20070531161433.pdfCity of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: May 31, 2007
TO: Sergey Antonyuk
4307147 th Place SW
Mill Creek, WA 98012
d
FROM: Jenny Readwin, Plans Ex iner
RE: Plan Check # 2006-0545
Project: Antonyuk SFR
Project Address: 15911 74th Place W.
During re -review of the above noted application, it was found that the following information,
corrections, or clarifications are needed. Please redline plans or submit two (2) sets of revised
plans/documents (affected sheets only) with a written response to each of the items below to a
Permit Coordinator.
Continents below are from corrections dated March 27, 2007 by Ann Bullis, Assistant Building
Official and responses by Dwight McGrew dated April 27, 2007.
MANGE OF PROPERTY O NERICGNTRACTt R/LEAD DESIGN PROFESSIONAL
L Until the City is, notified in writing otherwise, you are still the Lead Design Professional of record for
this project, and Michel Construction is still the Owmer and General Contractor of record.
5/31/07 Response says these have been changed but I was unable to locate any letters addressing
this item. It is my understanding after talking to Jeannine Graf, Building Official that a new
Architect will be taking over as lead design professional and will be stamping all the plans. We
will also need a new Lead Design Professional Statement (see attached #2 for required wording)
and new Applicant/Owner Liability Statement from you as the new owner (see attached #11 for
required wording).
NONSTRUCTURAUSTR "I
2. Revise siteand civil plans to show change frorn.rockeries to retainin8 walls Viper previous e-mail
correspondence to Lyle Chrisinan). Provide structural calculations and details for the retaining walls
and cross refez-ence the details on the site and civil plans. This will be sent out for peer review and
special inspection will be required, Sem enclosed Retaining Wall handout for f arnation. (reference
pteviour nowtructural item 1)
5/31/07 Rockery/Retaining walls were covered under separate submittal. Separate comments for
the City's Geotechnical Consultant were sent May 18, 2007.
3, The Speciallaspection and Testing Agreements (3 special inspectors) submitted on 3/6/07 ate signed by
the Michel construction for. General Contractor and Owner. Submit new fore based ch.ange of
ownership and contractor inforination noted in item #1 above as atoplicablc_
5/31/07Still need prior to permit issuance.
4. Revise symbol legend on Sheets A2, .A:3, AS, A6, A7, so that the symbol lines up zvitli the, actual
description.
5/31/07 Response said see sheets A2, A3, A5, A-6 and A7 for revised legend. These sheets were not
resubmitted. Still need.
5. On Sheet A5, there is a now nous regarding pile, location that needs to be created with the structural
engineer and rernoved or clarified to give direction to the contractor,
5/31/07 Response said see sheet A5, note has been crossed out but this has not been done. Still
need.
6. Structural Egin=� ' response 9 from letter dated 8/21/06: prelude new detail 4 "typical deck post
mounting detail' on the plans and ems refertnct where it applies.
5/31/07 Response said detail Jincludes this information but that is not correct. Please add
Engineer's Detail (see attached) to plans.
7. Structural Engineer's response #15 from letter dated 8/21106'. On Sheet A6, reference thy: specific GLV
hanger that the engineer requirea at 6 N" CTLR to 7" M.
5/31107 Response said see sheet A6HGLTV 418-2 has been added butt was unable to locate this
on the plan. Please add.
Structural engineer's response #22 from leuer dated 8121106 states "architect to respond", however no
details could he faxed. on the pians addressing this itear,
5/31/07 This item is ok. No response needed.
Page 2 of 2
APPLICATION CHECKLIST FOR BUILDING PERMIT SUBMITTAL
APPOINTMENTS for application submittals must be scheduled with City Officials one week in advance.
Only complete submittals, including full review fees, will be accepted for City review. Failure to provide the
correct number of copies, plans, or other data will result in the application being rejected for review.
VESTING of building permit applications is achieved when the submittal contains each and every document
required by this checklist and is substantially complete in all respects. An applicant's rights shall vest when a
fully complete building permit application is filed. A fully complete permit application is an application
executed by owners of the property, or the duly authorized agent for such owners, contains each and every
document required under the terms of these ordinances, and is substantially complete in all respects. All
plans, reports and calculations must be prepared and stamped by design professionals licensed by the State of
Washington. It is anticipated that minor changes or revisions may be required during any application review
process. Such minor revisions or changes shall not keep an application from being deemed complete if a
good faith attempt has been made to submit a substantially complete application containing all required
components. A fully complete building permit application shall be accompanied by all fees, including, but
not limited to, building permit fees and plan check fees. (Ordinance #2769 & ECDC 19.00.015)
1. CRITICAL AREAS DETERMINATION AND/OR HEARING EXAMINER DECISION One Copy
A copy of the Critical Areas Determination and Hearing Examiner decision of Criticial Areas Reasonable
Use ExceptionNariance, or project specific Planning exemption as noted on the Critical Areas Checklist
must be complete at the time of permit submittal, OR, the applicant may request concurrent review of
Critical Areas ordinance compliance with the building permit review. Note, building permit review times are
extended when concurrent Critical Areas review is requested.
2. LEAD DESIGN PROFESSIONAL DESIGNATION AND STATEMENT Three Copies
One design professional shall act as the "lead design professional" for the applicant during the entire permit
review process. This licensed professional is responsible for coordinating and incorporating
recommendations of other design professionals onto the plans or into the submittal packet. This person
shall submit a letter or make a notation on the face of the plans that s/he has reviewed the geotechnical
report, understands its' recommendations and have incorporated into the design the established
measures to reduce the potential risk of injury or damage from any earth movement predicted in the
report. (ECDC 19.10.040)
3. VICINITY MAP Original
Within the packet, applicants are provided with the GeoEngineers map of the Landslide area. A signatory
block on the map must be filled out by the person who locates the project site on this map. (ECDC
19.10.030)
L;temp:bldg/handout/MeadowlMd_checkjlgREV06/07/2005 Page 3
7. Drainage Plan Information Continued
NOTE: If the proposed plan requires an easement across land owned by Burlington Northern Railroad, or
approval is needed from any other private party, the City shall be provided with a copy of the permit and/or
recorded easements.
8. GRADING PLAN Four Copies
Refer to Grading, Fill & Excavation handout. Plans shall be prepared and stamped by a State of Washington
licensed civil engineer. All geotechnical report recommendations shall be incorporated into the design and
detailed on the plans. Use existing grade contours from the topographic map to calculate grading yardage,
specifying exact yards of excavation, fill, and grading, as well as excavation yardage for the foundation.
Note, grade contours shall be shown at 2 foot intervals for slopes exceeding 15%. Include temporary erosion
control measures and permanent slope protection, indicate setbacks from top and toe of slopes. Provide a
driveway slope profile and indicate the maximum 4slope. No excavation, clearing or grading for any purpose,
including the creation of access to the site is permitted in advance of permit issuance. (ECDC 18.40) Be
advised, grading in excess of 250 cubic yards within 200 feet of a shoreline requires a separate Shoreline
Permit from the Planning Division. Be advised, grading in excess of 500 cubic yards requires State
Environmental Review by submitting a SEPA Checklist. (ECDC 20.55)
9. ARCHITECTURAL AND STRUCTURAL PLANS Thi'ee Copies
Refer to New Single Family Residential Permit Submittal handout for general requirements. All
architectural and structural plans must be stamped and signed by licensed professionals. Designers work
must be reviewed and stamped by State licensed professionals. It shall be the responsibility of the lead
design professional to submit, consistent with the findings of the geotechnical report, structural plans which
are prepared and stamped by the structural engineer. All architectural plans shall be stamped and signed by
the design architect or design engineer, whichever is applicable. The plans shall be consistent with the
hazards identified in the Roger Lowe Associates report from 1979 and the 1985 supplement by
GeoEngineers, and shall incorporate all geotechnical design requirements or recommendations that are
identified in the geotechnical report. Also, provide two stamped and signed copies of structural design
calculations. (ECDC 19.10.040)
10. AFFIDAVIT OF NOTICE OF APPLICATION
A notice shall be conspicuously posted and maintained on the site indicating that the owner has made
application for a permit with the City. The posting shall begin on the day the City accepts the permit
application for review and remain until occupancy is granted. Posting signs are available from the City (fee
$8.00). An affidavit of posting must be signed by the owner(s), notarized, and submitted to the Building
Division on the day the site is posted (form provided by the City). (ECDC 19.10.030C)
11. APPLICANT/OWNER LIABILITY & LANDSLIDE ACKNOWLEDGMENT Three Copies
The applicant/owner of the site shall submit a signed and notarized statement to the Building Official that
includes the following language: a) That the accuracy of all permit submittal information is warranted
by the applicant/owner in a form which relieves the City and its staff from any liability associated with
reliance on such permit application submittals. While an application may reference the reports of
prior public consultants to the City, all conclusions shall be those of the applicantlowner and her/bis
design professionals and, b) That the applicant/owner understands and accepts the risk of developing
in an area with potential unstable soils and that they will advise, in writing, any prospective
purchasers of the site, or any prospective lessees of structures on the site, of the slide potential of the -T
area. (ECDC 19.10.040)
L;temp:bldg/handout/Meadow/Md_checkjlgREV06/07/2005 Page 5
ol
C)
m
cn
O
y !
m
--i
n
7-
C-
Cl
-
N
CO
L
_
"n
N
m
X
r
j
�rn
Z
r
N
L
_
v/
r
i�
CD
L
O C'>
O
-mIU
En
CO
C)
T M
�V r
C
i
s
s
s
cn
RESUB
MAR 6 2007
BUILDING
ClTY OF EDMON S