20150603133629873.pdfCedar View Memory Care — Narrative April 24, 2015 Re: Response to City of Edmonds Plan check for project # BLD2015-0032 Several significant changes took place since the last submittal that affected the structural engineering. First, the third floor framing system was changed from a 4 inch think concrete diaphragm and steel floor joist system to a wood "I" joist framing scheme with a 1.5 inch concrete toping. Second, the brick siding on the outside of the building was changed from a 4 inch thick brick to a 3/4" brick veneer, which had the affect of greatly reducing the weight of the building. The third major change were that several roof framing members were consolidated so that there are fewer individual members called out, and overall the roof framing plan is now simpler. S-1.0 Structural Cover Sheet Updated design criteria section to show Seismic Design Category as Da and the use of 2 different R values in the seismic design including R = 6.5 for the upper two levels of wood framing and R = 5.0 for the lower level which utilizes concrete shear walls. (This analysis is allowed given that the lower level is stiffer than those levels above.) Changed the roof snow load to 25 psf. Changed the base shear value. In the table for Cast -In - Place Concrete changed the specification for concrete in walls to 3,000 psi. Noted that the allowable soil bearing pressure is 3,000 psf in accordance with the geotechnical report by Terracon, project no. 81145006. S-1.1 Foundation Plan Changed the thickness of the slab on grade to 5" thick. Increased the overall dimension of the building by 1" each direction. Added 2 inches to the overall width and length of the building. Moved the pier located at gridlines C and 3, 9' 6" to the east. Added to grid line "K" to the plans. Updated Pier Schedule for the grade, size and number of rebar called out for each pier size. S-1.2 Foundation Details Changed thickness of slab on grade to 5" thick. Changed masonry header details to a concrete header detail. Removed details that were no longer applicable. S-1.3 Retaining Wall Details Provided a hook at the end of the footing's transverse bars. Added dimensions for concrete cover. S-1.4 Stair Details and Shear Reinforcement Details Changed details D, E and G to reflect new design caused by the removal of the third level concrete floor system and the lighter lateral loads. Removed details that no longer apply. S-1.5 Slab Construction Joints Changed thickness of slab on grade to 5" thick. S-3.1 Third Floor Framing Plan Added this sheet to the plans. Revised the entire design for this level to eliminate the 4" concrete diaphragm with Hambro steel trusses and replaced that design with a wood "I" joist design and 1.5" of concrete topping. S-4.1 Roof Framing Plan Consolidated the number of individual members specified so that there are fewer callouts and coordinated those specified members with the engineering calculations while also consolidating the engineering calculations. Eliminated a section of roof at the south west corner of the interior courtyard. Noted that all roof trusses will be designed and engineered by the truss manufacture and noted on the plan view of each manufactured truss configuration. Cross referenced detail bugs with other drawings. S-4.2 Roof Details. Removed the roof framing notes from this sheet and copied them over to sheet S-4.1. Detail D has been eliminated reflecting the removal of the roof beam over the dining area. At Detail H, provided member reference "2.18" to the glu lam shown in the detail. For Details I and K, changed the location of the detail bug on sheet S-4.1 so that the appropriate beam is addressed by the detail. S-4.3 Roof Details Eliminated this sheet. S-5.1 First Floor Shear Walls and Second Floor Diaphragm Eliminated all references to masonry shear walls as a decision was made to use concrete shear walls only. Simplified the drag rebar specifications to accommodate the lower lateral loads from the removal of the third level concrete floor and the weight savings change of the 3/4" thick brick veneer vs. 4" thick brick. Eliminated the concrete shear wall at the center of the stairway well. and eliminated the eener-ete shear walls at the S-5.2 Second Floor Shear Walls and Third Floor Diaphragm Redesigned the entire level for the change of the third floor assembly from a 4" thick concrete floor to wood "I" joists with a 1.5" concrete topping. Eliminated all concrete shear walls from this level and converted to wood framed shear walls with either plywood covering or a double sided sheetrock shear wall. S-5.3 Third Floor Shear Walls Revised shear wall specifications to reflect the lower overall shear loading resulting from the weight savings changes of the design of the third floor framing and the use of the 3/4" thick exterior brick veneer vs, 4" thick brick. S-5.4 and S-5.5 Shear Wall Elevations S-5.5 is a new sheet. Both sheets show concrete shear wall elevations and the placement of reinforcing bars. Sheet S-5.4 was modified to reflect the elimination of second level concrete shear walls. and the elif inat o of the eenefete shear walls an the Cedar View Memory Care — Narrative April 24, 2015 Re: Response to City of Edmonds Plan check for project # BLD2015-0032 Several significant changes took place since the last submittal that affected the structural engineering. First, the third floor framing system was changed from a 4 inch think concrete diaphragm and steel floor joist system to a wood "I" joist framing scheme with a 1.5 inch concrete toping. Second, the brick siding on the outside of the building was changed from a 4 inch thick brick to a3/4" brick veneer, which had the affect of greatly reducing the weight of the building. The third major change were that several roof framing members were consolidated so that there are fewer individual members called out, and overall the roof framing plan is now simpler. S-1.0 Structural Cover Sheet Updated design criteria section to show Seismic Design Category as Da and the use of 2 different R values in the seismic design including R = 6.5 for the upper two levels of wood framing and R = 5.0 for the lower level which utilizes concrete shear walls. (This analysis is allowed given that the lower level is stiffer than those levels above.) Changed the roof snow load to 25 psf. Changed the base shear value. In the table for Cast -In - Place Concrete changed the specification for concrete in walls to 3,000 psi. Noted that the allowable soil bearing pressure is 3,000 psf in accordance with the geotechnical report by Terracon, project no. 81145006. S-1.1 Foundation Plan Changed the thickness of the slab on grade to 5" thick. Increased the overall dimension of the building by 1" each direction. Added 2 inches to the overall width and length of the building. Moved the pier located at gridlines C and 3, 9' 6" to the east. Added to grid line "K" to the plans. Updated Pier Schedule for the grade, size and number of rebar called out for each pier size. S-1.2 Foundation Details Changed thickness of slab on grade to 5" thick. Changed masonry header details to a concrete header detail. Removed details that were no longer applicable. S-1.3 Retaining Wall Details Provided a hook at the end of the footing's transverse bars. Added dimensions for concrete cover. S-1.4 Stair Details and Shear Reinforcement Details Changed details D, E and G to reflect new design caused by the removal of the third level concrete floor system and the lighter lateral loads. Removed details that no longer apply. S-1.5 Slab Construction Joints Changed thickness of slab on grade to 5" thick. S-3.1 Third Floor Framing Plan Added this sheet to the plans. Revised the entire design for this level to eliminate the 4" concrete diaphragm with Hambro steel trusses and replaced that design with a wood "I" joist design and 1.5" of concrete topping. S-4.1 Roof Framing Plan Consolidated the number of individual members specified so that there are fewer callouts and coordinated those specified members with the engineering calculations while also consolidating the engineering calculations. Eliminated a section of roof at the south west corner of the interior courtyard. Noted that all roof trusses will be designed and engineered by the truss manufacture and noted on the plan view of each manufactured truss configuration. Cross referenced detail bugs with other drawings. S-4.2 Roof Details. Removed the roof framing notes from this sheet and copied them over to sheet S-4.1. Detail D has been eliminated reflecting the removal of the roof beam over the dining area. At Detail H, provided member reference "2.18" to the glu lam shown in the detail. For Details I and K, changed the location of the detail bug on sheet S-4.1 so that the appropriate beam is addressed by the detail. S-4.3 Roof Details Eliminated this sheet. S-5.1 First Floor Shear Walls and Second Floor Diaphragm Eliminated all references to masonry shear walls as a decision was made to use concrete shear walls only. Simplified the drag rebar specifications to accommodate the lower lateral loads from the removal of the third level concrete floor and the weight savings change of the 3/4" thick brick veneer vs. 4" thick brick. Eliminated the concrete shear wall at the center of the stairway well. and eliminated the eonerete sheaf ally at the sides of the elevator- shafts. S-5.2 Second Floor Shear Walls and Third Floor Diaphragm Redesigned the entire level for the change of the third floor assembly from a 4" thick concrete floor to wood "I" joists with a 1.5" concrete topping. Eliminated all concrete shear walls from this level and converted to wood framed shear walls with either plywood covering or a double sided sheetrock shear wall. S-5.3 Third Floor Shear Walls Revised shear wall specifications to reflect the lower overall shear loading resulting from the weight savings changes of the design of the third floor framing and the use of the 3/4" thick exterior brick veneer vs, 4" thick brick. S-5.4 and S-5.5 Shear Wall Elevations S-5.5 is a new sheet. Both sheets show concrete shear wall elevations and the placement of reinforcing bars. Sheet S-5.4 was modified to reflect the elimination of second level concrete shear walls. and the elimination of the , ro+o sheaf walls a -round the elevators,