2015-1622 Select Homes SFR2 - Nash.pdf
City of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: March 17, 2016
TO: Select Homes, Inc.
kayla.clark@outlook.com
FROM: Chuck Miller, Plans Examiner
RE: Plan Check: BLD2015-1622
th
Project Address: 919 9 Avenue N
Project: Select Homes SFR
Scope: Construct single family residence R-3/U occupancy group V-B
construction - NFPA-13D sprinkler system required mechanical and plumbing
included
disapproved
Please be advised that the building plans for the above referenced project have been
for the purposes of obtaining a building permit. During a review of the plans by the Building
Division for compliance with the applicable building codes, it was found that the following
.
information, clarifications, or changes are neededReviews by other divisions, such as Planning,
Engineering, or Fire, may result in additional comments that require attention beyond the scope of
this letter. Items that recur on this list appear in italics.
A complete review cannot be performed until the revised plans/documents, including a
written response in itemized letter formatindicating where the clouded or otherwise
highlighted changes can be found on the revised plans, have been submitted to a Permit
Coordinator.
nd
Resubmittals must be made at the Development Services Department on the 2 Floor of City
Hall. Permit Center hours are M, T, Th, & F from 8am-4:30pm and from 8:30am-12pm on
Wednesdays.
On sheet A3:
1.Foundation Plan - Clarify the callout for the 42x42x12 isolated footing below the east end of
beam B-2 8-3/4x18 GLB the south end of beam B-5 5-1/8x18 - and the south end of
the girder truss above. It appears to be undersized for the loads anticipated by the
represented construction and noted in the provided calculations. The noted load and the
change to the footing does not appear to account for the south end of the east girder truss.