1.9.19 - Eng. Inspection Correction Notice.pdfCITY OF EDMONDS
of EDA0 CORRECTION NOTICE
ENGINEERING DIVISION
CJ N
(425) 771-0220
City Website: www.edmondswa.gov
�sr. 1890
BLD20171296 & 1295
DATE: January 9, 2019 PERMIT NUMBER: PLN20160012 ENG20170309
OWNER: SITE CONTACT: Duane Landsverk
ADDRESS: 19125 941h Ave W.
TYPE OF INSPECTION: Final Inspection — Single Family Homes, Short Plat & Right of Way
❑ WORK DESCRIBED BELOW HAS BEEN INSPECTED AND APPROVED
❑ APPROVED PLANS AND PERMIT JOB CARD MUST BE AVAILABLE TO INSPECTOR
ON SITE
❑ CORRECTIONS LISTED BELOW MUST BE MADE BEFORE WORK CAN BE
APPROVED AND/OR THE NEXT PHASE OF WORK IS STARTED.
® RECALL FOR INSPECTION
❑ REINSPECTION FEE MUST BE PAID PRIOR TO NEXT INSPECTION REQUEST.
❑ STOP WORK UNTIL AUTHORIZED TO CONTINUE BY CITY INSPECTOR
BLD20171296 - 9306 192 PI SW
1. Provide the city with manufacturer specification for the permeable pavers installed.
2. Provide documentation showing that the pavers have been installed per manufacture
specifications.
3. Provide the city with a stormwater covenant accounting for the installed infiltration system as
well as the permeable pavers.
4. Install gripper type twist plug into 6" sewer cleanout, per city standard detail SS-200.
5. Submit as-builts.
6. Per short plat civils, native vegetation is required on portions of this site. Obtain approval of
landscaping from the Planning Division and/or bond shall be in place as directed by the
Planning Division.
BLD20171295 — 9304 192°d St SW.
1. Per short plat civils, native vegetation is required on portions of this site. Obtain approval of
landscaping from the Planning Division and/or bond shall be in place as directed by the
Planning Division.
2. Exposed soils outside of native vegetation area will need to be compost amended and stabilized
with bark/mulch, straw, plants, etc.
3. Installed crushed rock within the driveway will need to be removed and replaced with the
manufacture specified sub -base material for the permeable surface.
4. Permeable surface and sub -base layers will need to be inspected to verify install per
manufacturer specifications.
5. Install gripper type twist plug into 6" sewer cleanout, per city standard detail SS-200.
6. Provide the city with a stormwater covenant accounting for the installation of infiltration system
as well as the permeable driveway.
7. Submit as-builts.
ENG20170309 — Subdivision Right of Way
1. The low lying rhododendron limbs extending into 192nd Pl SW (as identified during final
inspection) will need to be cut such that the limbs do not extend over the asphalt.
PLN20160012 Short Plat
1. Mailboxes for both new single family homes need to be installed.
2. Fire/aid address sign needs to be installed for 9304 192nd St SW & 9302 192nd Pl SW.
• Provide a check for $75.00 to the City of Edmonds to manufacture sign. Submit to
Development Services Department Attn: Jeanie McConnell.
3. As discussed, since compaction reports were not obtained, you may provide a 5 year
performance bond for the amount of $10,819.90. Please note that the number was determined
by the Bond Quantity Worksheet provided with the short plat. You may provide a new Bond
Quantity Worksheet (if you feel the amount is incorrect) that shows the cost associated with the
removal and replacement of all trench work and road widening. We have to account for the
worst case scenario that all work may fail. Or the other option is to complete the compaction
testing in both the trench and road widening areas and repave as required.
4. Provide a 2 year maintenance bond in the amount of $6,768.18.
5. Obtain Planning Final approval.
For inspection scheduling call 425-771-0220 x1326.
Page 2 of 2