PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
DATE: June 7, 2016
TO: Brad Williams
brad@williams-mechanical.com
FROM: Chuck Miller, Plans Examiner
RE: Plan Check: BLD2016-0608
Project Address: 150 Sunset Avenue S
Project: Top Pot TI plumbing second review
Scope: Roof drains, plumbing, and gas piping installation for restaurant and
restrooms B occupancy group 48 occupants V-B construction - NFPA-13
sprinkler system
disapproved
Please be advised that the building plans for the above referenced project have been
for the purposes of obtaining a building permit. During a review of the plans by the Building
Division for compliance with the applicable building codes, it was found that the following
.
information, clarifications, or changes are neededReviews by other divisions, such as Planning,
Engineering, or Fire, may result in additional comments that require attention beyond the scope of
this letter. Items that recur on this list appear in italics.
A complete review cannot be performed until the revised plans/documents, including a
written response in itemized letter format indicating where the clouded or otherwise
highlighted changes can be found on the revised plans, have been submitted to a Permit
Coordinator.
nd
Resubmittals must be made at the Development Services Department on the 2 Floor of City Hall.
Permit Center hours are M, T, Th, & F from 8am-4:30pm and from 8:30am-12pm on Wednesdays.
General Review Note:
The plumbing installation depicted requires a grease interceptor to be installed to provide
1.
waste pretreatment per the Development Services Department Engineering Division and
the Public Works Department of the City of Edmonds see attached.The proposed size
and location of the grease interceptor and its installation criteria, including the invert
elevations for the drain lines serving the interceptor and the connection to the sanitary
side sewer, should be shown on the site plan to guide proper review, construction, and
inspection.
The installation of the grease interceptor can be added to the scope of work to
be done under this permit or under that of a separate permit. Either way, approval for the
currently proposed plumbing work cannot be obtained until the required grease interceptor
for the installation has been submitted.
The response to the plan review comments appears to be a resubmittal composed of cut-
sheets for the proposed installation of a hydromechanical grease interceptor (Great Basin
75) and a dishwasher (Jackson Avenger HT-E), a copy of Chapter 10 Traps and
Interceptors of the Uniform Plumbing Code, and a sanitary drainage diagram with the
added note Install GB 75 grease trap outside building.. A response letter could not be
found clarifying the proposed installation of the 125 gallon grease interceptor as an
alternative to that determined to be required by the Pretreatment Technician see attached.
No change appears to have been made to the site plan indicating the proposed location of the
grease interceptor, the invert elevations for the drain lines serving the interceptor, and the
connection to the sanitary side sewer.