PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: November 16, 2015
TO: Elizabeth Clay Johnson
elizabeth@claydesignllc.com
FROM: Chuck Miller, Plans Examiner
RE: Plan Check: BLD2015-1091
Project: Albertson addition-remodel
th
Project Address: 19715 80 Place W
During a review of the plans by the Building Division for the above noted project, it was found that
the following information, clarifications, or changes are needed. A complete review cannot be
performed until the revised plans/documents, including a written response indicating where the
clouded or otherwise highlighted changes can be found on the revised plans, have been submitted
to a Permit Coordinator. Items that recur appear in italics.
nd
Resubmittals must be made at the Development Services Department on the 2 Floor of City Hall.
Permit Center hours are M, T, Th, & F from 8am-4:30pm. The Permit Center is closed on
Wednesdays.
Reviews by other divisions, such as Planning, Engineering, or Fire, may result in additional
comments.
On sheet A104 Framing Plans
1.Roof Framing Plan
a.Clarify the callout for the 2-2x12 hip rafters. They appear to be over spanned, fail in
bending, and deflect beyond that permitted per IRC Table R301.7.
b.Clarify the callout for the proposed 2-2x12 ridge beam. It appears to be over
spanned and fails in bending.