Loading...
1875.01_DFR 3_11.07.17.pdfZipper Geo Associates Daily Field Report ZGA Project 1875.01 Daily Field 3 Page: 1 of 2 No.: Report No.: ................ ........ .................................... Project: Stormwater Detention Pipe Location: 622 Bell Street —Edmonds, WA ........ ......... .......... Installation Evaluation ........ ......... .......... Client: ......... .......... ......... Johnny Vong Contractor: ........ ......... .......... ........ ............... ......... ......... ......... ......... ......... Al Asphalt ........ ZGA Field Rep: ..... B. Fowler Permit No.: ................................................................................................................................................................................ 6354052 ........ ......... .......... Date: ........ ......... .......... ........ .............. 11/7/2017 ......... ... Arr./Dep. Time: ......... .......... ........ ........ ........ ........ ............................................ 9:00 am / 11:00 am, 1:30pm / 2:00pm Weather Overcast, 50s ........ Equipment ........ ........ ........ ........ ........ ......................... Plate compactor, skid -steer loader, Used: HMA paver We arrived on site at the request of the client Johnny Vong. The purpose of our site visit was to evaluate utility trench backfill in the City of Edmonds right-of-way. Utility trench backfill Upon arrival, we observed that the contractor had installed and backfilled above a storm drain pipe that extended laterally across Bell Street from CB # 4 and runs parallel next to the sidewalk in front of the residence. ZGA was not onsite during installation of the pipe and did not observe backfill compaction. As such, ZGA can only evaluate the compaction of upper 6 to 12 inches of the trench backfill. Project superintendent Johnny Vong indicated that the City of Edmonds requires compaction testing of the trench backfill that extended into Bell Street. The paving contractor, Al Asphalt was on site to remove the existing cold patch, prepare the subgrade, and pave the utility trench lines. The contractor saw cut the cold patched areas and roughly 1% feet laterally of the existing roadway around the cold patch areas. After removing the cold patch, the contractor re-compacted/smoothed out the trench backfill with a plate compactor in preparation of paving. We observed that the earthwork contractor had backfilled above the utilities with pit run sand and gravel. We completed two in -field nuclear density tests at pavement subgrade elevation, one each in the westbound and eastbound lanes. All test results met or exceeded 95 percent compaction. Test results are shown in Table 1 below. Mr. Vong asked that we visit the site later in the day to observe subgrade preparation of the section of trench backfill that extended parallel to Bell Street next to the sidewalk. Initial hand probing of that section of trench line penetrated 6 to 8 inches. Fill generally consisted of a mixture of pit run sand and gravel, 5/8-inch minus crushed rock, and recycled concrete fragments, as such conventional nuclear density testing was not feasible due to the coarse nature of the material. We recommended that the trench section be compacted to a firm and unyielding state prior to paving to reduce the risk of settlement. The paving contractor indicated that the upper 4 inches of loose material would be removed and the underlying subgrade re -compacted. When we arrived on site in the afternoon, we observed that the contractor had removed the loose fill and compacted the subgrade with a plate compactor. Subsequent hand probing penetrated minimally indicting that the fill had been adequately compacted for pavement subgrade, in our opinion. Reviewed by: ljitw This field report presents the results of our on -site testing as well as the observations and opinions of the field representative regarding the contractor's activities. The contractor is responsible to complete the project in accordance with the approved plans and specifications regardless of our presence on site and our observations and test results. Our services do not include supervision or direction of the contractor's work of that of its subcontractors or responsibility for job site Zipper Geo Associates Daily Field Report Daily Field Report ZGA Project No.: 1875.01 3 Page: 2 of 2 No.. .................................................................................................................................................................................................................................................................................................. Stormwater Detention Pipe Project: Date: 11-7-17 Installation Evaluation Table 1. Summary of Field Density Test Results Test Test Test General Approx. Feet Mat'I Field % % Pass/Fail Elev. No. Date Method Location to Type Dry Field Comp. (ft) Grade Density Moist. Field (pcf) DT-1 11/07 N CB # 4 trench N/A 0 1 129 4 95 P backfill in City of Edmonds right-of-way (WB lane) DT-2 11/07 N CB # 4 trench N/A 0 1 131 4 96 P backfill in City of Edmonds right-of-way (EB lane) Percent Compaction Based on: Specification: ® Modified Proctor, ASTM D 1557 ® 95% ❑ 90% LEGEND DT = Density Test RT = Retest TEST METHOD N = Nuclear (ASTM D 292) Optimum Material Reference Material Max. Dry Moisture Type Sample # Description Density (pcf) (%) Import Fill (pit run 1 NA 136 5 sand and gravel) *Typical value based on material composition. 19023 36t" Avenue W., Suite D, Lynnwood, WA 98036 P (425) 582-9928 F (425) 582-9930