2012-1103 Chang SFR2.pdf
City of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: April 4, 2013
TO: The Leren Co., Inc.
Attn: Tom Leren
tom@lerendesign.com
FROM: Chuck Miller, Plans Examiner
RE: Plan Check: 2012-1103
Project: Chang SFR
rd
Project Address: 17306 73 Avenue W
During a review of the plans for the above noted project, it was found that the following
information, clarifications or changes are needed. Please provide written responses as to where the
changes can be found on the plans, cloud all changes on the revised plans, and submit the revised
Previous comments that recur on this list appear in
plans/documents to a Permit Coordinator.
italics
Thank you.
.
On page 3:
1.2009 General & Structural Notes G. Timber Framing Note #14 Clarify the difference
in the required minimum header - #2 (2)2x8 DF-L and that noted on pages 6 & 8 - #2 4x8
DF to guide proper construction and inspection.
2.2009 Washington State Energy Code fan sizing and glazing percentage data Indicate on
the plans in the spaces provided the Glazing Square Footage and Glazing Percentage to
support the selection of the Table 6-1 Option II prescriptive compliance path of the WSEC.
It appears that the updated data (due to the window changes in Bedroom #3 and the Living
Room) was inadvertently omitted.
On pages 6, 8, or 9:
3.Provide on the plans the Post, Cap & Base Schedule and the Hanger Schedule to guide
proper installation and inspection. It appears that those items (previously placed on the same
pages of building plans dated 11/27/2012) were inadvertently omitted.