Loading...
20060629134730.pdfCity of Edmonds PLAN REVIEW COMMENTS BUILDING DIVISION (425) 771-0220 DATE: February 10, 2006 TO: Tony Shapiro FAX: 425-778-3032 FROM: Ann Bullis, Assistant Building Official RE: Plan Check #: 05-423 Project: Remax Office Building Project Address: 21020 76th Ave W Below are combined comments from the City's plan review consultant and myself Structural review of the next resubmittal willbe done in-house. Please provide written responses to each comment as to how it has been addressed, and where changes can be found on the plans. Please submit revised plans/documents (affected sheets onW to Theresa Umbaugh, Permit Coordinator. 1) 1 �-hour rated steel column protection with concrete: Provide calculation per IBC 721.5.1.4 to show that minimum concrete coverage will be provided (roof drains must also be taken into account in the calculations). Dimension the minimum thickness on the details as determined by the calculations. (previous item 12) 2) Therinafiber TopStop information provided is a product of the required 1 -hour head -of -wall listed and tested joint assembly. The UL listed joint assembly is still needed and must be noted on the plans, and where it will be used. The Therinafiber website has a "fire stop catalog" that contains joint assemblies for head of wall applications (starts -on page 20). Selectajoint assembly (that allows the Thennafiber product you are proposing to use), note it on the plans, including the cover compound product (usually a fire caulk) and any other requirements of the joint assembly. IBC 713 (previous item 13) 3) Fire stopping details with listed and tested assemblies must still be provided for through and membrane penetrations at the 1 -hour rated floor -ceiling and wall assemblies (the "fire stop catalog" mentioned in item 2 above also contains fire stop assemblies). This can be listed as a deferred submittal on the coversheet, however the fire stopping details and assemblies must be submitted to and approved by the Building Division prior to installation. IBC 712 (previous item. 20) 4) Emergency lighting fixture location and legend symbol, and method of power backup are still missing from Sheet A6. I. IBC 1006 (previous item 18) 5) Please provide manufacturer's specs for fire rated doors and relites to be used with proposed ceramic glass, or list as deferred submittal on the coversheet of the plans. If deferred, specs must be submitted to the Building Division for approval prior to installation. 6) Prior to permit. issuance, the general contractor must provide a written acknowledgement to the Building Division addressing items I through 4 of IBC 1705.3. 7) Special Inspection Agreements are still needed (the agreement provided was not signed by all -parties). Two agreements are required, one for the geotechnical inspections (by geotech of record), and one for the structural inspections (by WABO certified special inspector or State licensed Professional Engineer). These forms must be signed by the building owner, general contractor and special inspector. Return for Building Official approval prior to permit issuance. See attached forms. 8) As noted in letter dated 1/5/06 from the Geotechnical Engineer, revise foundation note 3 on Sheet S2. 1. Comments from City's Structural Consultant Next review of structural resubmittal will be done in-house. 9) Previous Item A regarding seismic uplift component on the horizontal cantilevers: ASCE 7 9.5.2.6.4.3 requires net uplift of 0.2 DL on cantilever components. 10) Previous Item E regarding detail 16/A9. 1, This detail was not changed by the architect as noted in the structural response. 11) Previous Item H regarding the connection of the steel beams into the web of column at gridline (1, C.2) for the floor and roof condition: See attached detail for typical non -moment connections to column web, and review. I have not seen your particular configuration before. 12) Previous Item N regarding detail 6/S5.4: Is this line of xl2x26's shown on I/S2.2 all running at the elevation shown in this detail? What is the out of plane bracing at the top of the short post? 13) Previous Item S regarding floor dead load: I am not familiar enough with RISA, I will presume that is accounted for. Have you also included partition loading as part of your dead load in your seismic lateral analysis? 14) Previous Item Tregarding orthogonal effects: Coordinate with requirements of ASCE-7 9.5.2.5.2.3 Page 2 of 2 SHOP WELDED TAB AND PLATES FIELD H.S. BOLTED MERM-1 mum Relative Cost 1.00 For simple shear connection to column web the base 1.00 index connection BW-11 has a single verfical plate welded to the column web with horizontal stiffener plates (normally 1/21, thick) welded at its top and bottom. The bolt holes are located outside the toe of the column flanges, which allows for easy erection entry of the beam as well as accessibility for impacting the high strength bolts. SHOP WELDED TAB AND PLATES FIELD WELDED anuBW-2aces Relative Cost 1.09 Substituting field welding for field high strength bolfing Mill increase the relative cost of 13W-2 by 9% over the base connection. Note that there will always be a requirement for erection bolts. The drilling or punching of bolt holes cannot, therefore, be totally eliminated. NOTE: Design procedures and design aids for single plate framing connections are given in Engineering for Sim constmcgon, 1984, published by AISQ Chicago. OCT-24-2005 14:54 CITY OF EDMONDS SPECIAL INSPECTION AND TESTING AGREEMENT The project at W. issued under building peruat number requires special inspection and/or testing per IBC Chapter 17. The complete list of special inspections is attached to this document. BEFORE A PERMIT CAN BE ISSUED: The owner and contractor and special Inspector shall complete this agreement and the attached structural test(s) and inspections schedule including the required acknowledgements. APPROVAL OF SPECIAL INSPECTORS: Each special inspector shall be approved by the Building Official prior to perforating any duties or inspections. Each special inspector shall submit Statement of Qualifications to the Building Official for review. Special inspectors shall display identification when performing special inspections on site. Special inspection and testing shall meet the iniaimum requirements of IBC Chapter 17 and the following: R E 141131 U B A. Duties and Res2onsibilities of the Special Inspecto JAN 19 2006 BUILDING DEPARTMENT 1. Observe Work CITY OF EDMONDS The special Inspector shall observe the site work for conformance with the approved (stampcd) plans and specifications and applicable workmanship provisions of the IBC. Architect or Engineer reviewed shop drawings may be used only as an aid to inspection. Special Inspections are to be performed on a continuous basis—meaniag that the special inspector is on site at all times obsefving the work requiring special inspection. Periodic inspections, if any, must have prior approval by the City based on a separate written plan reviewed and approved by the Building Official and the engineer or architect of record. 2. Report Non -conforming Items The special inspector shall bring non -conforming items to the immediate attention Of the contractor and note all such items in the daffy field repor� Any item not resolved in a timely manner shall be immediate cause of the special inspector to notify the Building Official of the plan deviation, error, change or omission. It shall also be the duty of the special inspector to promptly notify the engineer or architect. 3. Complete Daily Reports Each special inspector shall complete and sign both the speciallmspection record and the daily report form for each day's inspection. These records shall remain at the jobsite with the contractor for review by the City Building Inspector. 4. Furnish Weekly Reports The special inspector or inspection agency shaJI furnish the City with weekly reports of tests and inspections. The project engineer or architect, and others as designated shall also be copied on reports. Weekly reports must include the following: • Description of daily inspections and tests made with applicable locations • List of all non -conforming items • Report on status of non -conforming items (resolved or unresolved) • ftemiztd c1lauges authorized by the Architect, Engineer and City if not included in non- conformance items. 5- Furnish Final Construction Report The special inspector or Inspection agency shall submit a fmal signed report to the City stating that all item requiring special inspection and testing were fulfilled and reported. And, to the best of L:\TEMP\BUILDING'S�ialimpe,ctionAgrcc=ntMC.doe 71()4 OCT-24-2005 14:54 P. 07/31 histher knowledge the proj.,ct is in conformance�with the approved pa.Ans and specifications, approved change orders and the applicable workmanship provisions of the IBC. Items not in conformance or unresolved items or any discrepancies in inspection coverage, (ie., missed inspections, periodic inspection when continuous inspections were required, etc.) shall be specifically itemized in this report- R. Contractor Responsibilities 1. Notify the Special Inspector It is the duty of the contractor to notify the special inspector when work is ready for special inspection- Note, the items listed on the attached schedule and as noted on the approved plans and specifications are required to have special inspections. Adequate notice shall be provided by the contractor so that the special inspector has time to become familiar with the project. 2. Provide Access to Approved Plans The contractor is responsible for providing the special inspector access to approved plans at the jobsite. Retain Special Inspection Records The contractor is responsible to retain at the jobsite all special inspection records submitted by the special inspector. These records are to be provided to the City building inspector upon requesL C. City of Edmonds BmUdWE Department Responsibilities 1. Approve special inspectors or inspection agencies The building department shall approve all special inspectors and special inspection requirements. 2. Monitor special inspection and approve weekly reports Work requiring special inspection and the performance of special inspectors shall be monitored by the City Building Inspector. H1911ler approval must be obtained prior to placement of concrete or other similar activities in addition to that of the special inspector, 3. Issue Certificate of Occupancy The Building Official may issue 2 Certificate of Occupancy after all weekly special inspection reports including the final report have been submitted and accepted. D. Owner -Res S Ronsibilifie The project owner or the engineer or arcWtcct of record acting as the owner's agent shall fund special inspection services, E, E gineer or Architect of Record Respo rM asibilltles The engineer or architect of record shall include special inspection requirements on the plans and specifications. ACKNOWLEDGMENTS I have read and agree to comply with the terms and conditions of this agreement. Owner Date Special Inspector Date General Contractor Date City Building Official Date L:vrE&W\BUILDING�SpeciattaspectionAgTee=ntlBC.doc 7104 OCT-24-2005 14:55 brkA-MdL. L"MIL 11UN ANWfEb-FING F�"EDULE P. 08/31 REMORCED CONCREM GUNIM Gitour AND mompu- Tem Mill PRECASTWRESTRESM CONCREM ram p-d-'r— &.-v— =fin M&SONRY-. — SPcdd bdPcc4m Smws Und — Pichmimay Ac-cpt-m T-ft (masm, umw wiff his., — Suwcqvm Tau 4mmu, G~. Fidd Wall hi%=) — Fbccmcw b1spMian of uniu ADDITIONAL INSMUCTIONS OR MF_R TESn AND INSPECTION& -- Bu4j)MMM"m . -Le mttabit STRUCTURAL STMAMDING! &=* and Ten (liu sPcdftc M=bm behm) Sbw mamild ldmdrwmdm Wddk4 WSPM— 0 SbW )KF.W tftx,-m 4"ccmm Ljshw Or*m ifio-m� 301ft lavmfm 0 ShV �"25 )dN OX OF OA4% McW Deck Wc1&aSlnqmctkm Rew'04c� swa WCWUV I-pami" McW SaW WeldmT lwpwt" COX= law" Weldmg kmj� FIREPROOFING: — Pbccmcm Jwvmgi*q — Dmay Tem — 17wknm Tests — hupm Burling INSULATING CONCREIZ! saw* =4 Teu piwemm jmpcctiQn unit wcqNs FILL MATMAL: Accqx&wc Tew in Impewm Fidd Dmaity STRUCTURAL WOOD; Sh= V411 Naifinf wpvai00 lwmian ofGiu-jun Fab, 19SMcgicm Of Trum Joist hb. &Vwk W Ten COW000=0 CITY OF EDMONDS SPECIAL INSPECTION AND TESTING AGREEMENT The project at issued under building permit number requires special inspection and/or testing per IBC Chapter 17. The complete list of special inspections is attached to this document. BEFORE A PERMIT CAN BE ISSUED: The owner and contractor and special inspector shall complete this agreement and the attached structural test(s) and inspections schedule including the required acknowledgements. APPROVAL OF SPECIAL INSPECTORS- Each special inspector shall be approved by the Building Official prior to performing any duties or inspections. Each special inspector shall submit Statement of Qualifications to the Building Official for review. Special inspectors shall display identification when performing special inspections on site. Special inspection and testing shall meet the minimum requirements of IBC Chapter 17 and the following: A. Duties and Responsibilities of the Special Inspector 1. Observe Work The special inspector shall observe the site work for conformance with the approved (stamped) plans and specifications and applicable workmanship provisions of the IBC. Architect or Engineer reviewed shop drawings may be used only as an aid to inspection. Special Inspections are to be performed on a continuous basis —meaning that the special inspector is on site at all times observing the work requiring special inspection. Periodic inspections, if any, must have prior approval by the City based on a separate written plan reviewed and approved by the Building Official and the engineer or architect of record. 2. Report Non -conforming Items The special inspector shall bring non -conforming items to the immediate attention of the contractor and note all such items in the daily field report. Any item not resolved in a timely manner shall be immediate cause of the special inspector to notify the Building Official of the plan deviation, error, change or omission. It shall also be the duty of the special inspector to promptly notify the engineer or architect. 3. Complete Daily Reports Each special inspector shall complete and sign both the special'inspection record and the daily report form for each day's inspection. These records shall remain at the jobsite with the contractor for review by the City Building Inspector. 4. Furnish Weekly Reports The special inspector or inspection agency shall furnish the City with weekly reports of tests and inspections. The project engineer or architect, and others as designated shall also be copied on, reports. Weekly reports must include the following: Description of daily inspections and tests made with applicable locations List of all non -conforming items Report on status of non -conforming items (resolved or unresolved) Itemized changes authorized by the Architect, Engineer and City if not included in non- conformance items. 5. Furnish Final Construction Report The special inspector or inspection agency shall submit a final signed report to the City stating that all items requiring special inspection and testing were fulfilled and reported. And, to the best of L:\TENP\BUILDING\SpeciallnspectionAgreementIBC.doe 7/04 his/her knowledge the project is in conformance with the approved plans and specifications, approved change orders and the applicable workmanship provisions of the IBC. Items not in conformance or unresolved items or any discrepancies in inspection coverage, (i.e., missed inspections, periodic inspection when continuous inspections were required, etc.) shall be specifically itemized in this report. B. Contractor Responsibilities 1. Notify the Special Inspector It is the duty of the contractor to notify the special inspector when work is ready for special inspection. Note, the items listed on the attached schedule and as noted on the approved plans and specifications are required to have special inspections. Adequate notice shall be provided by the contractor so that the special inspector has time to become familiar with the project. 2. Provide Access to Approved Plans The contractor is responsible for providing the special inspector access to approved plans at the jobsite. 3. Retain Special Inspection Records The contractor is responsible to retain at the jobsite all special inspection records submitted by the special inspector. These records are to be provided to the City building inspector upon request. . C. City of Edmonds Building Department Responsibilities 1. Approve special inspectors or inspection agencies The building department shall approve all special inspectors and special inspection requirements. 2. Monitor special inspection and approve weekly reports Work requiring special inspection and the performance of special inspectors shall be monitored by the City Building Inspector. 11is/Her approval must be obtained prior to placement of concrete or other similar activities in addition to that of the special inspector. 3. Issue Certificate of.Occupancy The Building Official may issue a Certificate of Occupancy after all weekly special inspection reports including the final report have been submitted and accepted. D. Owner Responsibilities The project owner or the engineer or architect of record acting as the owner's agent shall fund special inspection services. E. EnLyineer or Architect of Record Responsibilities The engineer or architect of record shall include special inspection requirements on the plans and specifications. ACKNOWLEDGEMENTS I have read and agree to comply with the terms and conditions of this agreement. Owner Special Inspector General Contractor Date Date Date City Building Official Date L:\TENW\BLTILDING\SpeciallnspectionAgreementEBC.doc 7/04 ',PECIAL INSPECTION AND TESTING SC 'DULE __)MAX _-CMKF=- —f>" LD9 MC" PROJECT ADDRESS TEsnNG/MPECnON AGENCY SPECIAL INSPECTOR REINFORCED CONCRETE, GUNITE, GROUT AND MORTAR: Concrete Gonite Grow Mortar Aggregate Tests Reinforcing Tests Mix Desiyns Reinforcing Placement Bitch Plant inspection Inspect Placing -Cast Samples Pick-up Samples Compression Tests PRECASTIPRESTRESSED CONCRETE: TUC3 1-051- j AggrrgatcTests — Reinforcing Tests Tendon Tests Mix Desisms Reinforcing Placement Insert Placement Concrete Baiching �.Concrcic Placement Inst allation Insepction Cast SaMDICS Tests MASONRY Special ImPection Stresses Used Nrliminary Acceptance Tests (Masonry Units. Wall Prisms) Subsequent Tests (Mortar. Grout. Field Wall Prisms) Placement Inspection of Units ADDITIONAL INSTRUCTIONS OR OTHER TESTS AND INSPECTIONS: STRUCTURAL STEELfWELDING: Sample and Test (list specific mernbffs below) Shop Material Identification Welding inspection 0 Shop 0 Field UlURS06c InsPectiOn 11 Shop 11 FmId High-strengib Bolting Inspection D Shop 0 Field D A325 0 N OX OF 0 A490 — Metal Dock Welding Inspection — Reinforcing Steel Welding htspection — Metal Stud Welding Inspection — Concrete Insert Welding Inspection FIREPROOFING: — Placement Inspection — Density Tests — nickness Tests — Inspect Batching INSULATING CONCRETE: — Sample and Test — Placement Inspection — Unit Weiglits FILL MATERIAL: — Acceptance Tests — Placement Inspection — Field Density STRUCTURAL WOOD: — Shear Wall Nailing Inspection — Inspection of Glu-tam hb. — Inspection ofTruss Joist Fab. — Sample and Test Components Form completed by- Title: Tclephonc No-: -7? 1 -0 z -L Date: M