05.13.2013-PlatatWoodway_DFR_1_LBK-special inspect-pit drain (2).pdf
FIELD REPORT
Page 1of 4
911 Fifth AvenueDateProject NameProject No.
Kirkland, Washington 98033
5/13/2013Plat at Woodway ElementaryKH060644B
P: 425-827-7701 LocationMunicipalityWeather
th
F: 425-827-542423708 104Ave West, Showers/50-
EdmondsCity of Edmonds60s
www.aesgeo.com
Permit No.DPD No.Report No.
1
TO:Engineer/Architect
Burnstead Construction CompanyThe Blueline Group
th
Client/Owner
119880 NE 24Street, Suite 200
Bellevue, WA 98005
Burnstead Construction Company
General Contractor/Superintendent
ATTN:Ms. Tiffiny Brown
AS REQUESTED BY:Curtis Koger
EarthworkContractor/Superintendent
TE Briggs Construction/Tracy
THE FOLLOWING WAS NOTED:
Associated Earth Sciences, Inc. (AESI) was onsite part time today at the client’s request to observe the construction of a pit drain
located in the infiltration vault, and the preform infiltration rate flow testing in the pit drain.
Infiltration Vault and Pit DrainBackground
The current design plans include aninfiltration vault. The vault will be a below grade structure with cast-in-pace concrete walls,
precast concrete roof panels, and an open base through which storm water will be allowed to infiltration into the sediments and a pit
drain below the vault. The pit drain will consist of a pit excavated below the floor elevation of the vault and backfilled with pea gravel.
Backfill specifications were provided in our Technical Memorandum dated May 7, 2013.
Pit Drain Construction
Prior to pit drain construction, the infiltration vault was excavated to approximately 0.5-foot of the final grade, which was measured
by the earthwork contractor, and roughly corresponds to319 feet (ft) above mean sea level (amsl). We understand the earthwork
contractor plans to finish final grading of the vault after the majority of construction activities utilizing heavy equipment havebeen
completed in order to protect the vault subgrade from contamination.
The pit drain was excavated using a track-mounted excavator (John Deere 450C LC) with a 32-inch wide bucket with teeth.The pit
drainwas excavated to approximately 16 ft below existing grade along the sidewalls, and 17 ft below existing grade in the center.
Based on a review of the plans and survey staking, these depths would correspond to303.5 and 302.5 ft amsl, respectively. The
footprint of the pit was excavated to approximately 3 wide by 10 ft longat the bottom of the pit, and 4wideby 12 ft longat the top. A
2-inch diameter polyvinylchloride (PVC) piezometerwas placed roughly in the center of the pit to facility water level observation
during testing. The total length of the piezometer was 20 feet, and included 5-ft of 0.020-inch machine slotted well screen at the
bottom with a threaded cap, and 15-ft of blank well casing with threaded connections.The pit drain was backfilled with washed pea
gravel to 318 ft amsl, and 4 x 8 sand from 318 to 319 ft amsl.
Pit Drain Testing Mehodology
Generally, the infiltration testing method consists of introducing water from a water truck provided by TE Briggs through an
electronic flow meter with instantaneous and total flow readout and into the pea gravel via a 2-inch diameter hose placed into the
gravel pack. The water level in the pits was monitored in the PVC sounding pipes, placed on the bottom of the pit, with an electronic
water level meter. Water was introducedintothe pit until the water truck was out of water. Following the discontinuation of water
Copies To:Field Rep:Lara B. Koger
Date Mailed:Principal / PM:Curtis J. Koger, L.G., L.E.G., L.Hg.
AESI FIELD REPORT
Page 2of 4
To:Distribution ListProject Name:Plat at Woodway Elementary
Date:May 13, 2013Project No.:KH060644B
Permit No.DPD No.
flow, water levels were monitoring with the electronic water level meteruntil no water was measurable in the piezometer,
approximately 40 minutes.
Pit Drain Testing Details and Results
We understand that the design flow rate for the infiltration vaultand pit drain is 7 inches per hour (iph). As presented in Table 1,the
measured field rate was approximately 33iph. The maximum water level reached during testing was 10.5 ft below the existing ground
surface,or approximately 6.5 ft above the bottom of the pit drains.
Table 1
Pit Drain Testing Summary
Maximum Water Maximum Water Total Water Used Average Flow Equivalent Field Design Rate
Level (ft from Level from Base of (gallons)Rate Rate (inches/hour)(inches/hour)
existing grade)Pit Drain (ft)(gallons/minute)
10.56.51,55093337
Attachments:
Pit Drain Schematic
Copies To:Field Rep:Lara Koger
Date Mailed: Principal/PM:Curtis Koger, L.G., L.E.G., L.Hg.
Ѝ
ƚŅ
Ќ
tğŭĻ
at Woodway Elementary
KH060644B
ŅĻĻƷ
Plat
ЊА
{ƚǒƷŷ
ŅĻĻƷ
ЊЏ
ŅĻĻƷ
Ѝ
ŅĻĻƷ
Ќ
bƚƩƷŷ
ŅĻĻƷ
ƒğ
ƚŅ
ŅĻĻƷ
ğƓķ
ŅĻĻƷ
źƓĭŷ
βЌЊВ͵Ў
ƚƓƭ
ЌЊВ
ĭğƦ
Љ͵ЉЋЉЊЎ
9ƌĻǝ͵
ĻƓķ
ĭƚƓƓĻĭ
9ƌĻǝ͵
ğƓķ
ƚŅĭğƭźƓŭͳ
ƭĭƩĻĻƓͲ
CƌƚƚƩ
CƌƚƚƩ
ŅĻĻƷ
ƷŷƩĻğķĻķ
ğǒƌƷ
ǞĻƌƌ
Ў
ğǒƌƷ
ƭƌƚƷ
t/Ͳ
May 13, 2013
ĬƌğƓƉ
CźƓźƭŷĻķ
ĭŷźƓĻ
Ɠŭ
źƓĭŷ
9ǣźƭ
Ћ
Ѝ
ƚŅ
Ѝ
ŅĻĻƷ
tğŭĻ
at Woodway Elementary
ЊА
ŅĻĻƷ
9ğƭƷ
KH060644B
ЊЏ
Plat
ŅĻĻƷ
ЊЉ
ŅĻĻƷ
ЊЋ
ĻƭƷ
ŅĻĻƷ
ƒğ
ƚŅ
ŅĻĻƷ
ğƓķ
ŅĻĻƷ
źƓĭŷ
βЌЊВ͵Ў
ƚƓƭ
ЌЊВ
ĭğƦ
Љ͵ЉЋЉЊЎ
9ƌĻǝ͵
ĻƓķ
ĭƚƓƓĻĭ
9ƌĻǝ͵
ğƓķ
ƚŅĭğƭźƓŭͳ
ƭĭƩĻĻƓͲ
CƌƚƚƩ
CƌƚƚƩ
ŅĻĻƷ
ƷŷƩĻğķĻķ
ğǒƌƷ
ǞĻƌƌ
Ў
ğǒƌƷ
ƭƌƚƷ
t/Ͳ
May 13, 2013
ĬƌğƓƉ
CźƓźƭŷĻķ
ĭŷźƓĻ
Ɠŭ
źƓĭŷ
9ǣźƭ
Ћ