`~PLAN REVIEW COMMENTS
,F:2 of
BUILDING DIVISION
Fst_ 1 g90 (425) 771-0220
DATE: December 13, 2006
TO: Michel Construction Inc.
michelbz@nwlink.com
FROM: Jenny Readwin, Plans Exarraer
RE: Plan Check 4 2006-0794 through 006-0801
Project: 8 SFR Development
Project Address: 82"d and 212th
During re -review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit two (2) sets of revised
plans/documents (affected sheets only) with a written response to each of the items below to a
Permit Coordinator.
1) This is required before I can sign off on these permits. Please provide. Soils reports must be
site specific. Soil test pits and logs are required for each site. Please provide. They can not be
from adjacent site. Soils report from Dennis M. Bruce, PE dated June 21, 2006 specifies that 4
test pits were dug. Provide site plan from Dennis M. Bruce, PE showing test pit locations as
well as soil logs for each test pit as required by IRC chapter 4.
2) ok
3) ok
4) ok
5) ok