dense
—10
31
22
Gray silty SAND.to sandy SILT, fine grained, moist.
Dense
—15
36
20
(SM/ML)
-------------------------------------------------------------------------- -------------------------
Grayish-brown SAND with silt, fine grained, dry to moist.
(SP_SM)
Very
Dense
—20
-
68
4
Very
Dense
—25
53
5.
Grayish -brown SAND, fine grained, dry to moist. (SP)
I
Very
Dense
—30
-
IT
51
5
Boring terminated at 31.5 feet.
Minor groundwater perched at 7 feet.
Terra
BORING LOG
Associates,.Inc.
POINT EDWARDS CONDOMINIUMS
EDMONS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environment . al Earth Sciences
P roj. No. T-4.893
Date JAN. 2003
Figure 7
I-)
Boring No. B-4
Logged by: DPL
Date: 12/16/02 Approximate Elev. 90
Soil Description
Consistency/
Relative
Density
Depth
(ft.)
E
Ca
(N)
Blows/
Moisture
Content
N
FILL (Old test pit): bluish -gray silty sand, fine grained,
Loose
wet, with a trace of wood particles. Appears disturbed.
7
27.
FILL (Old test pit): mottled brown silty sand, fine grained, moist.
-
Medium
Dense
—10
-
17
21
31
FILL (Old test pit): brown silt and clay, moist, with a trace
____of_b_rown orqanic-material -------------------------------------------------
Very
stiff ----------
Bluish -gray SILT to CLAY, low to medium plasticity.
Very
17
28
(MUCL)
stiff
'Gray SILT to CLAY, moist, low to medium plasticity.
(MUCL)
Very
Stiff
—20
-
30
23
LL 35.5
P1 .11.5
Grayish -brown sandy SILT to clayey SILT, fine grained,
moist. (ML) With thin partings of iron -stained, fine- grained
Very
stiff
35
23
sand.
Grayish -brown clayey Sl . LT to silty CLAY, moist. (MUCL)
With thin discontinuous lenses of gray to mottled gray
---- !in�t_q!ainecl sand ------------------------------------------------ -------------------------
Very
stiff
—30
30
24
Gray silty SAND, fine grained, moist. (SM)
Dense
:E
37
15
-------------------------------------------------------------------------
Gray sandy SILT to clayey SILT, . fine grained, moist, low
plasticity. (ML to MUCL)
--------------------------
Hard
—40
:E
34
17
Gray clayey SILT, moist, low plasticity. (MUCL)
j(-jg_qfi[jg:gjC4ined sand.
------------------------------------------------
Hard
-------------------------
37
20
Gray sandy SILT to silty SAND, fine grained,.moist,
Dense
—50
32
.19
(MUSM)
47
18
—60
42
15
Boring terminated at 61.5 feet.
No significant groundwater encountered.
Terra
BORING LOG
Associates, Inc.
POINT EDWARDS CONDOMINIUMS
EDMONDS, WASHINGTON
Consultants in Geotechnical Engineering
Geology and
Environmental Earth Sciences
Proj. No. T-4893TDate
JAN,2003
Figure 8
N
Boring No. B-5
Logged by: bPL
Date: 12/16/02 Approximate Elev. 105
Soil Description
Consistency/
Relative
Density
Depth
(ft.)
0
-a
E
U10)
� (N)
Blows/
ft.
Moisture
Content
N
Brown to gfayish-brown silty SAND, fine grained, wet,
with faint mottling. (SM)
----------------------------------------------------------------------------------------------------
Medium
Dense
:E
19
Gray SILT, medium to high plasticity, moist. (MH)
stiff
—10
_T
13
35'
---------------------------------------------------------------------------------------------------
Gray CLAY and SILT, low plasticity, moist. (CUML)
Very
stiff
25
.26
40
Gray silty SAND, fine grained, moist to wet. (SM)
-------------------------------------------------------------------------
Dense
--------------------------
—20
31
26
Gray CLAY, low plasticity, moist. (CL)
Very
22
27
stiff
42
Gray CLAY, low plasticity, moist. (CL)
Very
—30
22
.25
------------------------------------------------------------------------
stiff
--------------------------
Gray sandy SILT to silty SAND, fine grained, moist.
Dense
46
25
(MUSM)
-------------------------------------------------------------------------
Dense
------------------------
—40
-
43
15
Gray sandy SILT to clayey SILT, non -plastic, moist.
(MIL to MUCL)
------------------ 7 --------------------------------------------------------------------------------
Dense
31
20
Gray sandy SILT to silty SAND, fine grained, dry to moist
Dense
—50
46
18
Moist to wet.
---------------------------------------------------------------------------------
Medium
-Dense ---------
28
20'
Brown silty SAND, fine grained, moist. (SM)
Very
Dense
60
64
13
Boring terminated at 60.5 feet.
No significant groundwater encountered.
Terra
Ass'ociates, Inc.
BORING LOG
POINT EDWARDS CONDOMINIUMS'
EDMONDS, WASHINGTON.,
Consultants in Geotechnical Engineering
Geology and
'Environmental Earth Sciences
Proj. No. T-4893
I Date JAN 2003
Figure* 5
Logged by: JCS
Date: 10/18/01
Depth
0 FILL: crus
5
10
15
20
Test Pit No. TP-1
Approximate Elev. 104-
Moisture
Soil Description Content
hed rock surfacing over brown to gray silty sand to sandy silt, fine grained,
firm, moist. (SWML)
Rusty brown silty SAND fine grained, medium dense, moist, with occasional fine
\gravel and fine roots. (�M)
Gray to mottled gray silty SAND, fine grained, medium dense, to dense,
moist, with occasional fine gravel. (SM)
Becomes light brown at approximately 6 feet.
Gray CLAY, hard, moist, massive. (CL)
26
Pp 4.5+
tonsife
LL 35 , 8
PI 15
Test pit terminated At 14 feet.
No groundwater seepage.
Logged by: JCS
Date: 10/18/01
Depth -
0 FILL: crus
5
10
15
Test Pit No. TP*2
Approximate Elev. 124
Moisture
Soil Description Content
hed rock surfa ing over brown silty sand to sandy silt, fine grained, I irm,
-
moist. 4-inch thick orqanic layer at base. (SM/ML) (Old topsoil horizon)
-
Brown silty SAND, fine grained, medium dense, moist. (SM)
Mottled grayish -brown silty SAND, fine grained, medium dense, moist.
20
(SM)
Grayish -brown silty SAND, fine grained, medium dense to dense, moist.
(SM)
Gray CLAY, hard,,moist, laminated with light gray silt partings�. (CL)
Pp 4.5t
tonsift'
37
Test pit terminated at 14 feet.
No groundwater seepage.
20
TEST PIT LO GS
Terra POINT EDWARDS:CONDOMINIUMS
EDMONDS, WASHINGTON
Associates, Inc.
Geotechnical Consultants
Proj. No. T-4893 Date JAN. 900 1 Figure
r. I
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0 FILL: br
61
10
15
20
Test Pit No. TP-3
Approximate Elev. 121
Moisture
Content
Soil Description
own silty sand, fine grained, firm, moist, with occasional fine
gravel and organic material. (SM) (Hydrocarbon odor)
Dark brown organic silty SAND, fine gra—ined, soft, moist to wet. (OL)
(Old topsoil horizon)
.15
Tan to light gray sifty CLAY to clayey SILT, hard, moist. (CUML)
(Hydrocarbon odor)
Gray CLAY, hard, moist, laminated with partings of light gray silt a4gray
-
fine sand. (CL)
Pp=4.5+
32
tons/te
-
Test pit terminated at 13 feet.
Light groundwater seepage from point source at 4.5 feet.
Logged by: JCS
Date:. 10/18/01
Depth
(ft.)
0 — FILL: liaht
5
10
15
20
Test Pit. No. TP-4
Approximate Elev. 92
Moisture
Content
Soil Description
brown silty sand e ained to moist. (SM) 2-inch thick
gi� tirm, dry
-
016fin
Soil horij
organic layer at base. on)
top
-
Light brown to tan silty SAND, fine grained, medium dense to dense, dry.
-
(SM)
Mottled grayish -brown silty SAND, fine grained, medium dense to dense,
29
moist. (SM)
LL = 42.�.
Light drayish-brown to light brown CLAY and SILT, hard, moist, laminated
29
PI = 19.7
with partings of dark gray fine sand. (CUML)
Pp =� 4.5+
tons/te
Gray CLAY, hard, moist. (CL)
Pp 4 5+
:2"
tons/te
Test pit terminated at 13 feet.
Trace groundwater seepAge at 6 feet.
TEST PIT LOGS
Terra -POINT EDWARDS CONDOMINIUMS
EDMONDS,- WASHINGTON
Associates, Inc.
Geotechnical Consultants
Proj.No.T-4803 I Date, JAN 2003 1 Figure. 11.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
10
15
20
Test Pit No. TP-5
Approximate Elev. 110
Moisture'
Soil Description Conte'nt
MY
6 inches DUFF and TOPSOIL.
Light brown SAND with silt to silty SAND, fine grained, medium dense,
moist. (SO-SM/SM)
23
Mottled grayish -brown SAND to SAND with silt, fine grained; medium
dense to dense, moist. (SP/SP-SM)
Becomes wet at approximately 9 feet.
26
34
LL = 44.5
Grayish -brown to gray CLAY, hard, moist, generally massive, with
P.1 = 21.3
occasional thin laminations of gray silt.' (CL)
Pp = 4.5+
'tons/fe
-
Test pit terminated at 16 feet.
-
Light groundwater seepage between 9 and 10 feet.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
5
10
15
Test Pit No. TP-6'
Approximate Elev. 1*50
Moisture
Soil Desc . ripti on Content
-
FILL: brown to grayish -brown SILT, CLAY, and fine grained SAND, firm
-
moist to wet, with some fine gravel and occasional. organic material.
32
-
FILL: gray to brownish gray silt, clay, and fine grained sand, firm, moist to
-
wet, with'moderate organic material (including wood debris) and some
-
gravel. 12-inch thick organic layer at base. -(Old top soil horizon)
-
-
bray silty SAND to sandy SILT, fine grained, dense, moist,
with occasional fine to coarse gravel. (SM/ML) (Glacial till -like)
-
Test pit terminated at 16 feet.
-
No groundwater seepage.
20
TEST PIT LOGS
Terra POINT.-EDWARDS CONDOMINIUMS
E
Associates, Inc. DMO . NDS, W . A.SHINPTO.N
Geo*tedh.n1caJ consultants
Proj,.No.T-4893 DateJAN.2003 Figurel
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
5
10
15
20
Test Pit No. TP-7
Approximate Elev. 121
Moisture
Soil Descripti.oh Content
FILL: dark brown organic silty sand, fine'grained, firm, moist.
-
Mottled gray to brown SAND with silt to silty SAND, fine grained; medium
-
dense to dense, moist.. (SP-SM/SM) (Hydrocarbon odo,r)
20
Tan to light grayish -brown silty CLAY to CLAY, hard, moist, occasional
24
mottling. (CL)
Pp - 4.5+
tons/fe
31
-
Test pit terminated at 15 feet.
-
No groundwater seepage.
Logged by: JCS
Date: 10/18/.01
Depth
(ft.)
.0 ___:
1411
10
15
Test Pit No. TP-8.
Approximate Elev. 121
Moisture
Soil Description Content
FILL: light brown to gray silty sand, firm, moist to wet,.with organics.
FILL: dark brown -organic silty, sand, loose, wet, with significant wood
debris (timbers and branches). 2.5-foot diameter boulder..
Gray SILT to SILT with sand, fine grained, dense, moist to wet. (ML)
25
—7
-
Light grayish -brown to tan sandy SILT, fine grained,, very dense, moist,
-
with occasional fine gravel. (ML) (Glacial,tilklike)
16
-
Test pit terminated at 15 feet
-
Light groundwater seepage at 6 feet.
20
TEST PIT LOGS
Terra. POINT EDWARDS CONDOMINIUMS
Associates, In' c.* E,DlVI.0NDSj:.WASH_INGTON1.
Geotechnical Consultants 4893 D
Proj. No. T ate JAN 2008 Figure 13
k
Logged by: JCS.
Date: 10/18/01
Depth
ft)
0-
5
10
15
20
Test 'Pit, No-.- TP-9
Approxi , riiate Ele'v. 1-50
Moisture
Content
Soil Description (%)
-
FILL: crushed rock surfacing over grayish -brown, sandy silt and clay, firm,
-
moist. 6-inch thick organic layer at base. (Old topsoil horizon)
Mottle d grayish -brown. sandy SILT to sandy CLAY, stiff, moist. (MUCL)
Pp 4.5+
30
tons/fe
37
Grayish -brown CLAY, hard, moist, massive. (CH)
LL = 58.8
P1 = 30.1
Gray SILT and CLAY, hard, moist,with occas.ional laminations of gray
Pp = 4.5+.
fine'sand. (MUCL)
1 22
tons/ft'
-
Test pit terminated at 15 feet.
-
No groundwater seepage.
Logged by: JCS
Date: 10/18/01
Depth
(ft.)
0-
5
10
15
20
Test Pit No. TP40
Approximate Elev. 157
Moisture
Soil Description Content
6 inches DUFF and TOPSOIL.
Brown sandy SILT, fine grained, medium dense, moist. (ML)
Grayish-broWn SILT and CLAY, hard, moist. (MUCL)
Pp 4.5+
tons/ft'
I . 34
Gray SILT.And.CLAY, hard, moist. (MUCL)
Test'pit terminated at 15, feet.
No groundwater
TEST.PIT LOGS
err
T a -POINT EDWARDS CONDOMINIUMS
Associates,,Inc EDMONDS, WASHINGTON
C
Geotechnical onsultants;
Proi. No. T-4893 Date JAN 2003 Figure 14