PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: February 2, 2012
TO: Gasline Mechanical Inc.
Woodinville, WA 98072
Email: janderson@gaslinemechanical.com
FROM: Leif Bjorback, Assistant Building Official
nd
RE: Plan Check: 2011-1086, 2 review
Project: GRE HVAC
Project Address: 23020 Edmonds Way
During review of the plans for the above noted project, it was found that the following information,
clarifications or changes are needed. Please provide written responses as to where the changes can
be found on the plans, and submit revised plans/documents to a permit coordinator. Thank you.
1.The floor plans for the common area (Fitness, Media, etc) on the ground floor do not match
the approved building plans. Please verify the layout on this set is accurate, otherwise adjust
as needed. This item has not been addressed in writing. Please verify the proper floor plan.
2.Completed.
3.Completed.
4.Completed.
5.Completed.
6.The exhaust ducts from the Fitness Room and Restrooms penetrate a 3 hour fire wall into the
garage. Show 3 hour fire dampers at these locations. IBC 716.5.1 and IBC Table 716.3.2.1
The SFDs added at the restroom exhaust are satisfactory, however there is none shown for
the Fitness room as requested.
7.A fire rated shaft is required where the supply duct from RTU-1 penetrates the roof and 2
floors. Provide details for construction of the shaft, including the listing of the rated
assembly. IBC 708.2 This item has not been addressed, but must be prior to proceeding.
Please consult the building designer, and provide a note on the mechanical plans
referencing the rated shaft.
8.Please provide stamped and signed calculations and details by a licensed engineer for the
RTU seismic attachments as it exceed 400 lbs. This is to include unit-to-curb and curb-to-
roof attachments. This item has not been addressed.