01679Schedule Notes
A Please note this schedule has not been approved by the Cityrof Edmonds
as of yet, until it is, this is an estimate based on our October 15
meeting with the City of Edmonds.
B. The meetings outlined items 1-9 are scheduled for initial acceptance,
but the Edmonds P.R.D. application process allows for two or more
reviews at 2.weeks to a month intervals. WJA does not anticipate more,
than one review with each group, if addition reviews are required a new
project schedule -is required.
C. The Hearing Examiner has not been selected at this time and his meeting
dates are not set. Until a final schedule for this individual is
established all meetings with the Hearing Examiner are estimates. The
Hearing Examiner position is expected' to be filled by January 1981.