20080829141352.pdfStru'ture x„ Stated Area
S.F.
Gross Area
Existing Not dimensioned 1240
New area 799
Total 2039
2042
The above referenced project is in the process of plan review for compliance with
Edmonds ordinances andapplicable codes. The following comments,
deficiencies/corrections must be addressed prior to completion of plans review and
subsequent issuance of permits
Provide revised plans and calculationsalong with a written response to each of the items
listed below to facilitate a shorted, back -check time.
SCOPE OF REVIEW
The scope of this review is for the Sir'dit,'A al, Ordinance, V&IAQC, Energy requirements
of this project.`
All features were checked onl 'to='.tom' extent allowed by the submittals provided. All
portions of this project are assumed to°meet or will meet other departmental requirements,
conditions and concerns before permif approval.
10. Please clarify on the elrawing`how the dryer will be vented to the outside.
M1502 This appears not -.to be ad ressed at this time. Please modify drawings
accordingly. It is important that & duct does not terminate with in 3 feet of any
opening. Windows arc considered ripenings. Please modify the drawings
accordingly.
STRUCTURAL COMMENTS'
Sheet 1 of 3 Main Floor Plan
2. 15. Please specify he required. support of the new 3 118 X.12 glu-beams noted on
this sheet. Nothing is specified at. this time to support the beam. The drawings now
specify the post put the i6yuired,connection of the post to the beam is not
specified. Only the center post has the top but not the other post. This is required
to be specified on the dz*�rings iiv order to prevent lateral translations. 8407.3
3. Please note the required connection of the existing 2x8 that is bearing on the 4x5
beam. The connections rs very important since is braces the compression zone of
the beam under bending Pleaseclarify where this is specified on the drawings or
add to the drawings as required
Sheet 2 of 3 Foundations Plan and Sections
4. 20. Please specify the requred.post-to-foundation connection at all load-bearing
posts. Nothing is specified at '41 time to resist lateral displacement. R407.3 It was
not clear on the revised dz:avvin(); where the required post to fowidations was
specified. Please clarify an.the ilra Ings where this information was specified.
VENTILATION AND IDOOIZ; AJR QUALITY CONTROL COMMENTS
No comments at this time'
ENERGY COMMENTS
General
5. 23. Please specify the required ground cover in the crawl space. WSEC 502.1.6.71
was unable to determine from the 'drawings submitted where this information was
specified. Please clarify upon the response.
:Pdge3of3
Additional corrections may be''regiuredfollowing receipt of corrections and additional
information as requested.
Your plans are being reviewed':,. concurrently with the Building Department, Fire
Department, Zoning Department: and. Public Works Engineering. Changes, clarifications
or additional corrections may 17e required subsequent to the Building Department plan
review when comments are received from the other concerned departments.
Should you have any inquiries regarding this letter, please contact Hoyt Jeter at (360) 874-
0562 between 8:00 a.m. and 5:00. pm':
By.
Hoyt Jeter, P.E.
President