Loading...
20061168 edmonds-woodway high school on 212th.doc City of Edmonds TH 121 5 AVENUE NORTH • EDMONDS, WA 98020 • (425) 771-0220 FAX(425) 771-0221 Website: www.ci.edmonds.wa.us DEVELOPMENT SERVICES DEPARTMENT Planning • Building • Engineering Plan Review Comments Plan Check : Date: # 20061168 13 Nov 06 th Project Name/Address: Edmonds/Woodway High School; 7600 212 St SW Contact Person/Address/Fax: fax : : Reviewer: Division:Engineering Lyle Chrisman, Engineering Program Manager The subject application has been reviewed but cannot be completed until the following items have been addressed/corrected. Please resubmit 3 sets of revised drawings to a Development Services Permit Coordinator. Sheet 2 1. Need wet signature on surveyor’s stamp. Sheet C1.0 2. Provide detail of overflow restrictor at the sediment trap. 3. Provide cross section of the sediment pond. 4. FYI: there is an underground electrical conduit along the fence line from the pedestrian xing button and the advanced warning light at the far west end of the site. 5. Temporary construction entrance needs to be increased to 100’. 6. General note 10: If water will be obtained from a City hydrant, contractor will have to obtain a backflow device with meter from the City of Edmonds Public Works Water Department. 7. Construction Sequence a. Note 1: change to: Call the City of Edmonds Engineering inspection line (425-771-0220 ext 1324) to set up a preconstruction meeting and 24 hours in advance for inspections. b. Add “Review ESC notes” after note 2. c. Add Dust control measures after note 6. Sheet C1.1 8. All 17 points of ESC per Chapter 18.30.050 of the ECDC must be added verbatim. __________________(Attach fax transmittal) DATE FAXED PAGE ____ OF ___ C:\\Users\\cockrum\\AppData\\Local\\Temp\\20061168 edmonds-woodway high school on 212th.doc_154116\\20061168 edmonds-woodway high school on 212th.doc 9. Erosion note 15: Dates and duration of exposed surface areas are identified in 18.30.050 so this note can be elimated to avoid duplication. 10. Change detail 3 to the current City standard detail (can be found on the Edmonds web site). Sheet C2.0 11. Provide a detail of the collection storm drain. Storm Drainage report 12. Comments to follow within a week. General 13. Provide a proposed truck route plan. 14. Provide cost estimate for proposed work so an engineering inspection fee can be determined. __________________(Attach fax transmittal) DATE FAXED PAGE ____ OF ___ C:\\Users\\cockrum\\AppData\\Local\\Temp\\20061168 edmonds-woodway high school on 212th.doc_154116\\20061168 edmonds-woodway high school on 212th.doc