Application:bld20071048 (grading)Date:
# bld20070040-20070645 (townhomes) April 28, 2008
Project Name/Address:
Valhalla / 23004 Edmonds Way
Contact Person/Address, Fax or E-mail:
Lesley Brown / lesleyb@adshapiro.com
Ed SibrelDivision:Engineering
Reviewer:
During review of the above noted application, it was found that the following information, corrections, or
clarifications are needed. Please redline plans or submit three (3) sets of revised plans/documents with a
written response to each of the items below to Marie Harrison.
GENERAL
Review Comments #1 Î 9/10/07
Review Comments #2 Î 12/5/07
Review Comments #3 Î 2/22/08
Review Comments #4 Î 3/24/08
Review Comments #5 Î 4/22/08
Review Comments #6 Î 4/28/08
th
Please note, Jeanie will be out of the office April 23-29. Please contact Ed Sibrel with any questions you
may have regarding your project. Ed can be reached at 425-771-0220 or by e-mail at
sibrel@ci.edmonds.wa.us. Ed is prepared to review the remaining items needed prior to issuance of your
permit. Permit submittals should still be made directly to Marie Harrison.
4/22/08 - The cost estimate was e-mailed to me today. I have reviewed the submittal and the following
changes need to be made and resubmitted to the City for reviewÈ.
4/28/08 – The bond for the right-of-way improvements shall be $51,132. The 2.2% inspection fee
shall be $4768. Onsite work may commence when these items are addressed and permit is issued.
DATE E-MAILED 4/28/08 PAGE
1 of 2
1.9/10/07 comment - Please provide a traffic control and haul route plan. Traffic control shall be shown for
nd
work on SR104 as well as 232.
12/5/07 Î response letter states this will be provided by contractor. To date, City has not received.
o
2/22/08 Î To date, City has not received.
o
3/24/08 Î Thank you for submitting a traffic control plan. Please revise and resubmit per the following:
o
nd
a.TCP plan shall show 232 St SW & SR-104 intersection.
b.Please remove signage from 2-way left turn lane.
nd
c.Provide TCP for work on 232 St SW.
d.Will only 400Ó of the east bound travel lane be closed at one time? The traffic control plan calls
out a 400Ó closure.
4/22/08 Î I was not been able to find a revised traffic control plan with the latest submittal. Please
o
revise as requested. No work shall commence in the City right-of-way prior to approval of the traffic
control plan.
4/28/08 – The TCP received 4/25/08 is inadequate for the scope of the project. It does not address
o
items (c) and (d) of the points above, and does not appear to follow standard WSDOT guidelines
for traffic control on State rights-of-way. Helpful information on this topic may be found at:
http://www.wsdot.wa.gov/Design/Standards/Plans.htm#SectionK
Permitted activities at this point shall be limited to onsite work. Work within the right-of-way
shall not commence priot to approval of a TCP.
Please contact me at 425-771-0220 or by e-mail at mcconnell@ci.edmonds.wa.us if you have specific