2014-0659 Prestige Care PMG.pdf City of Edmonds PLAN REVIEW COMMENTS BUILDING DIVISION (425) 771-0220 DATE: July 22, 2014 TO: David Wilson Carletti Architects Email: david@carlettiarchitects.com FROM: Leif Bjorback, Building Official RE: Plan Check: 2014-0659 Project: Prestige Care Mechanical th Project Address: 21008 76 Ave W During review of the plans for the above noted project, it was found that the following information, clarifications or changes are needed. Please provide written responses as to where the changes can be found on the plans, and submit revised plans/documents to a permit coordinator in the Development Services Department. Thank you. General 1.Please provide calculations and design details for the seismic anchorage of rooftop equipment weighing more than 400 pounds. (All RTU’s and MUA-1) The documents must be stamped and signed by a Washington state licensed engineer. 2.On the HVAC floor plans, please show the reference callouts for the applicable details that are shown on sheets M4.0 and M4.1. 3.The notes on sheet M1.0 state that smoke fire dampers are to be installed where ducts penetrate fire and smoke rated assemblies, and there appear to be a large number of these locations. Please show these locations on the HVAC floor plans, including ceiling dampers, either by symbol, notation or referenced callouts. 4.Add a note on the plans that the med gas system is to be verified by a third party agency according to UPC 1327. Sheet M-1.3 5.Please indicate which fixtures will require backflow prevention devices and what devices will be used. UPC 103.2.2 and 603.1 Sheet M-2.2 6.Add a note as to the location of the reference key and equipment schedule for the circled callouts in the kitchen, or include the information on sheet M2.2. 7.Please provide an enlarged/enhanced kitchen drainage plan. Revise the drainage plan to discharge fixtures into the grease interceptor or directly to sanitary sewer as appropriate, and according to comments from Les Krestel, Wastewater Treatment Technician. Sheet M2.10 8.What is the symbol “MAP/1” shown in Nurse Station 130? Sheet M3.2 9.A Type 2 exhaust hood is required over the warewasher. Provide details and CFM for this hood. IMC 507.2.2 10.Clearly show the locations of the kitchen exhaust hoods on the plans. I suggest this information would be helpful if shown on sheets M3.2 and FS1. 11.The med gas room is shown to be exhausted by a 50 cfm fan, through a “6x4 wrapped duct up to roof cap.” Please provide a design for the “wrap” to show how it complies with the shaft requirement of IMC 502.9.1 12.Provide a supply duct to the med gas room complying with the requirements of IMC 502.9.1. Sheet M3.6 13.On the Roof Plan, provide at least 10 feet of separation between the kitchen exhaust fans and any other equipment with air intake, or show how it meets the exception to IMC 506.3.13.3. Sheet M3.8 14.The size of the dryer exhaust duct on the roof plan does not match that in detail 6/M4.0. Please coordinate. 15.How will the grease ducts be separated from combustible materials as per IMC 506.3.6? The note on detail 5/M4.1 states: “See Captive Aire detail on MX.XX for duct detail” but a detail is not provided. Please clarify. 16.Drawing #2 on M4.2 notes “1 inch layer of insulation meets 0 inch requirements for clearance to combustible surfaces.” Please provide the mechanical code section or other approved agency listing to show how this detail complies with IMC 507.9. 17.The appliances under the Type 1 hood are listed as a gas range, broiler, griddle, and oven, and these appear to be medium duty or even heavy duty appliances by definition in IMC 202, and need at least 300 cfm or 400 cfm, respectively. Please clarify, and modify the plans as needed. IMC 507.13 Page 2 of 2