2014-0915 Edmonds Village mechanical - AllStar Htg.pdf
City of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: September 26, 2014
TO: Patrick Converse
patrick@allstar-hvac.com
FROM: Chuck Miller, Plans Examiner
RE: Plan Check: BLD2014-0915
Project: Edmonds Village mechanical
Project Address: 22001 Highway 99
During a review of the plans by the Building Division for the above noted project, it was found that
the following information, clarifications, or changes are needed. A complete review cannot be
performed until the revised plans/documents, including a written response indicating where the
clouded or otherwise highlighted changes can be found on the revised plans, have been submitted
to a Permit Coordinator. Reviews by other divisions, such as Planning, Engineering, or Fire, may
result in additional comments.
In the provided equipment specifications:
1.Clarify the callout for the duct-free cooling-only condensing units to be used to provide air-
conditioning. They do not appear to meet the SEER requirements per the Washington
State Energy Code (WSEC) Table C403.2.3(1).
Additional Note:
A separate permit will be required for the installation of the required fans, ductwork,
·
diffusers, grilles, etc. used to provide the minimum mechanical ventilation to the space(s)
per IMC 403.3.