PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: January 29, 2016
TO: Golddiggers Inc.
Attn: Dan
golddiggersinc@aol.com
FROM: Andrew Gahan, Plans Examiner
RE: Plan Check: BLD2016-0107
Project: Maplewood Manor
Fire Connection
During a review of the project by the Building Division for the above noted project, it was found
that some form of verification is required for the work performed. The City cannot issue final
approval until verification is received.
In specific, verification is needed by an Engineer licensed in the State of Washington (EOR)
regarding the structural adequacy of the vault walls and of the replacement lid where the original lid
has been removed. The aforementioned verification is acceptable in one of the following formats:
1.Submit a letter sealed and signed by the EOR stating that the structural adequacy of the
vault walls is uncompromised by removing a portion of the lid. In addition, the
aforementioned letter should state that the structural adequacy of the replacement lid has
been verified, as built.
OR
2.Submit as-built construction plans including the layout, sections, details, etc. required to
allow for plan review, accompanied by supporting calculations, all sealed and signed by the
EOR.
Should you have additional comments or questions, please feel free to contact Andy at 425-771-
0220, ext. 1389.