PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: July 17, 2014
TO: Randall J. Munson
randy.munson@comcast.net
FROM: Andrew Gahan, Plans Examiner
RE: Plan Check: BLD2014-0189
Project: Coleman SFR
th
Project Address: 902 9 Avenue S
During a review of the plans by the Building Division for the above noted project, it was found that
the following information, clarifications, or changes are needed. A complete review cannot be
performed until the revised plans/documents, including a written response indicating where the
clouded or otherwise highlighted changes can be found on the revised plans, have been submitted
to a Permit Coordinator. Reviews by other divisions, such as Planning, Engineering, or Fire, may
result in additional comments.
General Note:
1.Clarify on the plans the means to be used to develop the required energy credits from the
selected WSEC Table R406 options. The provided energy code compliance worksheet
indicates that option 1a has been selected, while the window schedule indicates an
incorrect U-factor and the floor insulation is improperly specified on sheets A-4 and A-5 to
meet the requirements of option 1a. Additionally, it was indicated on the Building Permit
Application Form A that the furnace will be replaced and/or relocated. If the furnace is to
be replaced, the required energy credits could be obtained through option 3a, with the
installation of a 95% efficiency furnace.