20150325150937845.pdfJoAnne,
The following is our response to the corrections we received from your office re: Lot 4 Woodvale
1. Drywell moved
2. Water and sewer lines moved
3. Sewer is connected where the stub is shown. That other line is the connecting line form the note about the
manhole cover
We are submitting 3 complete new site plans of the project.
Please feel free to contact me if you need any other information or have any questions.
Joe"%ert
Directol of Architectural Design
Burnstead Construction Company LLC
Joe 2Butnstead.coin
(425) 818-7467
11980 N.E. 24th St., Suite 200, Be1lerue, 111,4 98005-1576 425 454 1900 Fax: 425 990 349
ri�iv�s�.h�.u•rzstead.carn
THE
3/20/2015
S -
URNSfFAD-
JoAnne Zulauf
City of Edmonds
Engineering Division
121 5th Ave N
Edmonds, WA 98020
Plan Check: BLD2015-0167
23602 105"' PI W
Project: Burnstead SFR lot 4
JoAnne,
The following is our response to the corrections we received from your office re: Lot 4 Woodvale
1. Drywell moved
2. Water and sewer lines moved
3. Sewer is connected where the stub is shown. That other line is the connecting line form the note about the
manhole cover
We are submitting 3 complete new site plans of the project.
Please feel free to contact me if you need any other information or have any questions.
Joe"%ert
Directol of Architectural Design
Burnstead Construction Company LLC
Joe 2Butnstead.coin
(425) 818-7467
11980 N.E. 24th St., Suite 200, Be1lerue, 111,4 98005-1576 425 454 1900 Fax: 425 990 349