20060821091939.pdfTO: Ken Mattson PO Box 234 Edmonds, WA 98020 FROM: Jenny Readwin, Plans Exam er RE: Plan Check # 06-165 Project: Falcone 2nd Story Addition Project Address: 824 Main St. During re -review of the above noted application, it was found that the following information, corrections, or clarifications are needed. Please redline plans or submit two (2) sets of revised plans/documents (affected sheets only) with a written response to each of the above items to a Permit Coordinator. 1) ok 2) ok 3) ok 4) ok 5) ok 6) ok 7) ok 8) ok 9) ok 10) ok 11) ok 12) ok 13) ok 14) ok 15) Provide calculations for 3 % x 12 beam on main floor structural plan between the stairs and the bedroom, specify the beam at he stairs and provide calculation with point load from the 3 % "x 12, provide calculations for all double floor foists with point loads and provide calculation for 4x8 header on the lower floor structural plan with point load from beam above. Still need. No posts are shown, foundation, bearing walls, etc. It is unclear how all loads from proposed second story addition are being carried to bearing. Provide complete framing plans showing how all loads are being carried to bearing (beams, post size and location, bearing walls, joists, existing foundation, etc.). A complete gravity review can not be done until this is provided. See attached handout for sample plans with minimum submittal requirements. 16) ok 17) ok 18) ok 19) Still need prior to permit issuance. Will need prior to permit issuance. Special inspections are required for the Kwik bolts and expansion anchors. Complete the enclosed special inspection agreement signed by the owner, the general contractor and the special inspector and submit to the City for approval prior to issuance. 20) ok City of Edmonds PLAN REVIEW COMMENTS BUILDING DIVISION (425) 771-0220 DATE: August 21, 2006 TO: Ken Mattson PO Box 234 Edmonds, WA 98020 FROM: Jenny Readwin, Plans Exam er RE: Plan Check # 06-165 Project: Falcone 2nd Story Addition Project Address: 824 Main St. During re -review of the above noted application, it was found that the following information, corrections, or clarifications are needed. Please redline plans or submit two (2) sets of revised plans/documents (affected sheets only) with a written response to each of the above items to a Permit Coordinator. 1) ok 2) ok 3) ok 4) ok 5) ok 6) ok 7) ok 8) ok 9) ok 10) ok 11) ok 12) ok 13) ok 14) ok 15) Provide calculations for 3 % x 12 beam on main floor structural plan between the stairs and the bedroom, specify the beam at he stairs and provide calculation with point load from the 3 % "x 12, provide calculations for all double floor foists with point loads and provide calculation for 4x8 header on the lower floor structural plan with point load from beam above. Still need. No posts are shown, foundation, bearing walls, etc. It is unclear how all loads from proposed second story addition are being carried to bearing. Provide complete framing plans showing how all loads are being carried to bearing (beams, post size and location, bearing walls, joists, existing foundation, etc.). A complete gravity review can not be done until this is provided. See attached handout for sample plans with minimum submittal requirements. 16) ok 17) ok 18) ok 19) Still need prior to permit issuance. Will need prior to permit issuance. Special inspections are required for the Kwik bolts and expansion anchors. Complete the enclosed special inspection agreement signed by the owner, the general contractor and the special inspector and submit to the City for approval prior to issuance. 20) ok