Loading...
20070410153214.pdfCity of Edmonds ri PLAN REVIEW_ COMMENTS BUILDING DIVISION Fsr. a9° (425) 771-0220 DATE: April 10, 2007 TO: Dennis Walcker PO BOX 996 Lynnwood, WA 98046 FROM: Jenny Readwin, Plans Ex ine RE: Plan Check ## 2006-1198 Project: Walcker SFR Project Address: 742 Daley St. During re -review of the above noted application, it was found that the following information, corrections, or clarifications are needed. Please redline plans or submit two (2) sets of revised plans/documents (affected sheets only) with a written response to each of the items below to a Permit Coordinator. 1) 4/10/07 Still need no response given. Revise site plan to say proposed residence. Currently all is shown is proposed garage. Please clarify. 2) 4/10/07 Still need on the site plan. No response given. Also, rockery is now shown on the East side of the driveway. Provide top and bottom wall elevations as well as stamped and signed detail and calculation for proposed wall. Please note: rockeries are not permitted to support a surcharge. Provide top and bottom wall elevations at 5' intervals for proposed retaining walls on both sides of the driveway. 3) 4/10/07 Still need no response given Specify detail to be used for patio retaining wall including a connection detail for the guardrail. Also, specify top and bottom wall elevations on the site plan. 4) 4/10/07 Still need no response given Note on site plan if rockery shown on property to the South is existing or proposed. If proposed separate permit will be required signed by that property owner with calculations and details. 5) ok 6) 4/10/07 Still need no response given Grading plan shows existing retaining wall on the West side of the house. Clarify if it will be removed in its entirety including portion on adjacent property. Also show how this area will be re -graded or if a new retaining wall is proposed. Modify side plan accordingly. 7) ok 8) 4/10/07 Still need no response given On the site plan note that handrails are required for 4 or more stair risers and guardrails are required to protect falls greater than 30". 9) 4/10/07 Still need no response given On the site plan specify what is being used as the datum point. Based on the topography please choose a point that will allow the Building inspector to perform the height verification inspection. 10) 4/10/07 Still need on Sheet A3 in the laundry room. Show size and location of all source specific exhaust fans (50 cfin minimum for bath/laundry and 100 cfin for kitchen stove). 11) 4/10/07 Still need no response given Please complete the enclosed Energy and Ventilation Worksheet. Note on the plans which fan will act as the whole house fan and specify cfrn rating as determined by enclosed form. 12) 4/10107 Still need no response given Provide crawlspace ventilation calculations and show size and location of crawlspace vents on foundation plan. 13) 4/10107 Shoring must stay entirely on this parcel Please revise showring plan to clearly show shoring wall does not cross over the property line. Provide shoring detail and a separate site plan showing locations of the temporary shoring walls as noted in the Geotechnical Report. Structural calculations and peer review will be required. 14) ok 15) 4/10107 Still need. Bold italicized special inspections were added during the last resubmittal based on shoringplans. Special inspections are required for the following. Complete the enclosed special inspection agreement signed by the owner, the general contractor and the special inspector and submit to the City for approval prior to issuance. • Soil cuts • Temporary and Permanent Shoring including site monitoring • Foundation Subgrade Verification • Retaining wall/Rockery Placement • Placement of Fill and Compaction • Subsurface drainage installation • Temp and Final Erosion Control • General Site Monitoring during earthwork • Field Welding 16) 4110107 See attached additional comments. See attached structural comments from city consultant. Respond to each item in writing. Page 2 of 2 ...... Eagle Eye Consulting Engineers, P.S. PO Box 523 Olalla, WA 98359 hoytjeter@centurytel.net 360 874 0562 Fax 360 874 0591 To: Marie Harrison 121 5th Avenue Edmonds, WA 98020 Re: Walcker Residence Date: April 4, 2007 742 Daley Street Edmonds, WA 98020 Plan Review # 2006-1198 EECE # EDM 06-62 (2) Second Letter Structure Area S.F. Lower Floor 140 Main floor 1017 Second floor 1052 Total 2209 Garage 770 Total 2979 Deck 52 rand total 3031 t gR BULI)IN DEPT - The above referenced project is in the process of plan review for compliance with Edmonds ordinances and applicable codes. The following comments, deficiencies/corrections must be addressed prior to completion of plans review and subsequent issuance of permits. Provide revised plans and calculations along with a written response to each of the items listed below to facilitate a shorter back -check time. SCOPE OF REVIEW The scope of this review is for the Structural requirements of this project and the retaining wall All features were checked only to the extent allowed by the submittals provided. All portions of this project are assumed to meet or will meet other departmental requirements, conditions and concerns before permit approval. Page 2 of 7 EECE#: EDM 06-62 (2) Walcker Residence STRUCTURAL COMMENTS General 2. 3. 3. EOR please provide calculation for the slab to resist 7.5 kip force at the base as noted in the Enercalc program. A narrative response was submitted but not an analysis. Submit an analysis to justify the load path as required per code. The slab is required to resist this force. Just stating the load path is not sufficient. Submit an analysis to justify the forces will be resisted and modify accordingly. 4. 4. Please reference the location of each different wall type to use throughout this structure. Sheet SI and S2 have many different cases for retaining wall to be built. It is not clear where all the locations of these walls are to be used. This should not be decided by the contractor but should be clearly referenced on the drawings. This still has not been modified clearly. Sheet Al has details that do not occur on the sheet. For example; there is not a detail 2 on sheet S-1. There is a detail A2 but not a 2. The drawing should be clear in order to make sure the correct detail is used at the correct location by the contractor and the inspector is able to cross reference it during inspections. 5. EOR, when nail spacing is required to be spaced at 2" O/C the minimum size member shall be a single 3X. The drawings state (2) 2x. The IBC 2006 has. modified this when the spacing is this close and must be a single 3X. Modify drawings to clearly state 3x and not double 2x studs. IBC 2306.3.1 footnote c. Sheet A2 BASEMENT PLAN SHOWING 2ND FLOOR FRAMING: 6. 5. EOR please clearly specify the required connections for the post to the beams. The response states see attached. The drawings still do not reflect the required post to beam connections. This is required to be clearly specified on the drawings. For example, the 3- 1/8X12 or the 5-1/8X16-1/2. The required connections are not clear on the drawings in order to complete the review. Sheet Al one states `post to beam connections "Simpson" or equal size as required'. But Simpson makes many different types of hangers that may be used. There is no way to check the connections if the specific hanger is not specified. More information is required to be added to the drawings to complete the review. Page 3 of 7 EECE#: EDM 06-62 (2) Walcker Residence 7. 6. EOR please specify the required connection of the post that bears on the supporting beam below. I was unable to determine the required connections for the drawings. The response states `see attached'. The note that the post is inside of a wall is not a positive connection as required per code. The base and the top must be positively attached to prevent lateral translations. Provide a detail at these locations to show the required connections of these members. Sheet A4 2ND FLOOR SHOWING 3' FLOOR FRAMING: 8. 8. EOR please clearly specify the required connections for the post to the beams. This also should include the double joist. This still has not been addressed. Please specify the required connections of the all double joist connections to the supporting members. This should include the cantilever beams, the connections to the bearing walls, etc, Currently the complete load path to the foundations is not clear on the submitted drawing. 9. EOR, please clarify the required support for the left hand side area with the cut 2/A8. Clarify these areas. There is a porch area at this location but the detail does not reflect this. Sheet A5 FLOOR PLAN 3"0 LEVEL: 10. 9. Please clarify on the drawing how the shear force from the roof framing is transferred to the interior shear wall. Sheet A7 does not show how these walls are framing to transfer this force. Please add detail and collector elements to transfer the required lateral forces. IBC 1620.2.6 Details are still not clearly referenced to the drawings to show a complete load path More information is required to be added to show how the force from the roof will transfer to the vertical resisting elements, i.e. shear wall. Not only is the blocking required but also the collector element to transfer to this wall. Please add this information to the drawing to complete the load path. Sheet A7 ROOF FRAMING PLAN: 11. 10. EOR please provide analysis for the horizontal diaphragm nailing requirements. It appears the nailing specified in note 2 will not support the required horizontal diaphragm forces for an unblocked diaphragm. IBC 1620.2.5 and IBC 1620.4.3 The response states see note 6 of the shear wall schedule. Note 6 is for the connections of the trusses, rafter, etc. The analysis should be submitted to show how the lateral forces are transferred though the diaphragm. IBC 1620.4.3 Sheet A8 CONSTRUCTION DETAILS: 12. 11. Detail 10: EOR please provide analysis far the deck guardrail including the connections required. The detail does not match the analysis submitted. Modify the Page 4 of 7 EECE#: EDM 06-62 (2) Walcker Residence detail on the drawings to match the required analysis. For example, the 2X fascia must be removed. 13.12. Detail 12: EOR please sped the required stair angle bolted to floor beam to resist the design forces. All that is noted is the following, "STAIR < BOLTED TO FLOOR BEAMSIAfflSOY'. The detail now states Simpson A35 at each side but the there are (3) stringers. The plan does not show these stringers are connected. Please clarify on the drawing how these will be connected in order complete the review. Sheet A9 CONSTRUCTION DETAILS: 14. 13. Detail 5: Please clarify note "RAILING DETAIL SEE SHEET A ". It is not clear the required connection required at this location. Also this connection should resist the minimum code required forces of 200 pounds applied in any direction. R301.5 See comment under sheet A8. 15. 14. Detail 7. Please clarify in the detail what the % diameter ledger bolts are connecting to the main structure. All that is noted is building line. Without this information there is no way to check the connection to support the minimum code design loads. IBC 106.3.3 EOR, Please specify the require gage between the bolts and also the required connections of the rim to the structure to transfer the forces. Sheet S1 STRUCTURAL DETAILS: 16. EOR, submit an analysis for the slab to resist the reaction from the basement retaining walls. An analysis has not been submitted. For detail A2 the force is 7.47 kips per foot of wall. Submit an analysis to justify the slab will resist this force. 17.16. Detail A2: Design analysis used a d for the top stem wall to be 3.69 inches. With a 2" clear and center of reinforcement the d from the compression face of concrete to center of tension steel shall be 3_ 18 and not 3.69. Please modify the analysis or the drawings to resist the design force as required ACI chapter 10: (d= distance from the extreme compression fiber to the centroid of tension reinforcement.) Also note the program output picture clearly states the center of steel to the compression face to be 1-3/4 " but the drawings show 2 " clear. The detail specifies the reinforcement still on the wrong face for the retaining wall. The tension face will be on the earth face but as noted the steel will be placed on the other face with a 1-3/4". The stud wall will not brace the top of the retaining wall. See Enercalc calculation print out for placement of reinforcement steel. Modify the drawings accordingly. This also is the case for detail Al. Please modify both details to show the correct locations of the tension steel. 18. 17. Detail Al and A2: Please specify the required length of the #5 @ 10 " O/C reinforcement at the top of the footing. The length is specified but not the required location of the placement of the steel. Please add this information to the drawings. Page 5 of 7 EECE#: EDM 06-62 (2) Walcker Residence 19.18. EOR please provides analysis for detail A1. The submitted analysis does not appear to have this wall designed. EOR, the new analysis has a reaction of 5.3 kips to be resist by the slab. Submit an analysis to justify the slab can resist this force. 20. 19. Detail 4: EOR, provide an analysis for the A34 to resist the horizontal force from the soil pressure as a restrained wall. The maximum force and A34 can resist with a force applied perpendicular is 345 pounds. Therefore, (2) A34 can only resist 690 pounds if the joists were spaced at 12" OIC. Also, the bolts spaced at 8" OIC do not resist this force. Note per table I IE Z perpendicular to plane is 470 pounds per foot. So the maximum force that can be resisted is 705 pounds, but it is clear in the analysis the required force the top of the wall is required to resist is 1.1 kips. Modify detail accordingly. NDS 11.3 21.20. Detail 4: When the joist run parallel to the wall the blocking at 24" O/C will not resist the design force. Please modify accordingly. NDS table HE. The new drawings do not match the analysis submitted. For example, A34 supports a smaller force than the A35 required by analysis. Nothing appears to be modified as per the analysis except the spacing of the anchor bolts. Also, see Simpson catalog for the appropriate resisting force. Based off the reactions the connections will not be resisted as detailed. Modify drawings to match analysis and verify the connections will resist the forces as required. 22.21. Detail 4: EOR submit analysis to account for the 100 psf force required for the restrained wall. All the analysis submitted has stated the wall is free to rotate at the top. This is not the case for the restrained wall. This still has not been addressed. Also, the new analysis submitted used grade 60 steel but the detail states to use grade 40. Modify the drawings accordingly. 23.22. EOR please submit analysis for straight bar embedment of the dowel to resist the design force. It appears the analysis is counting on this bar to transfer this force. Please clarify on the response. It is not clear how the straight bar embedment was determined in the new analysis. What does the soil bearing pressure have to do with bar developments? The dowels are required to resist shear forces? Also, in seismic zone classified a zone D1 or D2 then 90 degree hook is required in the footings unless analysis is submitted to justify straight bar embedment per ACI.. Please modify accordingly and submit an analysis to transfer the required design loads. 24.23. Detail 4: EOR submit analysis for the 18" wide footing to support the vertical loads with out exceeding the allowable bearing pressure. This must include the weight of concrete and the floor loads above. The maximum force that can be resisted vertically is 2500 PSF * I8" wide footing * 12 " per foot = 3750 pound per foot of wall. Just the weight of wall alone has a vertical force of 150 *I1 feet*8 inch wall/12 =1100 pounds per foot. IBC 1801.2 The analysis submitted states the footing shall be 2'6" wide but the detail still state 18". Also, the analysis submitted Page 6 of 7 EECE#: EDM 06-62 (2) Walcker Residence notes the stem is free to rotate about at the top of the footing. The detail shown on the drawings does not match the analysis submitted. Please modify accordingly. 25. Detail A: The code requires the top and bottom of the ties spacing to be placed not more than one half a tie spacing above the top of the footing and below the lowest horizontal reinforcement in slab or drop panel above. Please modify the tie reinforcement spacing of the pilaster column top and bottom to note 4" OIC. ACI 7.10.5.4 Shoring Review General 26. 27.NiNknical 28. The analysis requires the concrete strength to have a compression force of 4 KSI as noted on sheet SH5.2 Please add the requirements for the concrete to the drawing. IBC 1901.4 Sheet SH1.0 Cover and Shoring Notes No comment for this sheet at this time. Sheet SH1.1 Shoring Notes 29. EOR, please the design properties of the pressure treated timber lagging add to the general notes. Without this information there is no way to check the size specified. Please add this information to the drawings and submit an analysis to justify the size used. Sheet SH2.0 Site Plan 30. Sheet SH3.0 Elevations 31. Design analysis specify the piles spacing shall not exceed S foot O/C but the drawings exceed this. The last page of the geotechnical analysis has the spacing of 9 feet but the wall height shall not exceed 5 feet. Pile P2 will exceed the wall height of 5 feet. Please modify accordingly. Sheet SH5.0 Typical Details 32. EOR, submit an analysis to justify the 4" pressure treated lumber to resist the required design force. 33. EOR, please submit an analysis for the flange of the steel beams to support the timber lagging. Page 7 of 7 EECE#: EDM 06-62 (2) Walcker Residence Sheet SH5.1 Typical Details 34. EOR, please specify the required length of the tie back. The drawing states anchor bond lengths see pile and anchor schedule, but 1 was unable to find the anchor schedule specifies these requirements. Please clarify where this is located. Sheet SH5.2 Typical Details 35. EOR, please submit an analysis for the flange of the steel beams to support the timber lagging. Sheet SH5.3 Typical Details 36. Detail 1: EOR, submit an analysis to justify the wood lagging will not shear off due to the flange bearing directly on the wood piece. Based off a check of analysis the wood will not be able to resist the design force bearing on the WI 8x55 flange (tf=518). NDS 3.10.1 and NDS 3.4.1 37. EOR, please submit an analysis for the angle to support the design loads. Sheet SH6.0 Permanent Retaining Wall Specifications No comment for this sheet at this time. Additional corrections may be required following receipt of corrections and additional information as requested. Your plans are being reviewed concurrently with the Building Department, Fire Department, Zoning Department and Public Works Engineering. Changes, clarifications or additional corrections may be required subsequent to the Building Department plan review when comments are received from the other concerned departments. Should you have any inquiries regarding this letter, please contact Hoyt Jeter at (360) 874- 0562 between 8:00 a.m. and 5:00 p.m. By: Hoyt Jeter, P.E. President