Loading...
20080516141420.pdfDATE: May 16, 2008 City of Edmonds PLAN REVIEW COMMENTS BUILDING DIVISION (425) 771-0220 TO: Doug Johnson Fax: 425-745-2813 FROM: Ann Bullis, Assistant Building Official RE: Plan Check # 2008-0176 Project: Johnson SFR Project Address: 8040 Cyrus Place During review of the plans for the above noted project, it was found that the following information, clarifications or changes are needed. Redline existing plans on file with the City. Please coordinate resubmittal with Marie Harrison, Permit Coordinator. 1. Show location and label PUD and PSE easements on the site plans. 2. The following Special Inspections will be required by the Geotechnical Engineer of Record for this project: a. Excavation, grading and site preparation, including cut slopes b. Placement of fill and compaction c. Soil bearing verification d. Foundation drainage e. General site monitoring during wet weather construction f. Final letter from the Geotechnical Engineer of Record Complete the enclosed Special Inspection and Testing Agreement, have the owner, general contractor and geotechnical engineer sign the agreement and return to the City prior to permit issuance. 3. Revise underslab gravel and vapor barrier requirements as specifically noted in soils report. 4. Revise detail for foundation drainage as specifically noted in the soils report. CITY OF EDMONDS SPECIAL INSPECTION AND TESTING AGREEMENT The project at b L-f—r[J Com') Y_V—.2> )— 4-A:6 .T issued under building permit number 2,c%S-- 017 1--, requires special inspection and/or testing per IBC Chapter 17. The complete list of special inspections is attached to this document. BEFORE A PERMIT CAN BE ISSUED: The owner and contractor and special inspector shall complete this agreement and the attached structural test(s) and inspections schedule including the required acknowledgements. APPROVAL OF SPECIAL INSPECTORS: Each special inspector shall be approved by the Building Official prior to performing any duties or inspections. Each special inspector shall submit Statement of Qualifications to the Building Official for review. Special inspectors shall display identification when performing special inspections on site. Special inspection and testing shall meet the minimum requirements of IBC Chapter 17 and the following: A. Duties and Responsibilities of the Special Inspector 1. Observe Work The special inspector shall observe the site work for conformance with the approved (stamped) plans and specifications and applicable workmanship provisions of the IBC. Architect or Engineer reviewed shop drawings may be used only as an aid to inspection. Special Inspections are to be performed on a continuous basis --meaning that the special inspector is on site at all times observing the work requiring special inspection. Periodic inspections, if any, must have prior approval by the City based on a separate written plan reviewed and approved by the Building Official and the engineer or architect of record. 2. Report Non -conforming Items The special inspector shall bring non -conforming items to the immediate attention of the contractor and note all such items in the daily field report. Any item not resolved in a timely manner shall be immediate cause of the special inspector to notify the Building Official of the plan deviation, error, change or omission. It shall also be the duty of the special inspector to promptly notify the engineer or architect. 3. Complete Daily Reports Each special inspector shall complete and sign both the special inspection record and the daily report form for each day's inspection.. These records shall remain at the jobsite with the contractor for review by the City Building Inspector. 4.. Furnish Weekly Reports The special inspector or inspection agency shall furnish the City with weekly reports of tests and inspections. The project engineer or architect, and others as designated shall also be copied on reports. Weekly reports must include the following: • Description of daily inspections and tests made with applicable locations • List of all non -conforming items • Report on status of non --conforming items (resolved or unresolved) • Itemized changes authorized by the Architect, Engineer and City if not included in non- conformance items. S. Furnish Final Construction Report The special inspector or inspection agency shall submit a final signed report to the City stating that all items requiring special inspection and testing were fulfilled and reported_ And, to the best of L:ITEMP1BUILDTNG1SpeciallnspectionAgreementlBC_doc 7/04 his/her knowledge the project is in conformance with the approved plans and specifications, approved change orders and the applicable workmanship provisions of the IBC. Items not in conformance or unresolved items or any discrepancies in inspection coverage, (Le., missed inspections, periodic inspection when continuous inspections were required, etc.) shall be specifically itemized in this report. B. Contractor Responsibilities 1. Notify the Special Inspector It is the duty of the contractor to notify the special inspector when work is ready for special inspection. Note, the items listed on the attached schedule and as noted on the approved plans and specifications are required to have special inspections. Adequate notice shall be provided by the contractor so that the special inspector has time to become familiar with the project. 2. Provide Access to Approved Plans The contractor is responsible for providing the special inspector access to approved plans at,the jobsite. 3. Retain Special Inspection Records The contractor is responsible to retain at the jobsite all special inspection records submitted by the special inspector. These records are to be provided to the City building inspector upon request. C. City of Edmonds Building Department Responsibilities 1. Approve special inspectors or inspection agencies The building department shall approve all special inspectors and special inspection requirements. 2. Monitor special inspection and approve weekly reports Work requiring special inspection and the performance of special inspectors shall be monitored by the City Building Inspector. His/Her approval must be obtained prior to placement of concrete or other similar activities in addition to that of the special inspector. 3. Issue Certificate of Occupancy The Building Official may issue a Certificate of Occupancy after all weekly special inspection reports including the final report have been submitted and accepted. D. Owner Responsibilities The project owner or the engineer or architect of record acting as the owner's agent shall fund special inspection services. E. Engineer or Architect of Record Responsibilities The engineer or architect of record shall include special inspection requirements on the plans and specifications. ACKNOWLEDGEMENTS I have read and agree to comply with the terms and conditions of this agreement. Owner Date Special Inspector Date General Contractor Date City Building Official Date L:\TEMP\BUILDING\SpeciallnspectionAgreementlBC_doc 7104 REINFORCED CONCRETE, GUNITE, GROUT AND MORTAR: Concrett Gwm to Grout Mortar Aggregate Tests RemfC"g Tests Mix Designs Reinforcing Placement Batch Plant Inspection Inspect Placitte Can Samples Pick-up Samples Compression Tests PRECAST/PRESTRESSED CONCRETE: r rio tubi-i[rt5 Y[eYlt7ls Aggregate Tests Reinforcing Tests Tendon Tests Mix Designs Reinforcing Placement Insert Placement Concrttt Batching Concrete Placement Cast Tests MASONRY Special lnspeetion Stresses Used — Preliminary Acceptance Tests (Masonry Units. Wall Prisms) — Subsequent Tests (Mortar. Grout, Field Wall Prisms) — Placement Inspection of Units STRUCTURAL STEEL (WELDING: — Sample and Test (list specific memo n below) — Shop Material Identification Welding ksp<c — 0 Shop D Field — Ultrasonic Inspcctiat OShop D Field — High-strength Mdng O Shop D Field D A325 D A490 ON OX . OF — Metal Deck Welding Inspection � Reinforcing Steel Welding Inspection — Metal Stud Welding inspection — Concrete Insert Welding Inspection FIREPROOFING: Placement Inspection — DemityTests - Thickness Tests — Inspect Batching INSULATING CONCRETE: — Sample and Test — Placemtut Inspection — Unit Weights FILL MATERIAL: — Acceptance Tests — Placement Inspection — Field Density STRUCTURAL WOOD-- Shear OOD.Shear WaII Nailing Inspection Inspection of Glulan Fab. Inspection of Truss Joist Fab. ADDITIONAL INSTRUCTIONS OR OTHER TESTS — Smnpkand Test Conptxrcnis AND INSPECTIONS: �MAVA'aOAJ. • I' : .UOr r .i+r�.�� CA AAA --I Formconpleted by Title_ Tekpborx No. 1 — Date: