PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: December 1, 2009
TO: Stefan Rehnfelt
Stevens Hospital
srehnfelt@stevenshospital.org
FROM: Leif Bjorback, Assistant Building Official
RE: Plan Check: 2009-0799
rd
Project: Stevens Hospital, 3 floor lobby
th
Project Address: 21601 76 Ave W
During review of the plans for the above noted project, it was found that the following information,
clarifications or changes are needed. Please provide written responses as to where the changes can
be found on the plans, and submit revised plans/documents to Theresa Umbaugh, Senior Permit
Coordinator. Thank you.
1.On sheet A-001, change the Occupancy group to I-2.
2.Wall bracing shall be independent of the suspended ceiling. Please modify the wall details
on sheet A-105 to show rigid bracing from the top of wall up to structure. ASCE 7-05
Section 13.5.8.1
3.The Interior Lighting Summary as submitted indicates that no changes are being made to the
lighting; however, new fixtures are shown above the information desk and behind the built-
in seating, and it is likely that existing fixtures will be relocated at the new offices and
reflection room. Please revise the Lighting Summary as applicable. The Alteration
Exceptions on the form may still be used if appropriate.
If you wish, the architect may choose to redline any changes to the plans and forms by coming in to
the permit counter to do so.