Loading...
16-1113 Plan review comments 2.pdfCITY OF EDMONDS • 121 51h AVENUE NORTH • EDMONDS, WA 98020 PHONE: 425.771.0220 • FAX: 425.771.0221 • WEB: www.edmondswa.gov DEVELOPMENT SERVICES DEPARTMENT: PLANNING • BUILDING October 11, 2016 November 1, 2016 Rick Bynum Maston Properties rick@mastonproperties.com RE: PLAN REVIEW COMMENTS #2 FOR PLAN CHECK # 2016-1113 NEW SFR AT 23914 84TH AVENUE WEST Rick, I have again reviewed the above building permit application for the Planning Division. Before I can sign off on the permit, the following information needs to be clarified in a written response and through submittal of updated plans with changes called out. New comments are in italics. Plans flipped: Is the layout of the site plan correct or are the building plans? If the building plans are correct, update the site plan to match the layout shown on the building plans. The Site Utility Plan does not agree with the layout shown on the building plans. Verify which is to be used. There is a shadowed garage space shown on the building plans but it appears to be included on the site plan. Verify whether that portion of the structure is to be included with the project at this time. 2. Lot area: Addressed. On the Site Utility Plan, please verify the gross and net lot area for Lot 2 and update the structural lot coverage and impervious calculations as appropriate. 3. Rear deck, front steps: Addressed. Please show all proposed features on the Site Utility Plan. 4. Structural lot coverage: Addressed. Per ECDC 21.15.110, "[c]overage means the total ground coverage of all buildings or structures on a site measured from the outside of external walls or supporting members or from a point two and one-half feet in from the outside edge of a cantilevered roof, whichever covers the greatest area." Break out the square footage covered by the house, extra garage, front porch and steps, as well as the west deck, and then show a total structural coverage as a percentage of net lot area. 5. Datum point: Addressed. Please identify the 440.46' TBM on the Site Utility Plan. 6. Height calculations: The calculations appear to have been updated on the October 14 site plan but the lines of average original grade, maximum allowed height, and proposed height were not included on the elevation drawing. Update Sheet Al to include these lines. Please refer to Handout B141 for assistance on height calculations. If the rear deck has an impervious surface, it must also be included in the height rectangle since it is covering the patio below. Once average original grade, maximum allowed height, and proposed building height are recalculated, show those on the Site Utility Plan and lines for each on Sheet Al. The development code, handouts and related materials are available at: http_://www.edmondswa.gov/2015-01-22-21-27-29.html. Please submit two copies of your updated site plan and two sets of any updated sheets of the building plans. Please make all submittals to a Permit Coordinator, Monday through Friday, 8:00 am to 4:30 pm (8:30 am to 12:00 pm on Wednesdays only). If you have any questions, please contact me at (425) 771-0220. Sincerely, Mike Clugston, Al Associate Planner