01678EDMONDS-VIEW PROPERTY ESTIMATED SCHEDULE
This schedule to be final must be approved by City of Edmonds in writing.
1. Submit Preliminary P.R.D.
2. City Environmental Checklist
Determination (if E.I.S. required
adds 4-6 months to this Project
Schedule).
3. Planning Commission
Preliminary Review
4. Submit final P.R.D. and Short
Plat Application.
5. Public Hearing by Hearing Examiner
(date not formaly set at
this time).
6.'Written Decision by Hearing Examiner
(date not formaly.set at
this time)
7. Architect Design Board final
Review.
8. Submit construction documents of
roads and utilities for building
permit to building department.
9. Attend City Council for Preliminary
P.R.D. approval.
10.Correetions to construction
documents by City of Edmonds
submitted February 16, 1981.
11.City of Edmonds issues building
permits for roads and utilities.
r
12.Start site construction on roads
and utilities.
13.Complete site construction of roads
and utilities.
October 15, 1980
November 1, 1980.
November 12, 1980
December 15, 1980
January 15, 1981
January 25, 1981
February 11, 1981
February 16,.1981
February 23, 1981
February 26, 1981
March 9, 1981
March 10, 1981
May 10, 1981
14.Start construction of buildings. June 10, 1981