2014-1073 Kongsomboot 4.pdf
City of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: August 9, 2015
TO: Kristadang Kongsomboot
kongsomboot@hotmail.com
FROM: Andrew Gahan, Plans Examiner
th
RE: Plan Check: BLD2014-1073 4 Review
Project: Car Port
th
Project Address: 23422 76 Avenue West
During a review of the plans by the Building Division for the above noted project, it was found that
the following information, clarifications, or changes are needed. A complete review cannot be
performed until the revised plans/documents, including a written response indicating where the
clouded or otherwise highlighted changes can be found on the revised plans, have been submitted
to a Permit Coordinator. Reviews by other divisions, such as Planning, Engineering, or Fire, may
result in additional comments.
1.The plans currently represent that the 4x8 roof beam is a full span beam, which is an
overstressed condition. It is assumed that a post is meant to be installed at mid-span. Please
verify.
2.Please provide a footing at each of the posts, or provide calculations showing that the use of
the existing slab is adequate.
3.Per IRC R905.2.2, asphalt composition shingles are reserved for use with roofs having a
slope of 2:12 or greater. It appears that the car port roof shown on the plans has a low slope
or flat roof. Please provide acceptable roof covering material.