20140806145310957.pdfJuly 31, 2014 ATTN: Chuck Miller City of Edmonds RE: Plan Check: BLD2013-0860 Project: Gray Addition d Project Address: 22306 92 Ave. W On Sheet AD1.0: RESJ,jjj�,.�,7, jj�, CITY E0A40NDi,,,' 1. Foundation Demo Plan — Clarify the difference in the size of the east isolated footing in the center of the garage and of that required at that location on sheet 'AF1.0" — Foundation Plan. Detail 1 on sheet AD1.0 — The dimension for the area of the slab to demolished is 2'-6"x2'-6", which matches the 30"x3O" footing to be installed. I rol 1191 ffz�i 11iiWlI L a. Indicate on the plans the required post to support the loads below the east end of the proposed (4)2x8 HF #2 girder beam. Detail 2 on sheet AF1.0 — The built-up (4)2x8 IIF #2 spans over the existing 5 1/2'W%" GLB's. No post is required. b. Clarify the callout for the (4)2x8 F -IF #2 to be used as a girder supporting the post below the west end of the roof girder. It appears to be over spanned and fails in bending. 'The tributary load may be reduced as a result of the response to review comment'5b'. Indicate on the plans the required nailing (size of fastener, spacing and arrangement, etc.) when specifying a 'built-up' member. Detail 2 on -- :F1.0 The • (4)2x8 INF 42 supports a point loaf-q- from wall of - existing house. O.C.ADD KEYNOTE 1.6 — "BUILT-UP MEMBER: NAIL LAM. 1,14 16d @ 12" 1 DIRECTLY UNDER WALL ADD — Built-up beam ((3)2x8 HF #2) located under the north wall of the computer ••. ADD • •-.m ((2)2x8 HF #2) located under the southof computer•• c. Clarify the callout for the 'existing 6x8 glu-lam beam' to be used to support the loads at each end of the girder noted in the above review comment and the loads from the floor joists — see review comment '4a'. Keynote on - - a GLU-LAM BEAM TO REMAIN". '4111111rourINFUNTITS a. Provide a 'shearwall schedule', or a reference to that provided on sheet 'S- 2.0% to guide the proper construction and inspection of the walls 'marked' with a number -in -a -triangle'. Sheet AF1.0 — ADD GENERAL NOTE — 111. SEE S-2.0 FOR SAEASM',IALL ■ Dv SCHEDULE.Sheet A1.1 — ADD GENERAL NOTE — 112. SEE S-2.0 FOR SHEARWALL b. Provide an 'epoxy holdown schedule', or a reference to that provided on sheet 'S-2.0', to guide the proper installation and inspection of the holdown anchorage. Sheet -' 0 _ :DD GENERAL NOTE _w_ S:-2.0 FOR EPDXY _ ii 4. Foundation Plan Key Notes: a. Clarify the 'existing 6x8 glu-lam beam' identified in note 1.2'. Typically the result of a process where multiple 1-1/2 inch thick members are glued together, the depth of the beam is usually a product of the number of layers multiplied by 1-1/2 inches. The specified width does not reflect that of those commonly manufactured. Keynote 1.2 on _ GLU-LAM BEAM TO x b. Provide on the plans a reference to note '1.6' to guide proper installation and inspection of the required construction per the structural design. Sheet AF1.0 — ADD GENERAL NOTE — "3. SEE DETAIL 2/S-1.0 FOR REQUIRED • 5. Roof Framing Plan: a. Clarify the reference to detail '2/S-1.0'— Interior Shearwall Connection — along the interior wall between the `Hall' and the `Computer Room'. There does not appear to be any other information elsewhere in the provided construction documents indicating a shearwall at that location. b. Clarify the callout for the 2x8 HF #2, installed at 16 inches on -center, to be used as the upper roof rafters. They appear to be over spanned and deflect beyond that allowed per table R301.7. There does not appear to be any intermediate bearing elements represented on the provided construction documents. c. Clarify the callout for the (4)2x8 HF #2 to be used as a girder supporting the upper and lower roof rafters. It appears to be over spanned, fails in bending and deflects beyond that allowed per Table R301.7. The tributary load may be reduced as a result of the response to the review comment above. Indicate on the plans the required nailing (size of fastener, spacing and arrangement, etc.) when specifying a `built-up' member. Sheet A1.1 — ADD KEYNOTE 1.2 — "BUILT-UP MEMBER: NAIL LAM. W/ 16d • O.C. C Indicate on the plans the required post to support the loads below each end of the proposed (4)2x8 HF #2 girder beam. existing top plate and the top plate of the east wall of the addition. No post is required. 6. Second Floor Plan: a. Clarify the square footage of the proposed `Computer Room'. It does not appear to meet requirements of R304.2 and R304.3. Detail 1 on -- The Northof - Computer roombeen • -• two feet to the northorder to meet the requirements of R304.2. RD NOTE b. Provide a shearwall schedule, or a reference to that provided on sheet 'S-2.0', to guide the proper construction and inspection of the walls `marked' with a `number -in -a -triangle'. Sheet A1.1 — ADD GENERAL NOTE — "2. SEE S-2.0 FOR SHEARWALL c. General Notes — Update the mandatory lighting equipment requirements to that of the 2012 Washington State Energy Code (WSEC). Sheet A1.1 — CHANGE GENERAL NOTE 1 TO READ "ELECTRICAL — t5% OF LUMINARIES SHALL BE HIGH EFFICACY LUMINARIES 2012 WSEC." 7. Clarify the applicability of the provided lateral calculations to the proposed project. The cover sheet notes an address different than that on the application and the information contain therein does not appear to reflect the conditions represented on the provided construction documents. The address on the provided structural calculations is the correct project ar.OWress. See tWe attached structural calculations. Sincerely, Miles Walker Associate