Loading...
09.21.2018-Engineering_Correction_Notice-Magic Toyota (2).pdf°F EDAf 0 �St. 1890 DATE: September 21, 2018 CITY OF EDMONDS CORRECTION NOTICE ENGINEERING DIVISION (425) 771-0220 City Website: www.edmondswa.gov PERMIT NUMBERS: BLD20170493 Fill/Grade/Excavate, ENG20170122 Stormwater, BLD20161684 New Commercial, ENG20170333 Side Sewer, ENG20170286 Right -of -Way, OWNER: Magic Toyota, Peter Chung ADDRESS: 21300 Hi2hwav 99 SITE CONTACT: Paul Wassell TYPE OF INSPECTION: FINAL INSPECTION — New Car D ® CORRECTIONS LISTED BELOW MUST BE MADE BEFORE CITY ENGINEERING DIVISION CAN PROVIDE FINAL CONSTRUCTION APPROVAL ® RECALL FOR INSPECTION A final inspection was not requested, however, in an effort to be well informed of the project status, city engineering inspectors performed a walk-through on August 28, 2018. It is understood that some of the items noted below may already have been corrected at this time. A follow-up inspection shall be scheduled by the contractor when all items have been corrected or as needed to complete individual phases of work. 9/4/2018 — Original Inspection 9/17/2018 — Re -inspection 9/21/2018 — Updated correction BLD20170493 — Fill/Grade/Excavate (civil site and utility work 1. ok 2. ok 3. Trash enclosure - Drop pin holes not installed for use when gate is in open position and drop pin does not exist on north gate. 9/17/2018 - Correction not addressed. 9/21/2018 — Contractor informed they are working on this. 4. ok 5. ok 6. Construction debris to be removed from site to ensure storm system remains clean and functioning properly. 9/17/2018 - Much of the site has been cleaned, few materials remain. Will inspect again prior to final. 9/21/2018 — Will confirm the last of the cleanup with the final re-insepction. 7. Electronic asbuilt of civil construction improvements to be provided to the City. Asbuilt shall include complete civil plan sets. 9/17/2018 - Not yet received. 9/21/2018 — Not yet received. This will not hold up final C of O — the City will continue to work with the applicant/owner on this item. ENG20170122 — Stormwater (stormwater detention vault 1. ok 2. ok 3. ok ENG20170286 Right -of -Wad 1. ok 2. Open trench along backside of sidewalk along Highway 99 needs to be backfilled. 9/17/2018 - Final restoration in process during inspection. Will inspect again prior to final. 9/21/2018 — As noted, will inspect again at final re -inspection. 3. The utility pole on 2121h St SW is to be relocated to the back of the sidewalk. Separate communications on this are taking place with Peter Chung and David Estes. If this item has not been resolved prior to final certificate of occupancy, a performance bond shall be held in place until the work is complete. With a performance bond in place, final C of O will not be held back for this item alone. 9/17/2018 - This issue has not yet been resolved. 9/21/2018 — This issue has not yet been resolved. As noted, with the performance bond in place, this item will not hold up issuance of final C of O. 4. Sidewalk surrounding PUD pole on 2121h St SW was not replaced with temp asphalt as requested. Concrete was placed, but was not poured with joints placed to meet City standards and the section immediately around the pole was not poured. In addition, the sidewalk was poured around the guy anchor within the pedestrian path of travel. These issues will be resolved with relocat 9/17/2018 - This issue has not yet been resolved. 9/21/2018 — This issue has not yet been resolved. As noted under item 3 above, with the performance bond in place, this item will not hold up issuance of final C of O. ok Page 2 of 3 6. ok BLD20161684 — New Commercial 1. Trash Enclosure: Drop pins required on both sides of gate. Sleeves to be placed in the asphalt for the pins to drop into when in the open position. 9/17/2018 - Correction not addressed. 9/21/2018 — Contractor has indicated they are working on a solution to this. 2. ok 3. ok ENG20170333 — Side Sewer 1. Oil/Water Separator in front of mechanic bays could not be opened due to asphalt debris stuck in the latch. Please remedy and ensure the separator has been cleaned and operating properly. 9/17/2018 — Hatch is now operable. Contractor to verify what white PVC pipe is coming into the south wall of the oil/water separator. 9/21/2018 — Have not yet received confirmation as to what the PVC pipe is. This will need to be resolved prior to final C of O. 2. Install twist plug in sewer cleanout located in paved drive aisle near north end of mechanic bays. 9/17/2018 — A twist plug was added at this particular cleanout. It was discovered during the re -inspection that an additional sewer cleanout, just east of the oil/water separator, does not have a twist plug. Please correct. 9/21/2018 — This will be confirmed to have been completed at the final re -inspection. The actions or corrections indicated above are required to be corrected PRIOR TO FINAL. Call 425-771-0220, ext. 1326 for all required inspections and/or re -inspection Page 3 of 3