20150413152932895.pdf4/10/15
JoAnne Zulauf
City of Edmonds
1215`h Avenue North
Edmonds, WA 93020
RE: BLD20150125
Dear JoAnne,
Per your correction letter dated 2/9/15 the plans have been revised as follows:
�r
1. Added the two yard drains on the east side. Noted to grade yard to the new yard drains.
2. Driveway length added.
3. We should not need to catch the driveway water before it flows into the road. It all drains to the
approved detention vault.
4. Was shown but clarified.
5. Added callouts to the roof drain system.
6. Revised line type for the footing drain to FT.
7. Revised sewer alignment.
Should you have any additional questions or issues I can be reached at 206.920.3673.
Sincerely,
Todd Echelbarger
u � I11 6° ,��> jG wOOd �"�1� � ��u��������p (z-112 e")') ���d/;�� a �d��� (�11-" �!�p� (573� ���d� n"un;�h
1. Added the two yard drains on the east side. Noted to grade yard to the new yard drains.
2. Driveway length added.
3. We should not need to catch the driveway water before it flows into the road. It all drains to the
approved detention vault.
4. Was shown but clarified.
5. Added callouts to the roof drain system.
6. Revised line type for the footing drain to FT.
7. Revised sewer alignment.
Should you have any additional questions or issues I can be reached at 206.920.3673.
Sincerely,
Todd Echelbarger
u � I11 6° ,��> jG wOOd �"�1� � ��u��������p (z-112 e")') ���d/;�� a �d��� (�11-" �!�p� (573� ���d� n"un;�h