20090317100450.pdfConfirmation Page Page 1 of 2
pscIeanair.org
Puget Sound Clean Air Agency
Notification Confirmation
on May 22, 2008, the Agency Board of Directors approved a fee increase to cover asbestos program costs. The fee change
became effective July 1, 2008.
Fee Information:
(Fees Last Revised 7/1/2008)
Please review the following information you have submitted. If a change is needed, select the Modify
Notification Information button.
Notification Fee. Asbestos
Demolition $75.00
Emergency
Total $75.00
Owner's Name BNSF Railway Phone (206) 625-6264
Site Address 191 West Dayton Street
Site City Edmonds Zip 98020
Contact Person Don Omsberg Phone (205) 625-6264
Mailing Address 2454 Occidental Ave. S. Suite 2D
Seattle, WA 98134
'his project Includes multiple structures. Each structure's number and street address:
Iris project consists of demolishing on actual permanent structure and 4 ilnivan portable structures that are parked
around it at the 191 West Dayton address.
This project includes a demolition.
Demolition Start Date 03/16/09 Completion Date 04/16/09
Demolition will be completed by a demolition contractor
Demo Contractor Derrick Construction Industries, Inc. Contractor Job # Edmond
Contact Shane Johnson Phone (952) 894-0012
Mailing Address 7217 W. 128th Street
Savage, MN 55378
https://secure.pseleanair.org/Asbestos/Confinn.aspx 2/23/2009
Alter payment,
Project Categories
when can I start
Asbestos
Fee
Demolition
Fee
my project?
Single -Family Residence Project
Asbestos removal only Today $30
L$O—$75
Demolition (with or without IlDemolition - In 10 Days75
asbestos removal) Asbestos Removal - Today
Project other than Single -Family Residence
with < 10 linear feet and/or
Demolition - In 10 Days $0 $75
48 square feet of friable asbestos
>= 10 - 259 linear feet and/or
sbestos Removal - Today
$75
0
Demolition- In 10 Days
$75
>= 48 - 159 square feet of asbestos
260 - 999 linear feet and/or
160 - 4,999 square feet of asbestos
In 10 Days $250
11
$75
>= 1,000 linear feet and/or
>= 5,000 square feet of asbestos
In 10 Days $750
$100
If your project is an Emergency, an additional fee may apply.
Emergency Demolition orToday
applicable fees + $50
Emergency Asbestos Removal*
*Single-family residences are exempt from the emergency fee.
Please review the following information you have submitted. If a change is needed, select the Modify
Notification Information button.
Notification Fee. Asbestos
Demolition $75.00
Emergency
Total $75.00
Owner's Name BNSF Railway Phone (206) 625-6264
Site Address 191 West Dayton Street
Site City Edmonds Zip 98020
Contact Person Don Omsberg Phone (205) 625-6264
Mailing Address 2454 Occidental Ave. S. Suite 2D
Seattle, WA 98134
'his project Includes multiple structures. Each structure's number and street address:
Iris project consists of demolishing on actual permanent structure and 4 ilnivan portable structures that are parked
around it at the 191 West Dayton address.
This project includes a demolition.
Demolition Start Date 03/16/09 Completion Date 04/16/09
Demolition will be completed by a demolition contractor
Demo Contractor Derrick Construction Industries, Inc. Contractor Job # Edmond
Contact Shane Johnson Phone (952) 894-0012
Mailing Address 7217 W. 128th Street
Savage, MN 55378
https://secure.pseleanair.org/Asbestos/Confinn.aspx 2/23/2009