20060207.pdfeWGINCIERING 1`4ELD OBSERVATION REPORT Project: Field Representatives: Stensland Residence Remodel Chrs Bernards P.E. Job No.: 05181.10 Report No. I Date: April 9, 2006 Location: Purpose of Site Visit: 8807 201 " Place SW Observe the general construction progress Edmonds, WA 98026 Client: General Contractor Chermak Construction Chermak Construction �NARRATIVE On April 6t", CG Engineering performed a site observation of the construction for the Stensland Residence in Edmonds, WA. The primary goal of the site visit was to observe the Construction progress as well as check for general conformance with the approved construction drawings. The following issues were discussed vvith the contractor. FZECEIVED 1. At tie east end of the 63/." glularn beam, there is not adequate length to install the APR 1 2006 4'strap as shown on 21S2.1. The contractor shall instal a CS16 strap from the notched portion of the glularn to the rough opening approximately 3'away. The DEVELOPMENT SERVICES CTR. contractor shall also add a 4' CSI 6 strap centered at the beam above this CITY OF EDMONDS opening. In both cases, the strap shall be nailed to added blocking between studs. 2. The east end of the 6/."giLlam beam did not have a holdown installed horizontally to the perpendicular wall as shown in 9/S2. 1. The contractor shall install this strap to the 2x12 adjacent to the shear wall and nail the 2x12 to blocking between each stud with 16d nails at 4" o.c. Install (I) -Simpson A35 each sice of each wall stud to attach the wall StLds to the 2xI 2. These should be staggered an the stud top and bottom of the 2x1 2. 3. The crpple wall above the concrete wall does not allow for the installation of a PHD5 per 2/S2.1. The contractor may install afternate holdown straps as shown in the attached sketch, SS-3. 4. The east end of the existing floor beam bears an the concrete wall further away then originally thought. The contractor will attach a P.T. 6x6 post to the concrete wall to help support this beam. The pos*, shall attach to the wall with (4)-equally spaced 519'diameter anchor bolts embed 4" into the wall with Hilti HIT HY 150 epoxy or equal. The conclusions and recommendations in this report are based on what was observable at the time of the site visit. If conditions appear significantly different than those described above, please contact us immediately for further review. This observation is 250 An Ave. South not a sufficient substitutiol for the inspection requirements shown on S1.0. Please feel free to call if you have any questions or concerns or to, more information or Eilmorlds,WASS02D the observations and recommendatiors above. Phore. 425.778,8500 Fax: 425.77B.562% Z 0 0 m -i m C M 0 80 C --i Im 0 m n M m U CO 0, 0 C M Co Q 0 Zq In Z CA Z 0 m j)r5L rrvo e R-_p—A), V1 -PAIJft &066-filrowli(p P&A- Ft�,M IUDIZ- i N -C OT -H PLINVOo At A44QD ForL tW-TALL"ON .Pw, le p qw Ai�". W�TD, C - I (,TT-131, M, 1,:IT;040 �:Pm jtrtW�lio TD Oi3L 2x, STUD . IN wp PPM0 s 04� h4Afsl . Ikm Wku�, W/ t"un, HIT Ra /P EPOYP� OR.. 6�WAI- 2-372 �Aotpowtj ALWO(T6 Dt-7-AIL, By CAS D Che t, 84GINC-EFUNG swe ot No. 250 4thAve. South Suite 200 P-j- M sTefisLAM Job No. Edmonds,WA98020 CF:1181 1 10 z 0 m m -q 0 0 0 -4 C m M 0 n n m M 0 0 C: M 0 X > z z 0 m Project: Stenslanc Residence Remodel Field Representatives, Chris Bernards P.E, Job No.: 05181,10 ReportNo.2 Date: April 10", 2006 L*cation: Purpose of Site Visit: 8807 201 " Place S.W. Holdown Epoxy Anchor Bolt Installation Edmonds, WA 98026 Client; General Contractor: 0 Chermak Construction Chermak.Construction V 'ARRXTIVE"' 3: r" On April Id", CG Engineering performed a site observation of the construction for the m 0 -40 Stensland Residence in Edmonds, WA, The primary goal of the site visit was to observe 0 C k" t�e holdown epoxy bolt Installation for general conformance with the approved construction drawings. The following items summarize our findings: m m Z . Simpson Set-Pac Epoxy used (acceptable alternate to Hilt! HIT HY 150) > . Hole diameter was 1/." r- . Hole depth was 7' . 516' diameter threaded expansion anchors were used 0 -n n . Ho,es were properly cleaned prior to installation M M The anchors appeared to be installed in accordance with the manufacturer 0 recommendations and Instructions. 0 C) The conclusions and recommendations in this report are based on what was observable C M 0 atthe time ofthesite visit. If conditions appear significantly different than those - described above, please contact us immediately for further review. M J. Please feel free to call :f you have any ques�ions or concerns or for rnore information on the observations and recommendations above. z 0 In ospe'd, Ate, 8"0 QPZ04' vice, 2504thAve. South 0)z SUb 200 EdmoridsWA911020 Phorw.425.778.8500 Fa)c 425778 6536 05L 57VO 8 ROL.PcxuA) W1 PAIJft P&A- FL4-6 NoTZ- i NDrc-m PLIw000 At R&CID Rf-�_ $Axpsof-i MsTc/,�5 Op- IAST-�77 T-V,AL!6N -sJ/ .Pwoqwlj� ItJTD COW-1 -SM-A34N, I-TT.i.'31 A LTT;08 :Z-NTdZ- 41 '01 JTTV"m 'TT) OPL �tx STUD IpJ L.1�� oF P'Hl> S ON. PL+Vl.. &MG6,9 %* It AtJtMDP- 6' MIA). v�j-o 'WICUL� to/ 11tL71 HIT kL4 lEb COMIC. -ALL Isr Ira ------------ 7 716 "'0- �40LPOw&j "RJitT6 W-AlL, "Y CAS Ch�ckelcLc, Du, (&la Sol. shcet No. 250 4th Ave. South Job No. Suite 200 Pmj Bdmonds,WA98020 CF7181, 10 z 0 m c MO --10 0 c m m 0 X r rn m m MR rn —c* 0 0 Fn c (1) m z 0 ;a z z 0 m CITY OF EDMONL)b MAYOR 121 5TH AVENUE NORTH EDMONDS. WA 98020 (425) 771-0220 - FAX (425) 771-0221 Website: —dedmonds—us DEVELOPMENT SERVICES DEPARTMENT Planning - Building - Engineering April 14, 2006 Z Jeanne Stensland 8807 201" PI SW Edmonds, WA 98020 Re: Building Permit: 2006-0207 Site Address: 8807 201" PI SW m Expiration Date: 03/17/07 m 0 0 Dear Jeanne Stensland, m The purpose of this letter is to inform you that the last remaining inspection on your project is a final inspection(s). The final inspection(s) determines that there are no outstanding life -safety issues and approval allows the City to close your permit file. -n The City considers the final inspection to be one of the most important inspections :41 ra conducted on a project. In order to grant final approval the following must be complete: C m M smoke detectors, house numbers, guardrails, handrails, self -close doors between garage a V; 0 and residence, egress from sleeping rooms, safety glazing, weather-stripping, any . r- Engineering department requirements etc. Ofcourse not all ofthese things may C.: specifically apply to your project but it does give you an idea about the kinds of things that must be complete as well as some items that do not need to be installed such as: paint, carpet, moldings, wallpaper, etc. Please be advised permits expire one year from X the date of issuance. If you will need more time to complete the work, pennaits can be renewed prior to expiration for one half fees. Ifthe pennit expires without a final approval granted by the Building Inspector, full fees are required in order to renew the permit. This can be very costly to you and we strongly encourage you to check your FO permit expiration date and call for the required final inspection(s). Note: If more than Z one department is required to final your project, this is noted on your Job Card. 0 m Please feel free to contact me at 425-771-0220 if you have any questions. �SinccrclZ J ul.ur P.jSp ci.li. Incorporated August 11, 1890 Sister City - Hekinan, Japan Project: Field Representatives, Stenstand Residence Remodel Chris Bernards P.E. i464 Job No.: 05181.10 Report No. 2 Date: April 10, 2006 Location: Purpose of Site Visit: 8807 201 "Place S.W. Holdown Epoxy Anchor Solt Installation Edmonds, WA 98026 Client: General Contractor; Chennak Construction Chermak Construction Z 0 M 95 '1AAR �Tl m On April 10", CG Engineering performed a site observation of the construction forthe M 0 0 Stensland Residence In Edmonds, WA. The primary goal of the site visit was to observe C the holdown epoxy bolt installation for general conformance with the approved C m construction drawings. The following items summarize our findings: . Simpson Set-Pac Epoxy used (acceptable alternate to Hilt! HIT HY 160) C 11, Z C:J . Hole diameter was 3/7 . Hole depth was r :� O"a S diameter threaded expansion anchors were used -n Holes were properly cleaned prior to installation rn M The anchors appeared to be installed in accordance with the manufacturer 055 0 r- recommendations and instructions. 001 The conclusions and recommendations in this report are based an what was observable M 0 at the time of the site visit. If conditions appear significantly different then those described above, please contact us immediately for further review, Please feel free to call if you have any questions or concerns or for more information on the observations and recommendations above. Z Z 0 m RECEIVED JUN 2 9 2006 OEVELO�MENT SERVICEs CTR, 2604thAve. South Stda 200 Ednmd%WA9BO2D Plione:425.178,8M Fax 425.778,5536 3 ENGINEIERING FIELD -OBSERVATION REPORT Project: Field Representatives: Stensland Residence Remodel Chris Bemards P.E. 05181.10 -JobNo.: Report N .11 Date: April e, 2006 Location: Purpose of Site Visit: 8807 201" Place SW Observe the general construction progress Edmonds, WA 98026 Client: General Contractor -1 Chermak Construction Chermak Construction -NARRATIVE On April 6"', CG Engineering performed a site observation of the Construction for the Stensland Residence in Edmonds, WA. The primary goal of the site visit was to observe the construction progress as well as check for general conformance with the approved construction drawings. The following issues were discussed with the contractor. I . At the east end of the 63/." glularn beam, there is not adequate length to install the 4'strap as shown on 21S2.1. The contractor shall install a CS16 strap from the notched portion of the glularn to the rough opening approximately Taway. The contractor shall also add a 4' CSI 6 strap centered at the beam above this opening. In both cases, the strap shall be nailed to added blocking between studs. 2. The east end of the 6Y."glulam beam did not have a hotdown installed horizontally to the perpendicular wall as shown in 9/S2A. The contractor shall Install this strap RECEIVED to the 2xi 2 adjacent to the shear wall and nail the 2xI2 to blocking between each stud with 16d nails at 4" D.C. Install (I) -Simpson A35 each side of each wall stud to attach the wall studs to the 2xl 2. These should be staggered on the stud top and JUN 2 9 2006 bottom of the 2xI 2. DEVELOPMENT SERVICES CTR, CITY OF EDMONDS 3. The cripple wall above the concrete wall does not allow for the installation of a PHD5 per VS21. The contractor may install alternate holdown, straps as shown In 250 4th Ave. South &&2110 EdmorlidSMA91302111 Phone:425.77&M Fax: 425,778M the attached sketch, SS-3. 4, The east end of the existing floor beam bears an the concrete wall further away then originally thought. The contractor will attach a P.T. 6x6 post to the concrete wall to help support this beam. The post shall attach to the wall with (4�-eqluslly spared 5/ir diameter anchor bolts embed 4" into the wall with Hilb HIT HY 150 epoxy or equal. The conclusions and recommendations in this report are based on what was observable at the time of the sitevisit. If conditions appear significantly different then those described above, please contact us immediately for further review. This observation is not a sufficient substitution for the inspection requirements shown on S1.0. Please feel free to call if you have any questions or concerns or for more information on the observations and recommendations above. Z 9 0 0 0 C M 3i Z co 0 -n m Im a 5 0 0 C Im 0 X Z 9 0 Im Permit Inspection Details Permit: BLD20060207 P E R M I T h r,S eat ng' 0411tf�005 W EXTERIOR SHEATHING APPROVED y Total Tim.: 20 K; ri; c 04111/2006 MS 20 FRAMING APPROVED y Total Time: 20 111' t 6 1 1144"-s4a ns6la I iniciu k : �:111�11' " �c fife? z 0411212006 MS 15 INS ULATIONAPPROVED y 0 Total Time: Is Floo, [On 1146 a. rd sulat' 'Ik' Au �I�: Com elte?.T, M 04/1212006' �MS M�'; INSULATION APPROVE'D' y — Total Time: 20 -4 -n ee, ck M SAE 04/13/2006 JR 20 ETROCK APPROVED y M C Total Time: 20 t 0 APPROVED y 3: 06/2612006 fvl� 15 FINAL M M z Total Time: 15 jo -q It Total Inspections: 6 Total Time: 110 E: :J 0 -n M M 0 0 C/) Q C) z t, z 0 M 7/8/2009 8:47:44 AM Page I of I 7� RECORD OF INSPECTIONS INSPECTOR DATE APPROVED SETBACKS ..................... FOUNDATION: Footing ...................... Wall ............... Pier/Porch ................. z Retaining Wall Stab Insulation .......... 0 PLUMBING: Underground ............. Rough -in M C ............... M -4 0 Commercial Final 0 0 HEATING: C M M z Gas Test .................... C) -4 C Gas Piping ................. > r- -4 Equipment 0 "TI Commercial Final 3: EXTERIOR SHEATHING M M NAILING .......................... 4 15 J 0 0 FRAMING ........................ co FIRST FLOOR FRAMING M 0 Z INSULATION .......... Floor Insulation Wall Insulation ........... Ceiling Insulation NAILING z SHEETROCK SPECIAL INSPECTION 0 M MISCELLANEOUS .......... FINAL APPROVAL FOR OCCUPANCY ................. 7 P7 M