18 01 04 Summary of meeting with City.pdfSALUS
HEALTHCARE ARCHITECTURE
Project ... Northpoint Recovery, Edmonds, WA Date ................................ January 4, 2018
Topic .......... Preliminary Meeting with City of Edmonds Project # ......................... 16029
Participants
Namc
Organization
Rol(-
Email
•
Christina Wayland
City of Edmonds
Permit Coord.
Christina.wayland(2edmonds.wa.aov
•
Mike Clugston
City of Edmonds
Planning
Michael.cluaston(2edmonds.wa.aov
•
Kevin Zweber
SSCF & Rescue
Fire Marshal
kzweber@southsnofire.org
•
Leif Bjorkback
City of Edmonds
Building
Leif. beorkbackged monds.wa.gov
•
Joss Gramstad
KPFF
Civil Engineer
Joss. a ramstadgkpff.com
•
Chris Borzio
KPFF
Civil Engineer
Chris.borziogkpff.com
•
Faramarz Manteghi
Salus Arch.
Architect
Faramarz. manteg h igsal us. arch i
•
R David Frum
Salus Arch.
Architect
David.f ru m(2sal us. arch i
0
City of Edmonds
No Item
1 David introduced the project: a residential drug and alcohol voluntary treatment
facility to accommodate up to 44 patients. The building, currently used for
commercial tenants, will be converted without building additions. The site will
maintain its current parking and driveway with modifications. Canopies will be
added at the entrance and in the landscaped, enclosed outdoor patio.
Fire Marshal
2. A sprinkler riser room is required at the northeast corner of the building with door
directly to the outside. The mechanical engineer will determine the size of the
room.
3. The fire hydrant located on the SW corner is private and non -conforming. Its
connection would have to be routed such that it is fed behind the backflow
preventer at the sprinkler riser.
4. A new FDC (fire department connection) is required at the street. It's connected,
via dry pipe, to the riser room.
5. Kevin discussed options for the fire truck turn around. Joss and Chris will study KPFF
options and consult with Eric accordingly.
6. The building is required to have a fire alarm system.
7. Fire flow data is available from COE Engineering (JoAnne)
Charges (permit, other)
8. Charges related to fire department permitting: Fire line/connection; Fire
alarm/sprinklers; Type I hood.
9. Mechanical and plumbing review.
10. Utility connection fees: water, storm and sewer by the city. These depend on McDonald
whether these connections need to be expanded. McDonald Miller to study. Miller
11. Gas connection fees: by Puget Sound Energy.
1402 Third Ave, Suite 200 / Seattle, WA 98101 / T 206.652.0722 / F 206.340.2266 / www.salus.archii
Meeting Northpoint Edmonds, Meeting with City Staff
January 5, 2018
Page 2
12. Electrical connection fees: by Snohomish County PUD. Electrical permit review
will be done by L&I.
13. Christina provided Salus with a copy of the permit submittal requirements for Christina
tenant improvements. The base permit fees are based on the valuation of the Wayland
construction. However, additional hourly fees ($1 00/hr.) are assessed based on
the specifics of the project. Christina will provide Salus estimates from similar
(nursing home) projects.
14. The plumbing permit fees are predicated on the number of fixtures in the facility. McDonald
Christina provided a plumbing permit fee. McDonald Miller will work out a ROM Miller
fee number.
15. The traffic review is done at $120/hr. with $200 initial fee.
16. Right of way permit is $350.
Site and Landscape
17. No apparent frontage improvements will be required, unless the project exceeds Salus
10% of addition (canopies count) and/or 10% of added parking. Salus to review
other potential triggers in the General Commercial Code they referenced.
18. Maintaining the impervious surface disturbance under 2,000 s.f. will be KPFF
challenging. On site storm water management (OSM) will be required if this target
can't be met. OSM would require the likes of LID stormwater infrastructure
(pervious pavements, bioretetion etc).
19. Verify in the 2017 addendum to the drainage code whether the project will require KPFF
onsite stormwater management for 25% of the exiting hard surfaces to remain.
20. No known drainage capacity issues
21. The slope will require submittal of an updated critical area checklist, performed
by a geotechnical engineer.
22. Street trees would have to be replaced if removed. No new requirement, unless
frontage improvements are required.
23. Landscape: 17.5 s.f. landscape is required per parking stall.
24. The ivy needs to be replaced. David noted that the owner intends to improve the
landscape to upgrade the facility's image.
25. The building maybe required to be brought up to Type 4 landscape standards. Communita
Communita Atelier will verify
26. Mike suggested that the team review the G.C. zoning code, updated last August. Salus/
It contains language regarding pedestrian oriented space pertaining to this Communita
property. Ideally remain below the 10% trigger (see 12 above) so as not to trigger /KPFF
additional requirements.
27. Verify parking requirements, using the residential standard (.75 stall per unit Salus
under 700 s.f.).
28. Rooftop mechanical units require screening. A structural engineer's seal would be
required for any unit exceeding 400 lbs.
29. Note that on site lighting should light the site only. Light poles should not exceed
Meeting Northpoint Edmonds, Meeting with City Staff
January S, 2018
Page 3
25', shielded.
Building construction
30. A demolition permit for the interior, non -bearing elements can be obtained over
the counter. A Puget Sound Clear Air Agency number (for the hazmat abatement)
will be required prior to issuing the permit.
31. It is possible to get a separate re -roof permit as well. The roofing permit should
be accompanied with a Puget Sound Clear Air Agency number (for the limited
asbestos abatement).
32. David indicated that Salus has been coordinating with Clynn Wilkinson of the WA
DoH. Leif knows Clynn and trusts his code judgement.
33. The building type is likely to be 5B.
34. The code review should start with the new IEBC, International Existing Building
Code with Edmonds amendments (on line).
35. Leif noted that each side of the smoke barrier should have access to, at least, one Salus
independent egress.
36. The occupancy of the dining room is likely to justify the two exists shown.
Accordingly, there should be two lit sign gateways from the fenced in yard..
37. Leif suggested that the architects review chapter 5 of the IEBC for the scoping of
existing buildings and its implications.
38. Permit review time frame: 20-30 business days to initial review. 2-3 months all
together. All submittals are done in hard copy only.
End
Submitted by .... R David Frum