016461
Edmonds view Property
CITY OF EDMOrrOS PROJECT N►,,,1E .
ENVIRONMENTAL ASSESSMENT DATE SUBMITTED October 15, 1980
-'�e information on this form will be used to determine the effect of your action upon the
�Avironment of the City of Edmonds Please answer h t'
eac ques ion as thoroughly as possible.
1.. LAND
Area 5 Acres Soils Type sandy w/cla
yp y Limitations none
Description of topography (% slope) 1.5 Acres 0 to 10%; .0.5 Acres
11 to 20%; 2.5 Acres 21 to 70% slope. NOTE: If grading or filling will
Grading: Estimated cubic yards 650 exceed 500 cubic yards a grading
Filling; Estimated cubic yards 0 and filling plan must be sub-
mitted with the application.
Estimated area to be paved (including buildings) 42,000 sf
Estimated area in open space (pervious surface) 11.5 acres
2. WATER
Stream - Estimated flow (cubic .feet per second) 0.5
Will. stream be altered?, No If yes, to what degree?
Other water bodies?
Impact on storm drainage minimal Method of handling runoff retention
pond with slow release
Adjacent to shorelines zone?. No Within 200 feet of MHHW? No
VEGETATION
�r Type and approximate number of trees entire site is presently woodeded, trees will only
be removed for roads and building footprints.
Minimum diameter of trees to remain 611 % of trees to be removed 20
Ground cover S014 Oregon Grape, Huckleberry, etc. o
to be removed 20
Proposed landscaping, if any new landscaping will utilize indigenous plant materials.
4. EXISTING LAND USE WITHIN 300 FEET RADIUS OF PROPOSED DEVELOPMENT:
Single Multi -
Vacant Family Familv Commercial. Other
North X
South
5. CIRCULATION
Estimated increase in auto trips daily, 120 to 140
Availability of public transportation
6. AREA OF IMPACT
Neighborhood x City-wide Regional
. EFFECT ON AIR QUALITY minimal
S. CHANGES IN NOISE GENERATION minimal
MW
■r