20160108131844.pdfJennifer Lambert 121 5th Avenue North Edmonds, WA 98020 (425) 771-0220 Re: Kemper Residence response to Storm Comment #3a IECO No. 15-0736 Dear Jennifer, This letter is in response to your storm comment #3a regarding the existing detention system installed per the Plat (S98-082). The detention system was designed to accommodate 5,000 sqft of impervious surface for the proposed development. A site reconnaissance was performed to verify the functioning of the detention system on December 16th 2015. Based on the visual inspection, it is my opinion that the detention system is functioning properly and can accommodate the drainage from the proposed project as designed. Also, the downstream of the system does not appear to have any drainage constraints. Sincerely, Brian R. Kalab, P.E. r