Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
20070123134648.pdf
or EDS City of Edmonds O PLAN REVIEW COMMENTS BUILDING DIVISION �Sr S g90 (425) 771-0220 DATE: January 23, 2007 TO: Thomas Estep tomestep@aol.com .d FROM: Jenny Readwin, Plans Ex in RE: Plan Check # 2007-0037 Project: Remodel Project Address: 8809 Olympic View Dr. During review of the above noted application, it was found that the following information, corrections, or clarifications are needed. Please redline plans or submit two (2) sets of revised plans/documents (affected sheets only) with a written response to each of the items below to a Permit Coordinator. 1) Is the new covered porch part of this permit? If not cross off plans and if so, provide complete framing plans and foundation plan (posts, beams, footings, etc.) and add to site plan. 2) Please provide new roof framing/truss plan that does not include the master bedroom addition that is crossed off this application and the covered porch if it also is not included in this permit. 3) Cross reference all details from sheet S-2 to their location on the plans. Cross out any details that do not apply to this house. If new footings or foundation is pour provide foundation plan. 4) Proposed shearwalls do not meet conventional wall bracing. Revise plans to meet conventional wall bracing requirements of the International Residential Code or provide calculations designed to IBC 1614.3 stamped and signed by a Washington State Licensed Professional Engineer. 5) Provide beam calculations for all proposed beams/headers (i.e. 3 %2" x 9 %i" PSL). 6) Special inspections are required for the following. Complete the enclosed special inspection agreement signed by the owner, the general contractor and the special inspector and submit to the City for approval prior to issuance. Special inspector must either be a Washington State Licensed Professional Engineer or a WABO certified inspector. • Epoxy bolts/holdowns • Expansion anchors CITY OF EDMONDS SPECIAL INSPECTION AND TESTING AGREEMENT The project at 17000 1W hADI,c, l%!Tetj Df—, issued under building permit number - (?U3 requires special inspection and/or testing per IBC Chapter 17. The complete list of special inspections is attached to this document. BEFORE A PERMIT CAN BE ISSUED: The owner and contractor and special inspector shall complete this agreement and the attached structural test(s) and inspections schedule including the required acknowledgements. APPROVAL OF SPECIAL INSPECTORS: Each special inspector shall be approved by the Building Official prior to performing any duties or inspections. Each special inspector shall submit Statement of Qualifications to the Building Official for review. Special inspectors shall display identification when performing special inspections on site. Special inspection and testing shall meet the minimum requirements of IBC Chapter 17 and the following: A. Duties and Responsibilities of the Special Inspector 1. Observe Work The special inspector shall observe the site work for conformance with the approved (stamped) plans and specifications and applicable workmanship provisions of the IBC. Architect or Engineer reviewed shop drawings may be used only as an aid to inspection. Special Inspections are to be performed on a continuous basis—meaning that the special inspector is on site at all times observing the work requiring special inspection. Periodic inspections, if any, must have prior approval by the City based on a separate written plan reviewed and approved by the Building Official and the engineer or architect of record. 2. Report Non -conforming Items The special inspector shall bring non -conforming items to the immediate attention of the contractor and note all such items in the daily field report. Any item not resolved. in a timely manner shall be immediate cause of the special inspector to notify the Building Official of the plan deviation, error, change or omission. It shall also be the duty of the special inspector to promptly notify the engineer or architect. 3. Complete Daily Reports Each special inspector shall complete and sign both the special inspection record and the daily report form for each day's inspection. These records shall remain at the jobsite with the contractor for review by the City Building Inspector. 4. Furnish Weekly Reports The special inspector or inspection agency shall furnish the City with weekly reports of tests and inspections. The project engineer or architect, and others as designated shall also be copied on reports. Weekly reports must include the following: • Description of daily inspections and tests made with applicable locations • List of all non -conforming items • Report on status of non -conforming items (resolved or unresolved) • Itemized changes authorized by the Architect, Engineer and City if not included in non- conformance items. 5. Furnish Final Construction Report The special inspector or inspection agency shall submit a final signed report to the City stating that all items requiring special inspection and testing were fulfilled. and reported. And, to the best of L:(TEMPIBUILDIN.GlSpeciallnspectionAgreementlBC.doe 7/04 his/her knowledge the project is in conformance with the approved plans and specifications, approved change orders and the applicable workmanship provisions of the IBC. Items not in conformance or unresolved items or any discrepancies in inspection coverage, (i.e., missed inspections, periodic inspection when continuous inspections were required, etc.) shall be specifically itemized in this report. B. Contractor _Responsibilities 1. Notify the Special Inspector It is the duty of the contractor to notify the special inspector when work is ready for special inspection. Note, the items listed on the attached schedule and as noted on the approved plans and specifications are required to have special inspections. Adequate notice shall be provided by the contractor so that the special inspector has time to become familiar with the project. 2. Provide Access to Approved Plans The contractor is responsible for providing the special inspector access to approved plans at the j obsite. 3. Retain Special Inspection Records The contractor is responsible to retain at the jobsite all special inspection records submitted by the special inspector. These records are to be provided to the City building inspector upon request. C. City of Edmonds Building Department Responsibilities I. Approve special inspectors or inspection agencies The building department shall approve all special inspectors and special inspection requirements. 2. Monitor special inspection and approve weekly reports Work requiring special inspection and the performance of special inspectors shall be monitored by the City Building Inspector. His/Her approval must be obtained prior to placement of concrete or other similar activities in addition to that of the special inspector. 3. Issue Certificate of Occupancy The Building Official may issue a Certificate of Occupancy after all weekly special inspection reports including the final report have been submitted and accepted. D. Owner Responsibilities The project owner or the engineer or architect of record acting as the owner's agent shall fund special inspection services. E. Engineer or Architect of Record Responsibilities The engineer or architect of record shall include special inspection requirements on the plans and specifications. ACKNOWLEDGEMENTS I have read and agree to comply with the terms and conditions of this agreement. Owner Date Special Inspector Date General Contractor Date City Building Official Date L:ITEMPIBUII.DING1SpeciallnspectionAgreermentlBC.doc 7104 SPECIAL INSPECTION AND TESTING SCHEDULE MOM -T NAME tet°' AtMNCY. or Se£CtAL DMPWXW REINFORCED CONCRETE, GUNITE, GROUT AND MORTAR: STRUCTURAL STEEL WELDING' Goncreftr Gnnitc Groot Mortar 5ampie d T Iisr A&gregate Tests Reinforcing Tests Mix Designs Reinforcing Placement Batch, Plant Inspection Inspect Placing Cast samples Pick-up Samples Com "on Tests Metal Stud Welding Inspection PRECASTIPRESTRESSED CONCRETE: — Ccmacte Insert welding Inspection atr est ( speetf tc --s below) — Shop Material Identification Welding Inspection 13 Shop © Field — Ult conic Ltspxtion 0 shop 0 Field — Iligb-susngtb Bolting Inspection © Shop .D Field DA325 ❑N OX QF D A490 — Metal Deck Welding Inspection Reinforcing Steel Welding Inspection rwe.-anus rre-fens LuRnitng ' Aggregate Tests Reinforcing Tests Tendon Tests Mix Desittns Reinforcing Placcmcnt Insert Placement Concrete Batching Concrete Placement Installation Imepction Cast samoles ion Tuts MASONRY: — Special Insper:tion Stresses Used — Prc&minmy Acceptance Tests (Masoury Units. Wall prisms), — Subsequent Tests (Mortar. Grout, Field Wall Prisms) Placement Inspection of Units ADDITIONAL INSTRUCTIONS OR OTHER TESTS AND INSPECTIONS: FIREPROOFING: Placement Inspection — Density Tests — Thickness Tests — Inspect Batching INSULATING CONCRETE: — Sample and Test Placement Inspection _ Unit weights .FILL MATERIAL: — Acceptance Tests — Placement Inspection — Field Density STRUCTURAL WOOD: — Shear Wall Nailing Inspection — Inspection of Glu -lam Fab. — Inspection of Truss Joist Fab- - Sample and Test Components Form completed by: Telephone No.: Title: Dare: S