PLAN REVIEW COMMENTS
BUILDING DIVISION
�St. is9° (425) 771-0220
DATE: August 18, 2006
TO: Valerie Sargent
FAX: 206-749-5005
FROM: Ann Bullis, Assistant Building Official
RE: Plan Check #2006-0705 & 2006-0706
Project: Foundation Only for Point Edwards Buildings 6 & 7
Project Address: 31 & 41 Pine Street
During review of the subject permit application, it was found that the following information or
corrections to plans must be made. Please respond in writing to each item and include the
location(s) of the changes to expedite the re -review. Please resubmit 3 sets of plans/documents
(affected sheets only) and written comments to Marie Harrison, Senior Permit Coordinator.
1. The frontage increase calculations for Buildings 6 & 7 (mainly 7) do not meet the
requirements of IBC 506.2 for adjoining or having access to a public way or open space with
approved fire lane. The Fire Marshal has noted this in his comments with regards to fire
fighter access. It appears that you may be able to meet allowable area with sprinkler
increases alone (IBC 506.3). Revise the allowable area calculations on the coversheet
accordingly. If you have questions concerning approved fire lanes and fire fighter access,
please contact the Fire Marshal directly.
2. Show locations of all grill openings in the concrete walls on the floor and structural plans.
Sheet 5/A3.2 shows a grill in the approximate location of the 2 hour fire wall Where the fire
wall intersects the exterior wall of the garage, a 1 -hour rated wall must be provided for a
distance of 4 feet on either side of the fire wall. IBC 705.5.1