20170124105053.pdf'�es po -I—
Botesch, bash & Mall JAN 19 W?
Architects, P.S.
DEPARTMENTcRY OF
January 18th, 2017
ATTN: Chuck Miller
City of Edmonds
RE.. Plan Check: BLD2016-1550
Project: Green Token Cannabis T.I.
Project Address: 7215 212th Street SW
Review Comments;.
On sheet AS1.0 — Site Plan:
1. Detail 1 — Site Plan
a. Clarify on the plans the represented width of the accessible parking space. It does
not appear to meet the requirement for a van parking space per IBC 1106.5/ICC
Al 17.1-2009 502.2
Site plan revised to show van accessible parking stall.
b. Eliminate from the plans the detail reference to, or provide on the plans, the detail
referenced on sheet "A1.0". A corresponding detail could not be found on sheet
"A1.01
.
The detail callout 1 on sheet A1.0 references the floor plan on sheet A1.0.
On sheet G1.0 — Cover Sheet:
2. General Notes — Note #1 and note #17 — Change on the plans the code versions to
reflect those currently adopted by the Washington State Building Code Council.
General notes updated to reflect the current code.
3. Project Data
a. Major Applicable Codes — Change on the plans the code versions to reflect those
currently adopted by the Washington State Building Code Council.
Major applicable codes list updated.
b. Occupancy Type (Chapter 3) — Change on the plans the occupancy type to reflect
that applicable to a structure used for the display and sale of merchandise.
Occupancy type updated to M occupancy.
1IPage
c. Scope of Work — Indicated on the plans the proposed work requiring review for
compliance with applicable codes.
Scope of Work updated to read: "TENANT IMPROVEMENT WORK TO INCLUDE
NEW NON -BEARING INTERIOR WALLS, NEW LIGHTING AND UPDATING THE
RESTROOM TO COMPLY WITH THE REQUIREMENTS OF THE ADA."
d. Occupant Loads (Table 1004.1.1)
i. Change on the plans the table reference to reflect that found in the currently
adopted building code (2015 International Building Code).
Occupant Load Table reference revised to read: "TABLE 1004.1.2".
ii. Clarify on the plans the indicated areas of the "Mercantile" and "Office" spaces.
They do not appear to reflect that determined by "scaling" or by other review
methods — see attached 'occupant load". Update the indicated occupant loads
as required.
Occupant load calculations updated. This has been revised on sheet G1.0 as
well as sheet A1.0.
4. Deferred Submittals — Indicate on the plans the required submittal under separate permit
application any proposed/required mechanical, electrical, and/or plumbing work
associated with the work completed under this permit application.
Deferred Submittals has been removed from sheet G1.0.
On sheet A1.0 — Floor Plan:
5. Detail 1 — Floor Plan
a. Change on the plans the indicated occupancy loads for each of the spaces to reflect
that determined in response to plan review comment "3.d.ii".
Occupant load calculations updated. This has been revised on sheet A1.0 for the
individual spaces.
b. Indicate on the plans any furnishings, shelving, or racks that may be installed in
space "102" — Office — to guide proper installation and for review and inspection of
the means of egress and accessibility provisions.
Sheet A1.0 — Add Note "ANY SHELVING OR STORAGE RACKS OVER 6 FT TALL
MUST BE SEISMICALLY ANCHORED."
c. Clarify on the plans the means to be used to support the mechanical mezzanine
indicated on the approved plans under permit BLD1988-0146 after the proposed
removal of the wall per keynote callout "1.3".
The mechanical mezzanine is not supported by this wall. This has been verified by
confirmation of the joist orientation spanning between the east and west walls of
the restroom and the absence of a header in the wall we are removing.
d. Indicate on the plans the required verification of the provision of a minimum of 187
CFM of outdoor air into space 101" - Sales — per International Mechanical Code
(IMC) Table 403.3.1.1. Any mechanical work required to meet the minimum
ventilation rate is to be completed under a separate permit.
Sheet A1.0 — Add Note 3: "PROVIDE A MINIMUM OF 187 CFM OF OUTDOOR AIR
INTO SALES 101 AS REQUIRED PER IMC TABLE 403.3.1.1."
6. Detail 4 — Restroom 103 — Change on the plans the keynote callout for the lavatory from
"7.2" to 7.5".
Sheet A1.0 — Detail 4 updated to show keynote 7.5.
On sheet A2.0 — Reflected Ceiling Plan:
7. Detail 2 — Wall Bracing Detail — Clarify on the plans the difference in the specified
construction and that anticipated to correspond with the mechanical mezzanine
indicated on the approved plan under permit BLD1988-0146.
Wall bracing detail updated to show wall being braced to structure of mechanical
mezzanine above.
On the provided Washington State Energy Code (WSEC) Compliance Forms for Commercial
Buildings:
8. Provide as part of a complete submittal the "interior Display Lighting — Space-By-Space-
LTG-INT-SPACE" checklist for the proposed "Lobby Art/Exhibit Display Lighting"
installation. It could not be found among the other provided WSEC checklists. The
proposed fixtures must be represented on the plans to guide proper review, installation,
and inspection.
Updated WSEC Lighting Compliance checklist — attached.
Sheet A2.0 — Updated LTG-INT-SPACE worksheet to show revised square
footages and Retail Display Allowance from LTG-INT-DISPLAY.
- SHEET A1.0 — Updated keynote 1.0 to read, "24"Wx24"H BUILT-IN
CONTINUOUS COUNTER. UNDER COUNTER DISPLAY LIGHTING TO BE
46 LINEAR LED FIXTURES AT 7 WATTS EACH. DISPLAY FIXTURES TO
BE MANUALLY CONTROLLED."
Sincerely,
BOTESCH, NASH & HALL ARCHITECTS, P.S.
Miles Walker
Associated