20160121102229.pdf9740 Evergreen Way * Everett, Washington 98204 WESTERN & (425) 356-2700 SURVEYORS SURVEYORS • ENGINEERS • LAND USE CONSULTANTS January 19, 2016 City of Edmonds Attn: Jennifer Lambert 121 5th Avenue North Edmonds, WA 98020 Subject: 2nd Construction Plan Comments, BLD20151168 Dear Ms. Lambert: FAX (425) 356-2708 i 13 A N P, 1, 20 V, ui 17yOff"1, ' Us Below is a response to comments you and others made per review of construction plan documents dated January 13, 2016: Demo: 1. Contractor to address Site Plan: 1. Architect to address all site plan comments. PLANNING DIVISION COMMENTS: Sheet 'I of 2 — Grading, SWPPP Plan and Notes. 1. Project number updated with no "G". 2. OK 3. Silt fence removed from tree drip line near the SE corner of the site. Unaware of any other silt fencing shown within tree drip lines. 4. OK 5. OK 6. OK 7. Temporary stock pile relocated to rear of house. 8. Silt fence protection shown around infiltration area. Sheet 2 of 2 — Drainage & Utility Plan 1. Project number updated with no "G". 2. Existing gravel along the frontage noted to be removed and replaced with landscaping area and is no longer shown on sheet 2 as it is to be removed. 3. I'm not sure why this comment is under the sheet 2 comments. Sheet 1 (ie SWPPP and Grading Plan) previously noted existing curb and wall to be removed. Additionally, these items to be removed are not shown on sheet 2 which also signifies its removal. Maybe this comment was only meant for site plan edits? 4. New Comment — Impervious areas have not changed with civil plan edits. Site plan to be updated accordingly to match civil plans. LAND USE CONSULTANTS * CIVIL ENGINEERS * LAND SURVEYORS * ENGINEERING CORPORATION R/\][[1CDSEIl'b'd ER\201 551467AR0NGuVF\V^N0NICi1L1CO NG'v\21" IIk]MEW (.",0MM1[" q' V L:"V'"LI"r ,".., r ll SURVEYORS • ENGINEERS • LAND USE CONSULTANTS Water: Sewer: Storm: 9740 Evergreen Way * Everett, Washington 98204 (425) 356-2700 FAX (425) 356-2708 1. Replaced water meter shall be located within public right-of-way. As the 2' gravel transition strip is not allowed in public right-of-way, this comment does not apply. Note that additional notes have been added to the driveway section detail noting no 2' gravel transition strip allowed in public right-of-way along with 6" depth compost amended soils beneath 2' gravel spreader. 2. No change 3. No change 1, No change 2. No change 3. No change 1. OK 2. OK 3. OK 4. Added surface flow direction to drawing for aid. Yes, portions of the driveway near 93rd Place slope more southwestern than southerly but there will still be a low point installed in the driveway to the east of the garage to facilitate driveway runoff through the adjacent vegetated area. Additionally, even if more driveway runoff reaches the low point in the driveway than just the standard perpendicular slope direction, there is so much available vegetated flow path to the south of the driveway to account for any potential additional driveway runoff. By this, the longest potential flow path on the driveway to the gravel spreader is approximately 401-F of surface flow. Per drainage manual specs, 10LF of vegetated flow required per 20LF of surface runoff. Assuming worst case for max driveway surface flows for this would result in a minimum vegetated flow path of approximately 201-F. Currently there is approximately 52LF of flow path from the edge of driveway to the south boundary line resulting in more than double the available flow path. 5. OK 6. OK 7. OK Utilities: 1. OK Sincerely, Western Engineers & Surveyors, Inc, Jesse Jarrell, P.E. Project Manager LAND USE CONSULTANTS * CIVIL ENGINEERS * LAND SURVEYORS * ENGINEERING CORPORATION 0 VIII SII!'.][VvIl RVO11115 1151467.A,,P W f'46'"FU '4d ill11"�F1n IIblcii ,p°"I][mvIlMh''UMVINIM>fII II a ]II'F:IF°. 1�lVl�� City of Edmonds - � � � BLD20151168 121 5TH AVENUE NORTH EDMONDS, WA 98020 • (425) 771-0220 FAX (425) 771-0221 n /O Website: �44vwV,l'Ri7 bi1dti1 y i. PUBLIC WORK DEPARTMENT RESUB Planning • Building • Engineering Jud 12010 Engineering Plan Review Comments Permit Application #: RT.n20151168 __ Date: ia.,,,a, y 111?01 F Project Name/Address: CTelotte _ _22420 — 9 id pl W Contact Person/Address, Fax or E-mail RanNewton - r°3cwtge)tnsn.cnm Reviewer: jENNIFF,R LAMBERT Division: FNCTINF,FRING During review of the subject submittal, it was found that the following information, corrections, or clarifications would need to be addressed. All Handouts referred to in these comments can be accessed at our website: www.edinondswa.gov under City Government / Development Services Department / Engineering Division then scroll down to Handouts: 1st Review— 11/13/15 2"d Review —1/13/16 DEMO BLD20151452 1) 1/13/16 — Comment was not addressed. Please add the note to the plans. 11/13/15 Comment - Add a note that the water and sewer will be cut and capped per Olympic View Water and Sewer District. SITE PLAN 1) As changes are made to other plan sheets, please revise this sheet as needed. 2) OK 3) OK 4) OK New comment —1/13/16 5) Please label the existing curb and wall to be removed from the Site Plan. 6) The impervious surface calculations are inconsistent with the Civils. Please revise to be consistent. DATE E-MAILED 1/14/2016 PAGE (1) City of Edmonds BLD20151168 1215 T" AVENUE NORTH EDMONDS, WA 98020 • (425) 771-0220 FAX (425) 771-0221 Q Website: ,vww.edn1ogds°4 a, ?vPUBLIC WORK DEPARTMENT Planning • Building • Engineering Engineering lig Plan Review Comments B PPPAND G ADING P?�LA:N '1 OF 2' X41) 1/13/16 — Comment was partially addressed. Please remove the `G'. 11/13/15 Comment - Revise `BLDG2015 'to BLD20151168'. 2) OK 3) 1/13/16— Cornment° was partially addressed; however, the silt fence is shown within the drip line IJ , of the trees. please revisethe plans such that there is no disturbance (except for the removal of the existing walkway) within the drip lane of the trees. 11/13/15 Comment - The silt fence is shown around the entire site; however, there appears to be no construction west of the infiltration system. Does the silt fence need to be located at the west property line. Please revise accordingly. 4) OK 5) OK 6) OK 7) 1/13/16— Comment was partially addressed; however, the stockpile is located within the drip line pr of the trees. Please revise the plans to show the stockpile located outside of the drip line. 11/ l3/ 15 Comment - Please show the location of any stockpiles. The stockpiles shall not be placed over flee 1 �°cal ose l l ac rt rar7 o{" the i� f 11ration system. 8) 1/13/16 — Comment was partially addressed. A note was added to the lines; however, a protection fence should be shown around the infiltration system. l.1 / 13/15 Comment - Protect proposed infi lt.ration area from compaction by heavy machinery. DRAINAGE AND UTILITY PLAN 2 OF 2 GENERAL 1) 1/13/16 — Comment was partially addressed. Please remove the `G'. DATE E-MAILED 1/14/2016 PAGE (2) City of Edmonds BLD20151168 121 5" AVENUE NORTH EDMONDS, WA 98020 • (425) 771-0220 FAX (425) 771-0221 Website: www.edniondswa.gov PUBLIC WORK DEPARTMENT Planning • Building • Engineering Engineering Plan Review Comments 11/13/15 Comment - Revise BLDG2015 ' to BLD20151168'. 2) 1/13/16 -- Comment was not addressed. �tr ° t' l/ l3/15 Comment - Show the drip line of the trees. If the gravel area (located in the right-of-way) is located within the drip kine, the gravel area will need to be removed and replaced with landscape to V"') protect the tree. u LY('4 3) 1/13/16 — Comment was partially addressed. Please label the existing curb and wall to be removed 'a on Sheet 1 and the Site Plan. „ 11/13/16 Comment - There is a concrete curb and wood retaining wall on the Site Plan. Please show the curb and wall on the drainage and utility plan. Note as existing or proposed. New comment —1/13/16 1) The impervious surface calculations are inconsistent with the Site Plan. Please revise to be consistent. WATER 1) 1/13/16 — Comment was addressed; however, the water meter and line will need to be relocated outside the 2' gravel flow spreader. Leaving original comments since locations may change. 11/13/15 Comment - It appears that a fire sprinkler system is required for this property. Typically if there is an existing water service line from the watermain to the meter the water service line/meter will not be the appropriate size and a new tap will be required. a. Please add a note that a 1" meter is to be installed b. Show the water meter located in the right-of-way, such that the back of the meter is on the property line. c. Show the water meter; such that it is not located within the driveway. d. Please show a 1-1/2" line to be installed from the back of the meter to the house (as required for a combination fire and domestic service line). e. Please label the pipe material and note tracer wire to be installed on the water service line. 2) 1/13/16 — Comment was addressed. Leaving original comments since locations may change. DATE E-MAILED 1/14/2016 PAGE (3) City of Edmonds BLD20151168 121 5TH AVENUE NORTH EDMONDS, WA 98020 • (425) 771-0220 FAX (425) 771-0221 Website: www .edrn nd nq! 8(')v PUBLIC WORK DEPARTMENT Planning • Building • Engineering Engineering Plan Review Comments 11/13/15 Comment - Show that there is a minimum of 10' of separation between the water and the sewer lines. 3) 1/13/16 — Comment was addressed. Leaving original comments since locations may change. 11/13/15 Comment - Show that there is a minimum of 3' of separation between the water and the dry utilities (i.e. power, phone, gas, cable, etc.). SEWER 1) 1/13/16 — Comment was addressed. Leaving original comments since locations may change. 11/13/15 Comment - Show the sewer line on the plans from the main to the house. This is to verify utility separation. 2) OK 3) OK STORM 1) OK 2) OK 3) OK 4) 1/13/16 — Comment was partially addressed. It appears that there is approx. 6% slope from the street to the garage. How will the surface water runoff from the driveway be directed to the gravel flow spreader? For a slope of 6% for a driveway, relying on cross slope alone may not be sufficient. a, 0 11/13/15 Comment - Show how the surface water runoff from the driveway discharges to the onsite stormwater management system (i.e. directional flow arrows). 5) OK DATE E-MAILED 1/14L7016 PAGE (4) 4 6) OK 7) OK City of Edmonds BLD20151168 1215 TH AVENUE NORTH EDMONDS, WA 98020 • (425) 771-0220 FAX (425) 771-0221 Website: wwv , dnnoid;wg.g(v PUBLIC WORK DEPARTMENT Planning • Building • Engineering Engineering Plan Review Comments Comments by the City Stormwater Engineer Program Manager, Jerry Shuster, PE The stormwater system has been approved. DRY UTILITIES 1) OK Please resubmit 3 copies of the revised plans and associated documents with a written response to each item to a Permit Coordinator. Please contact me at 425-771-0220 ext 1321 or by e-mail at "etittifer.latttbert ),edmoitdswit. ov if you have specific questions regarding these plan corrections. DATE E-MAILED 1/14/2016 PAGE (5)