2009-0345 Jorgensen #2.pdf City of Edmonds PLAN REVIEW COMMENTS BUILDING DIVISION (425) 771-0220 DATE: August 19, 2009 TO: Kristin Hanson hansondesign@hotmail.com FROM: Leif Bjorback, Assistant Building Official RE: Plan Check: 2009-0345 #2 Project: Jorgensen residence Project Address: 1122 Vista Place During review of the plans for the above noted project, it was found that the following information, clarifications or changes are needed. Please provide written responses as to where the changes can be found on the plans, and submit revised plans/documents to Marie Harrison, Senior Permit Coordinator. Thank you. NON-STRUCTURAL COMMENTS 1. Previous #13. Include drainage for the retaining wall in detail CFI/S2 as per the soils report. Additional information may be necessary from the geotechnical engineer to design an adequate drainage system for this wall. The response provided addressed a different wall (SRW/S2) than the one in question. Please provide a detail from the geotechnical engineer or the structural engineer for drainage at CFI/S2. (The same detail is also on sheet 4.) IBC 1805.5.6 and 1806.1 STRUCTURAL COMMENTS General 1.Not included. 2.Not included. Sheet 3 Upper floor 3.Not included. Sheet 4 Foundations 4.Not included. 5.7. EOR, please provide analysis for the footing specified on this sheet. This was not in the engineering analysis at this time. The response gives the vertical capacity for bearing but the reinforcement specified analysis has not been submitted. Please provide this upon the response. 6.8. The design analysis submitted for the wall used a grade 60 steel but the details state to use grade 40 for the #4. Please submit analysis for grade 40 steel for the wall on this sheet to support the design loads. The new response for the cantlever retaining wall shows the SRW wall will not support the loads. Please have the EOR stamp this sheet to show that this has been reviewed and submit an analysis for the wall shown on this sheet. Sheet 5 Lower Floor Framing 7. Not included. Sheet 6 Upper Floor Framing 8.Not included. 9.13. EOR, please specify the required post and connection for the 3-1/2X11-7/8 PSL In the garage area. The required post to beam connections are required to be specified. (The model number of the connector given is incomplete.) Please clarify on the drawings. 10.15. EOR, the interior wall that are bearing have different depth joist on each side. Please provide a detail how the joist are supported when the joist are different depth. For example, the 11-7/8 bearing on the hallway wall/beam and the hallway joist is only 9-1/2 deep and bedroom joist are 11-7/8”. All detail show the joist the same depth. Please clarify the drawings fro this case. The response states a note has been added to provide blocking. How is the blocking attached? Provide a detail for this condition to show a complete load path not just a note to provide blocking. This is not standard construction so a detail is required to show complete load path. 11.Not included. 12.17. EOR, please specify the required connection of the 4x12 (beam mark 1-6) to the 4X12 header (beam mark 1-8). The response states there are not any connections required since it bears on the top of the beam. All beams are required to have a positive connection and not just note to bear on the beam. Please specify the required beam connections on the drawings to transfer the design forces. IBC 2304.9.6 13.18. EOR, please specify the required connection for the 4X12 (Beam mark 1-21) and where the header beam 4x12 (Beam mark 1-8) frames in at the jamb. The response states the beam is lower and they do not interfere. Please provide a detail and the required connections at this location. The drawings are not clear and a detail is required to show complete load path. 14.Not included. Sheet 7 Roof Framing 15.Not included. Page 2 of 3 Sheet 9 Typical Wall C Deck Sections D and Stairs/Railing 16.Not included. Sheet S1 17.Not included. 18.26. Shear wall schedule: EOR please not the 2” nailing shall be staggered and member shall be 3-x member. IBC 2306.4.1 footnote 3. The response states note 7 has been added. This also needs to be added for the wall base plate nailing where it states 16d @ 2” O/C. Please modify accordingly. Page 3 of 3