20120427144949825.pdfLaniO'Connor 5831 106th Street SW, Mukilteo, WA 98275 -4646 Leonard Yarberry City of Edmonds 121 5th Avenue North Edmonds, WA 98020 April 24th, 2012 Application No.: #BLD20120170 Project: Paish, SFIR Add/Rem Structural Review Location: 832 Pine St Reviewer: O'Connor P425.315.8519 loconnor26@frontier.com APR 2, 15 2017, E" Uffl, ()F EUMON'Dor This project has been reviewed for a second time for the structural requirements of the 2009 International Building Codes. The following are comments directed to the applicant indicating additional or revised information required. Please let me know if you have any questions. Incomplete information or unrevised items are shown in bold under the original correction. 4. Structural calculation show design for pin piles at spread footings, detail 3/S3 provides a design with pin piles and a pile cap. Are pin piles required due to poor soil conditions? If so, was a soils report provided indicating the parameters for design and bearing or pile capacity? Provide documentation for the pin pile requirement and design criteria. 5. Sheet A7, south elevation - show new concrete retaining wall by grid A. Specify maximum slope for finished grade as 2 horiz to 1 vertical. Paish BLD20120170 Page 2 Structural 1. List individual special inspections on the plans including epoxy grout, welding, pin piles, etc. Engineer's letter indicates a note added to structural notes for special inspections. However, no new notes were found on sheet S 2.0, which was the only structural sheet that was revised and resubmitted. 2. Specify 5 1 /2 sack mix concrete for no special inspection. Engineer's letter indicates structural notes changed to show 51h sack. No new notes were provided on the structural plans. 10. Sheet Al - provide calculations showing the adequacy of 6 3/4 x 18" GLB at grid 3.3/D-G. Calculations show 8.25 x 18 or 2 - 5 1 /8 x 18 GLB. As indicated - Calculations recommend two beams both of which have a larger section modulus and area than the 6 3/4 x 18" GLB that is indicated on the plans. Provide calculations as previously indicated or revise the plans to show one of the beams recommended in the calculations. 11. Sheet A10 - provide calculations for the 8 3/4" x 24" GLB beams shown supporting the deck floor loads and their footings. Several different beam sizes were found in the calculations - however they do not reflect the construction conditions shown on the plans. As previously indicated, provide calculations for this beam. The calculations shown at Fir Bm Ln d/4-5 (page 9 - no page 10 is provided) do not reflect the beam length or loading conditions on the plans. 13. Provide uplift calculations for the roof cant, roof joists and beams. Calculations have been provided. However, the recommendation of the Engineer to provide an H3 for each rafter does not appear to be shown on the plans. Show this on the plans and/or indicate where this is shown. 14. Provide structural calculations for retaining wall shown in detail 1 /Al 8. Include over -turning, concrete strength, rebar, dimensions, and surcharge shown at the top of the wall via sloped backfill. Calculations have been provided and the retaining wall design limited to 5' retained height. Sheet Al no longer shows the retaining wall detail. However, details D- A17, C-A17, 5A18 still reference a retaining wall section on A18. Revise plans to show correction construction section and retaining wall reference. 16. Sections, elevations and plans refer to "air gap" material. Specify what the air gap material is and provide specifications. Provide a note indicating that the "air gap" material must be part of the approved, listed assembly for siding and veneer material. Paish BLD20120170 Page 3 22. Sheet A9, foundation plan - column details show #3 ties @ 12" O.C. -revise tie spacing notes to match Sheet Al 5, details 4 and 5. Column notes at entry way have not been revised. 24. Sheet A9, foundation plan grid D - specify detail references for new footings and columns. New reference shows A/B17 - should this be B/A17. 30. Al 5, detail 6 - show vent details including required openings in blocking to provide ventilation and cross ventilation. Detail shows blocking stopping short of the roof diaphragm, with no diaphragm nailing in order to provide ventilation. Revise the detail to show the blocking continuing to and flush with the roof diaphragm. Also show the nailing at the edge of the diaphragm. Show how ventilation and cross ventilation is to be accomplished, as previously indicated. 42. Sheet A22, shows two detail 3's. Clarify. Response indicates this was revised. This was not revised - Plans still show two detail 3's. 44. Sheet S-3.0 - detail 4 - where is this used? Response indicates revised - no revisions found. Please contact me if you have any questions. Thank You, Lani O'Connor, P.E. cc: Marie Harrison, Permit Coordinator