Subsurface Exploration, Geologic Hazard, and
Geotechnical Engineering Report
EDMONDS APARTMENTS
Edmonds, Washington
Prepared For:
CORNERSTONE ARCHITECTURAL GROUP
Project No. KE140265A
FebrUary 11, 2016
F4011
February 11, 2016
Project No. KE140265A
Mr. Roy Gursh
c/o Cornerstone Architectural Group
6161 Northeast 1751h Street, Suite 101
Kenmore, Washington 98028
Attention: Mr. Steve Barnes
a s s o c i a t e d
ea rt h sc i e n ces
I !I .� C. � 1) '� , 11 t t� Cl
Subject: Subsurface Exploration, Geologic Hazard, and
Geotechnical Engineering Report
Edmonds Apartments
Edmonds, Washington
Dear Mr. Barnes:
We are pleased to present the enclosed copies of the above -referenced report. This report
summarizes the results of our subsurface exploration, geologic hazard, and geotechnical
engineering studies and offers recommendations for the preliminary design and development
of the proposed project. Our recommendations are preliminary in that construction details
have not been finalized at the time of this report.
We have enjoyed working with you on this study and are confident that the recommendations
presented in this report will aid in the successful completion of your project. if you should
have any questions, or if we can be of additional help to you, please do not hesitate to call.
Sincerely,
ASSOCIATED EARTH SCIENCES, INC.
Kirkland, Washington
Kurt D. Merriman, P.E.
Senior Principal Engineer
KDM/pc
KE140265A2
Projects\20140265\KE\WP
Kirkland Office 1 911 Fifth Avenue I Kirkland, WA 98033 P 1425.827.7701 F 1425.827.5424
Everett Office 12911 Y2 Hewitt Avenue, Suite 2 1 Everett, WA 98201 P 1425.259.0522 F 1425. 827.5424
Tacoma Office 1 1552 Commerce Street, Suite 102 1 Tacoma, WA 98402 P 1253.722.2992 F 1253.722.2993
www.aesgeo.com
SUBSURFACE EXPLORATION, GEOLOGIC HAZARD, AND
GEOTECHNICAL ENGINEERING REPORT
EDMONDS APARTMENTS
Edmonds, Washington
Preparedfor:
Mr. Roy Gursli
c/o Cornerstone Architectural Group
6161 Northeast 175 1h Street, Suite 101
Kenmore, Washington 98028
Prepared by:
Associated Earth Sciences, Inc.
9115 1h Avenue
Kirkland, Washington 98033
425-827-7701
Fax: 425-827-5424
February 11, 2016
Project No. KE140265A
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Project and Site Conditions
1. PROJECT AND SITE CONDITIONS
1.0 INTRODUCTION
This report presents the results of Associated Earth Sciences, Inc.'s (AESI's) subsurface
exploration, geologic hazard, and geotechnical engineering study for the Edmonds Apartments
project, located 8509 244 1h Avenue Southwest, in Edmonds, Washington (Figure 1). The site
boundaries, the proposed building area, and the approximate locations of the explorations
accomplished for this study are presented on the "Site and Exploration Plan," Figure 2. Logs of
the subsurface explorations completed for this study are included in the Appendix.
1.1 Purpose and Scope
The purpose of this study was to provide preliminary geotechnical engineering
recommendations to be utilized in the design of the project. This study included a review of
selected available geologic literature, excavation of three exploration pits, and performing
geologic studies to assess the type, thickness, distribution, and physical properties of the
subsurface sediments and depth of shallow ground water. Geotechnical engineering studies
were completed to establish recommendations for the type of suitable foundations and floors,
allowable foundation soil bearing pressure, anticipated foundation and floor settlement, and
drainage considerations. Subsurface data was also used to formulate our conclusions
regarding the feasibility of infiltrating storm water generated on -site. This report summarizes
our fieldwork, and offers preliminary recommendations based on our present understanding of
the project. We recommend that we be allowed to review the recommendations presented in
this report, and revise them, if needed, when project plans have been developed.
1.2 Authorization
Written authorization to proceed with this study was granted by Mr. Reider (Roy) Gursli by
means of our signed scope of work and cost proposal. Our study was accomplished in general
accordance with our proposal dated May 2, 2014. This report has been prepared for the
exclusive use of Mr. Reider Gursli, the Cornerstone Architectural Group, and their agents, for
specific application to this project. Within the limitations of scope, schedule, and budget, our
services have been performed in accordance with generally accepted geotechnical engineering
and engineering geology practices in effect in this area at the time our report was prepared.
No other warranty, express or implied, is made.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 1
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Project and Site Conditions
2.0 PROJECT AND SITE DESCRIPTION
The project site consists of the parcel (Snohomish County Parcel No. 00463303200303) located
at 8509 244 1h Avenue Southwest, with an approximate total area of approximate ly 2 /3 acre in
Edmonds, Washington. We understand that the proposed project will include demolition of
two existing residential four-plex structures and the construction of new multifamily residential
structures, along with associated access, parking, and utilities. We understand that infiltration
is currently under consideration for the handling of storm water from the resulting impervious
surfaces.
For the purpose of preparing this report, we have assumed that the new structures will be
constructed close to existing grades without the need for deep earthwork cuts or thick
structural fills. We have assumed that light to moderate foundation loads typical of wood -
framed, residential construction will be required. Should actual project design differ
significantly from our assumptions, AESI should be allowed to review the report, and revise the
recommendations, as appropriate.
The site is bounded by existing multifamily residential structures to the north, south, and west.
A restaurant and associated parking lots border the site to the east. Site access is from the
south via a private drive connected to 244 th Street SW. The site currently contains two
residential four-plex structures, an asphalt drive, and gravel parking pads. The property is
vegetated with low grass with sparse, mature trees located along property boundaries. Site
topography is gently sloping towards the east, with overall vertical relief visually estimated at
about 20 feet. A moderately steep slope is present in the western half of the site, adjacent to
the existing four-plex structure and gravel drive, and accommodates a grade change visually
estimated at about 4 to 8 feet. A topographic survey of the site was not available at the time
our subsurface exploration program was completed.
3.0 SUBSURFACE EXPLORATION
Our subsurface exploration completed for this project included excavation of three exploration
pits using an excavator subcontracted through AESI on September 28, 2015. The conclusions,
and recommendations presented in this report are based on the explorations completed for
this study. The locations and depths of the explorations were completed within site and
budget constraints. In particular, the presence of underground utilities limited the locations
where we could advance subsurface explorations.
The exploration pits permitted direct visual observation of subsurface conditions. Materials
encountered in the exploration pits were studied and classified in the field by a geotechnical
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 2
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Project and Site Conditions
engineer from our firm. Selected samples were then transported to our laboratory for further
visual classification, and testing, as necessary.
4.0 SUBSURFACE CONDITIONS
Subsurface conditions at the project site were inferred from the field explorations
accomplished for this study, visual reconnaissance of the site, and review of selected applicable
geologic literature. As shown on the exploration logs, the exploration pits generally
encountered topsoil and/or fill over unsorted, dense to very dense silty sand with variable
amounts of gravel which we interpreted to be Vashon lodgement till. The following section
presents more detailed subsurface information organized from the youngest to the oldest
sediment types.
Because of the nature of exploratory work below ground, extrapolation of subsurface
conditions between field explorations is necessary. It should be noted that differing subsurface
conditions may sometimes be present due to the random nature of deposition and the
alteration of topography by past grading and/or filling. The nature and extent of any variations
between the field explorations may not become fully evident until construction begins.
4.1 Stratigraphy
Fill
Although no fill soils were encountered in our explorations, it is likely that some areas of fill
underlie portions of the site. Areas likely to contain fill include utility trenches and the area
immediately surrounding the existing buildings.
Topsoil
A surficial, organic sod/topsoil layer was encountered at the locations of exploration pits EP-1
and EP-2. The sod/topsoil layer was approximately 6 inches thick. Because of its relatively
loose condition and high organic content, the topsoil layer is not considered suitable for
foundation support or for use in a structural fill.
Gravel Driveway Pad
Moderately compacted, crushed gravel was encountered in exploration pit EP-3 to a depth of
about 1 foot below ground surface (bgs). This sequence is likely present around the site at
other gravel driveway locations, and at the gravel parking pad south of the existing eastern
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMGlpc — KE140265A2 —Projects �20140265 � KE�WP Page 3
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Project and Site Conditions
building. We recommend removal of the gravel pads and underlying loose soils, if present, in
order to expose medium to very dense native sediments in load bearing areas.
Voshon Lodgement Till
Sediments encountered in all exploration pits generally consisted of unsorted, cemented,
medium dense to very dense silty sand with variable quantities of gravel. These sediments
were generally medium dense and tan within a couple feet of the surface, and became denser
and greyer in color with depth. We interpret these sediments to be representative of Vashon
lodgement till. Vashon lodgement till consists of sediments that were deposited directly from
basal, debris -laden glacial ice during the Vashon Stade of the Fraser Glaciation, approximately
12,500 to 15,000 years ago. The high relative density characteristic of the Vashon lodgement
till is due to its consolidation by the massive weight of the glacial ice from which it was
deposited. The reduced density and lighter color observed within approximately 3 to 4 feet of
the ground surface is interpreted to be due to weathering. At all exploration locations, the
lodgement till extended beyond the maximum depths explored of approximately 5.5 to 8.5
feet. The lodgement till soils are suitable for foundation, floor, and pavement loads.
Permeability of lodgement till is relatively low, and storm water infiltration into the till is not
recommended.
Published Geologic Map
Our interpretations of subsurface conditions on -site are generally consistent with a published
geologic map of the area, as represented by the Geologic Map of the Edmonds East and part of
the Edmonds West quadrangles, Washington, by J.P. Minard (1983). The referenced map
indicates that the project area is expected to be underlain at shallow depth by Vashon
lodgement till. Our interpretation of lodgement till at the project site is in general agreement
with the published geologic mapping of the site and vicinity.
4.2 HVdrologV
Ground water seepage was not encountered in any of the exploration pits excavated for our
study at the time of exploration, September 28, 2015. It should be noted that the occurrence
and level of ground water seepage at the site may vary in response to such factors as changes
in season, precipitation, and site use.
4.3 Infiltration Feasibility
Vashon lodgement till underlies the site to the maximum depth explored of about 8.5 feet bgs.
Permeability of lodgement till is relatively low, and storm water infiltration into the till is not
recommended.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 4
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Geologic Hazards and Mitigations
11. GEOLOGIC HAZARDS AND MITIGATIONS
The following discussion of potential geologic hazards is based on the geologic, slope, and
shallow ground water conditions as observed and discussed herein.
5.0 SEISMIC HAZARDS AND MITIGATIONS
Earthquakes occur in the Puget Lowland with great regularity. The vast majority of these
events are small and are usually not felt by people. However, large earthquakes do occur, as
evidenced by the 1949, 7.2-magnitude event; the 2001, 6.8-magnitude event; and the 1965,
6.5-magnitude event. The 1949 earthquake appears to have been the largest in this region
during recorded history and was centered in the Olympia area. Evaluation of earthquake
return rates indicates that an earthquake of the magnitude between 5.5 and 6.0 is likely within
a given 20-year period.
Generally, there are four types of potential geologic hazards associated with large seismic
events: 1) surficial ground rupture, 2) seismically induced landslides, 3) liquefaction, and
4) ground motion. The potential for each of these hazards to adversely impact the proposed
project is discussed below.
5.1 Surficial Ground RuDture
The nearest known fault trace to the project site is the South Whidbey Island Fault Zone
(SWIFZ), located approximately 4 to 5 miles northeast of the site. A 2005 study by the U.S.
Geological Survey (USGS) (Sherrod et al., 2005, Holocene Fault Scarps and Shallow Magnetic
Anomalies Along the Southern Whidbey Island Fault Zone near Woodinville, Washington, Open -
File Report 2005-1136, March 2005) reported that "strong" evidence of prehistoric earthquake
activity has been observed along two fault strands thought to be part of the southeastward
extension of the SWIFZ. The study suggests as many as nine earthquake events along the
SWIFZ may have occurred within the last 16,400 years. The recognition of this fault splay is
relatively new, and data pertaining to it are limited with the studies still ongoing. The
recurrence interval of movement along this fault system is still unknown, although it is
hypothesized to be in excess of one thousand years. Due to the suspected long recurrence
interval for this fault zone, the potential for surficial ground rupture is considered to be low
during the expected life of the proposed structure.
5.2 Seismicallv Induced Landslides
It is our opinion that the potential risk of damage to the proposed development by seismically
induced slope failures is low due to the slope across the site being very gentle and the
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 5
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Geologic Hazards and Mitigations
likelihood of the existing moderate on -site slope being re -graded during construction. We did
not complete a quantitative slope stability analysis as part of this study, and none is warranted
at this time, in our opinion.
5.3 Liquefaction
It is our opinion that the risk of damage to the proposed structure by liquefaction is low due to
the high relative density of the underlying sediments, and the lack of adverse ground water
conditions. No mitigation of liquefaction hazards is recommended for the project.
5.4 Ground Motion
It is our opinion that earthquake damage to the proposed structures, when founded on
suitable bearing strata in accordance with the recommendations contained herein, will likely
be caused by the intensity and acceleration associated with the event. Structural design of the
buildings should follow 2012 International Building Code (113C) standards using Site Class "D" as
defined in Table 20.3-1 of American Society of Civil Engineers (ASCE) 7 — Minimum Design Loads
for Buildings and Other Structures.
6.0 EROSION HAZARDS AND MITIGATIONS
The lodgement till sediments contain a high percentage of silt and fine sand and are sensitive
to erosion, particularly in the more steeply sloping portions of the site. In order to control
erosion and reduce the amount of sediment transport off the site during construction, the
following recommendations should be followed.
1. Construction activity should be scheduled or phased as much as possible to reduce the
amount of earthwork activity that is performed during the winter months.
2. The winter performance of a site is dependent on a well -conceived plan for control of
site erosion and storm water runoff. The project temporary erosion and sediment
control (TESC) plan should include ground -cover measures, access roads, and staging
areas. The contractor must implement and maintain the required measures. A site
maintenance plan should be in place in the event storm water turbidity measurements
are greater than the Washington State Department of Ecology (Ecology) standards.
3. TESC measures for a given area to be graded or otherwise worked should be installed
soon after ground clearing. The recommended sequence of construction within a given
area after clearing would be to install sediment traps and/or ponds and establish
perimeter flow control prior to starting mass grading.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMGlpc — KE140265A2 —Projects �20140265 � KE�WP Page 6
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Geologic Hazards and Mitigations
4. During the wetter months of the year, or when large storm events are predicted during
the summer months, each work area should be stabilized so that if showers occur, the
work area can receive the rainfall without excessive erosion or sediment transport. The
required measures for an area to be "buttoned -up" will depend on the time of year and
the duration the area will be left un-worked. During the winter months, areas that are
to be left un-worked for more than 2 days should be mulched or covered with plastic.
During the summer months, stabilization will usually consist of seal -rolling the
subgrade. Such measures will aid in the contractor's ability to get back into a work area
after a storm event. The stabilization process also includes establishing temporary
storm water conveyance channels through work areas to route runoff to the approved
treatment facilities.
5. All disturbed areas should be revegetated as soon as possible. If it is outside of the
growing season, the disturbed areas should be covered with mulch, as recommended in
the erosion control plan. Straw mulch provides a cost-effective cover measure and can
be made wind -resistant with the application of a tackifier after it is placed.
6. Surface runoff and discharge should be controlled during and following development.
Uncontrolled discharge may promote erosion and sediment transport.
7. Soils that are to be reused around the site should be stored in such a manner as to
reduce erosion from the stockpile. Protective measures may include, but are not
limited to, covering with plastic sheeting, the use of low stockpiles in flat areas, or the
use of silt fences around pile perimeters.
8. On -site erosion control inspections and turbidity monitoring (when required) should be
performed in accordance with Ecology requirements. Weekly and monthly reporting to
Ecology should be performed on a regularly scheduled basis. Temporary and
permanent erosion control and drainage measures should be adjusted and maintained,
as necessary, for the duration of project construction.
It is our opinion that with the proper implementation of the TESC plans and by field -adjusting
appropriate mitigation elements (best management practices [BMPs]) throughout
construction, as recommended by the erosion control inspector, the potential adverse impacts
from erosion hazards on the project may be mitigated.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 7
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
111111. PRELIMINARY DESIGN RECOMMENDATIONS
7.0 INTRODUCTION
Our exploration indicates that, from a geotechnical standpoint, the parcel is suitable for the
proposed development provided the recommendations contained herein are properly
followed. The foundation bearing stratum is relatively shallow and conventional spread -
footing foundations may be utilized. Consequently, foundations bearing on either the medium
dense to very dense, natural glacial sediments or on structural fill placed over these sediments
are capable of providing suitable building support. Infiltration of on -site stormwater is not
recommended due to the presence of low -permeability lodgement till underlying the site.
8.0 SITE PREPARATION
8.1 Clearing and Stripping
Site preparation of the planned building areas should include removal of all trees, brush,
debris, and any other deleterious materials. These unsuitable materials should be properly
disposed of off -site. Additionally, all organic topsoil within the proposed building area, or areas
to receive structural fill should be removed and the remaining roots grubbed. Areas where
loose surficial soils exist due to grubbing operations should be considered as fill to the depth of
disturbance and treated as subsequently recommended for structural fill placement. Any
existing fill soils below footing areas should be stripped down to the underlying, medium dense
to dense natural sediments. These sediments were not encountered in our explorations, but
can vary locally, particularly in the vicinity of the existing residences and associated buried
utilities.
8.2 Temporary and Permanent Slopes
In our opinion, stable construction slopes should be the responsibility of the contractor and
should be determined during construction based on the local conditions encountered at that
time. For planning purposes, we anticipate that temporary, unsupported cut slopes within the
medium dense to very dense lodgement till sediments can be planned up to a 1H:1V
(Horizontal:Vertical) inclination. Permanent cut and structural fill slopes should not exceed an
inclination of 2H:IV. Permanent non-structural landscape fill should not exceed a 3H:1V
inclination. As is typical with earthwork operations, some sloughing and raveling may occur,
and cut slopes may have to be adjusted in the field. In addition, WISHA/OSHA regulations
should be followed at all times.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 8
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
8.3 Site Disturbance
The lodgement till sediments contain a high percentage of fine-grained material, which makes
them moisture -sensitive and subject to disturbance when wet. The contractor must use care
during site preparation and excavation operations so that the underlying soils are not softened.
If disturbance occurs, the softened soils should be removed and the area brought to grade with
structural fill. If crushed rock is considered for the access and staging areas, it should be
underlain by stabilization fabric (such as Mirafi 50OX or approved equivalent) to reduce the
potential of fine-grained materials pumping up through the rock and turning the area to mud.
The fabric will also aid in supporting construction equipment, thus reducing the amount of
crushed rock required. We recommend that at least 10 inches of rock be placed over the
fabric; however, due to the variable nature of the near -surface soils and differences in wheel
loads, this thickness may have to be adjusted by the contractor in the field. Crushed rock used
for access and staging areas should be of at least 2-inch size.
9.0 STRUCTURAL FILL
Placement of structural fill may be necessary to establish desired grades in some areas. All
references to structural fill in this report refer to subgrade preparation, fill type, and placement
and compaction of materials as discussed in this section. If a percentage of compaction is
specified under another section of this report, the value given in that section should be used.
9.1 Subgrade Compaction
After overexcavation/stripping has been performed to the satisfaction of the geotechnical
engineer/engineering geologist, the upper 12 inches of exposed ground should be
recompacted to a firm and unyielding condition. If the subgrade contains too much moisture,
suitable recompaction may be difficult or impossible to attain and should probably not be
attempted. In lieu of recompaction, the area to receive fill should be blanketed with washed
rock or quarry spalls to act as a capillary break between the new fill and the wet subgrade.
Where the exposed ground remains soft and further overexcavation is impractical, placement
of an engineering stabilization fabric may be necessary to prevent contamination of the free -
draining layer by silt migration from below.
After recompaction of the exposed ground is tested and approved, or a free -draining rock
course is laid, structural fill may be placed to attain desired grades.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 9
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
9.2 Structural Fill Compaction
Structural fill is defined as non -organic soil, acceptable to the geotechnical engineer, placed in
maximum 10-inch loose lifts, with each lift being compacted to at least 95 percent of the
modified Proctor maximum dry density using American Society for Testing and Materials
(ASTM):D 1557 as the standard. Utility trench backfill should be placed and compacted in
accordance with applicable municipal codes and standards. The top of the compacted fill
should extend horizontally a minimum distance of 3 feet beyond footings or pavement edges
before sloping down at an angle no steeper than 2H:1V. Fill slopes should either be overbuilt
and trimmed back to final grade or surface -compacted to the specified density.
9.3 Moisture -Sensitive Fill
Soils in which the amount of fine-grained material (smaller than No. 200 sieve) is greater than
approximately 5 percent (measured on the minus No. 4 sieve size) should be considered
moisture -sensitive. Use of moisture -sensitive soil in structural fills should be limited to
favorable dry weather conditions. The on -site sediments below the root zone are suitable for
use as structural fill; however, the lodgement till sediments contain significant amounts of silt
and are considered highly moisture -sensitive. If the moisture content of these sediments is
elevated at the time of construction, moisture -conditioning would be recommended prior to
their use as structural fill. Such moisture -conditioning could consist of spreading out and
aerating the soil out during periods of warm, dry weather.
Construction equipment traversing the site when the soils are very moist or wet can cause
considerable disturbance. If fill is placed during wet weather or if proper compaction cannot
be attained, a select import or on -site material consisting of a clean, free -draining gravel
and/or sand should be used. Free -draining fill consists of non -organic soil with the amount of
fine-grained material limited to 5 percent by weight when measured on the minus No. 4 sieve
fraction.
9.4 Structural Fill Testing
The contractor should note that any proposed fill soils must be evaluated by AESI prior to their
use in fills. This would require that we have a sample of the material at least 3 business days in
advance to perform a Proctor test and determine its field compaction standard.
A representative from our firm should inspect the stripped subgrade and be present during
placement of structural fill to observe the work and perform a representative number of in -
place density tests. In this way, the adequacy of the earthwork may be evaluated as filling
progresses and any problem areas may be corrected at that time. It is important to understand
that taking random compaction tests on a part-time basis will not assure uniformity or
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMGlpc — KE140265A2 —Projects �20140265 � KE�WP Page 10
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
acceptable performance of a fill. As such, we are available to aid the owner in developing a
suitable monitoring and testing frequency.
10.0 FOUNDATIONS
10.1 Allowable Soil Bearing Pressure
Spread footings may be used for building support when founded either directly on the medium
dense to very dense, natural lodgement till, or on structural fill placed over these materials.
Lodgement till sediments suitable for foundation support were encountered in our
explorations at depths of approximately 2 to 3.5 feet but may be locally deeper, particularly in
the vicinity of the existing structures and buried utilities. For footings founded either directly
upon the medium dense to very dense glacial sediments, or on structural fill as described
above, we recommend that an allowable bearing pressure of 3,000 pounds per square foot
(psf) be used for design purposes, including both dead and live loads. We recommend that the
footing subgrade be recompacted to a firm and unyielding condition prior to footing
placement. An increase in the allowable bearing pressure of one-third may be used for short-
term wind or seismic loading. If structural fill is placed below footing areas, the structural fill
should extend horizontally beyond the footing edges a distance equal to or greater than the
thickness of the fill.
10.2 Footing Depths
Perimeter footings for the proposed building should be buried a minimum of 18 inches into the
surrounding soil for frost protection. No minimum burial depth is required for interior
footings; however, all footings must penetrate to the prescribed stratum, and no footings
should be founded in or above loose, organic, or existing fill soils.
10.3 Footinas Adiacent to Cuts
The area bounded by lines extending downward at 1H:1V from any footing must not intersect
another footing or intersect a filled area that has not been compacted to at least 95 percent of
ASTM:D 1557. In addition, a 1.5H:lV line extending down from any footing must not daylight
because sloughing or raveling may eventually undermine the footing. Thus footings should not
be placed near the edges of steps or cuts in the bearing soils.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 11
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
10.4 Footing Settlement
Anticipated settlement of footings founded as described above should be on the order of 1
inch or less. However, disturbed soil not removed from footing excavations prior to footing
placement could result in increased settlements.
10.5 Footing Subgrade Bearing Verification
All footing areas should be observed by AESI prior to placing concrete to verify that the
exposed soils can support the design foundation bearing capacity and that construction
conforms with the recommendations in this report. Foundation bearing verification may also
be required by the governing municipality.
10.6 Foundation Drai
Perimeter footing drains should be provided as discussed under the "Drainage Considerations"
section of this report.
11.0 LATERAL WALL PRESSURES
All backfill behind walls or around foundations should be placed following our
recommendations for structural fill and as described in this section of the report. Horizontally
backfilled walls, which are free to yield laterally at least 0.1 percent of their height, may be
designed using an equivalent fluid equal to 35 pounds per cubic foot (pcf). Fully restrained,
horizontally backfilled, rigid walls that cannot yield should be designed for an equivalent fluid
of 50 pcf. Walls that retain sloping backfill at a maximum angle of 50 percent should be
designed for 60 pcf for yielding conditions and 75 pcf for restrained conditions. If parking areas
or driveways are adjacent to walls, a surcharge equivalent to 2 feet of soil should be added to
the wall height in determining lateral design forces.
11.1 Wall Backfill
The lateral pressures presented above are based on the conditions of a uniform backfill
consisting of either the on -site glacial sediments or imported sand and gravel compacted to
90 percent of ASTM:D 1557. A higher degree of compaction is not recommended, as this will
increase the pressure acting on the walls. A lower compaction may result in unacceptable
settlement behind the walls. Thus, the compaction level is critical and must be tested by our
firm during placement.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 12
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
11.2 Wall Drainage
It is imperative that proper drainage be provided so that hydrostatic pressures do not develop
against the walls. This would involve installation of a minimum 1-foot-wide blanket drain for
the full wall height using imported, washed gravel against the walls.
11.3 Passive Resistance and Friction Factor
Lateral loads can be resisted by friction between the foundation and the natural, medium
dense to dense glacial sediments or supporting structural fill soils, or by "passive" earth
pressure acting on the buried portions of the foundations. The foundations must be backfilled
with compacted structural fill to achieve the passive resistance provided below. We
recommend the following design parameters:
• Passive equivalent fluid = 250 pcf
• Coefficient of friction = 0.30
11.4 Seismic Surcharge
As required by the 2012 IBC, retaining wall design should include a seismic surcharge pressure
in addition to the equivalent fluid pressures presented above. Considering the site soils and
the recommended wall backfill materials, we recommend a seismic surcharge pressure of 5H
and 10H psf, where H is the wall height in feet for the "active" and "at -rest" loading conditions,
respectively. The seismic surcharge should be modeled as a rectangular distribution with the
resultant applied at the midpoint of the walls.
12.0 FLOOR SUPPORT
Slab -on -grade floors may be constructed either directly on the medium dense to very dense
natural sediments, or on structural fill placed over these materials. Areas of the slab subgrade
that are disturbed (loosened) during construction should be recompacted to an unyielding
condition prior to placing the pea gravel, as described below. We recommend that structural
fill be placed below slab -on -grade floors where necessary to raise floor subgrades above the
seasonal high water table.
If moisture intrusion through slab -on -grade floors is to be limited, the floors should be
constructed atop a capillary break consisting of a minimum thickness of 4 inches of washed pea
gravel or washed crushed rock. The pea gravel/crushed rock should be overlain by a 10-mil
(minimum thickness) plastic vapor retarder.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 13
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
13.0 DRAINAGE CONSIDERATIONS
Most of the natural glacial sediments encountered in our explorations contained significant
amounts of silt and are considered to be highly moisture -sensitive. Traffic from vehicles,
construction equipment, and even foot traffic across these sediments when they are very
moist or wet will result in disturbance of the otherwise firm stratum. Therefore, prior to site
work and construction, the contractor should be prepared to provide drainage and subgrade
protection, as necessary.
13.1 Wall/Foundation Drains
All retaining and perimeter footing walls should be provided with a drain at the footing
elevation. The drains should consist of rigid, perforated, polyvinyl chloride (PVC) pipe
surrounded by washed pea gravel. The level of the perforations in the pipe should be set
approximately 2 inches below the bottom of the footing, and the drains should be constructed
with sufficient gradient to allow gravity discharge away from the building. All retaining walls
should be lined with a minimum, 12-inch-thick, washed gravel blanket provided to within
I foot of finish grade, and which ties into the footing drain. Roof and surface runoff should not
discharge into the footing drain system, but should be handled by a separate, rigid, tightline
drain.
Exterior grades adjacent to walls should be sloped downward away from the structure to
achieve surface drainage. Final exterior grades should promote free and positive drainage
away from the building at all times. Water must not be allowed to pond or to collect adjacent
to the foundation or within the immediate building area. It is recommended that a gradient of
at least 3 percent for a minimum distance of 10 feet from the building perimeter be provided,
except in paved locations. In paved locations, a minimum gradient of 1 percent should be
provided unless provisions are included for collection and disposal of surface water adjacent to
the structure. Additionally, pavement subgrades should be crowned to provide drainage
toward catch basins and pavement edges.
14.0 DETENTION VAULT
We anticipate that the proposed project may utilize a vault for detention of storm water
generated on site. The vault may be constructed of cast -in -place concrete walls, likely with
prefabricated flat roof panels. For storm water vault foundation elements cast on very dense
lodgement till sediments, prepared as recommended above, we recommend designing for an
allowable foundation soil bearing pressure of 5,000 psf. This value may be increased by
one-third to accommodate transient wind and seismic loads. The vault may be designed to
resist lateral earth pressures represented by an equivalent fluid of 35 pcf if the walls are free to
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMGlpc — KE140265A2 —Projects �20140265 � KE�WP Page 14
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
yield during backfill placement, and 50 pcf if the walls are structurally restrained from
deflection during backfill. An allowable base friction coefficient of 0.32 may be assumed.
These lateral pressures assume that the walls will be provided with a blanket drain that
extends from the ground surface and connects to a footing drain at the foundation elevation.
If a footing drain is not installed, or if the footing drain is constructed higher than the base of
foundation due to available discharge locations, lateral earth pressures used for design should
be adjusted to reflect saturated conditions below the level of the footing drain. A saturated,
restrained lateral earth pressure of 90 pcf should be assumed for design. If roads or parking
areas are to be constructed above the vault, a lateral earth pressure surcharge equivalent to
2 additional feet of soil should be added.
15.0 PROJECT DESIGN AND CONSTRUCTION MONITORING
We are available to provide additional geotechnical consultation as the project design develops
and possibly changes from that upon which this report is based. If significant changes in
grading are made, we recommend that AESI perform a geotechnical review of the plans prior
to final design completion. In this way, our earthwork and foundation recommendations may
be properly interpreted and implemented in the design.
We are also available to provide geotechnical engineering and monitoring services during
construction. The integrity of the foundations depends on proper site preparation and
construction procedures. In addition, engineering decisions may have to be made in the field
in the event that variations in subsurface conditions become apparent. Construction
monitoring services are not part of this current scope of work. If these services are desired,
please let us know, and we will prepare a proposal.
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMG/Pc — KE140265A2 —Projects �20140265 � KE�WP Page 15
Subsurface Exploration, Geologic Hazard, and
Edmonds Apartments Geotechnical Engineering Report
Edmonds, Washington Preliminary Design Recommendations
We have enjoyed working with you on this study and are confident that these
recommendations will aid in the successful completion of your project. If you should have any
questions, or require further assistance, please do not hesitate to call.
Sincerely,
ASSOCIATED EARTH SCIENCES, INC.
Kirkland, Washington
Danika M. Globokar, E.I.T., G.I.T.
Senior Staff Geotechnical Engineer
Attachments: Figure 1: Vicinity Map
Figure 2: Site and Exploration Plan
Appendix: Exploration Logs
23,E80
G /S'T
ks-;� I . C'�
'/ '7 -- '-�' -1
Kurt D. Merriman, P.E.
Senior Principal Engineer
February 11, 2016 ASSOCIATED EARTH SCIENCES, INC.
DMGlpc — KE140265A2 —Projects �20140265 �KE� WP Page 16
--J —X�; —11 A
I— , f
Afkl
n J,
s
IS
v? oc
Lake
UnincorporAed bwo
, �,04
no
MIX) U.-N �LKE
TERRA
ALI
t-7
.9 so
Z. I
ank
Lake
T
SITE inger
!14
h b
iUJSH
ft dl vi
7
V
L ,o
99
g; r
� . I - t z
T
;-7 . ......
4w (3
J16
%
475
Lr
Ri
is N
909
7
0 1000 2000
NOTE BLACK AND WHITE REPRODUCTION OF THIS COLOR ORIGINAL MAY
REFERENCE: USGS, SNOHOMISH CO REDUCE ITS EFFECTIVENESS AND LEAD TO INCORRECT INTERPRETATION. FEET
T FIGURE 1
c i a t I d VICINITY MAP
e a r t h s c i e In c e s EDMONDS APARTMENTS DATE 10/15
E
i n c o r p o r a t e d EDMONDS, WASHINGTON
0 PROJ. NO. KE140265A
a
2()
fkm
OIJTA,L TO
CS IN
PARKINC WT
U)
-am 0 20 40
NOTE: BLACK AND WHITE REPRODUCTION OF THIS COLOR ORIGINAL MAY
FEET
7: REFERENCE: BING 2010/ CORNERSTONE REDUCE ITS EFFECTIVENESS AND LEAD TO INCORRECT INTERPRETATION.
FIGURE 2
10 a s s o c i a t e d SITE AND EXPLORATION PLAN
E
I
Lu e a r t h s c i e n c e s EDMONDS APARTMENTS DATE 10/15
n c o r p o r a t e d EDMONDS, WASHINGTON PROJ. NO. KE140265A
APPENDIX
Exploration Logs
C�
C�
C
0
Well -graded gravel and
Terms Describing Relative Density and Consistency
ILL
M,�
6W
gravel with sand, little to
Density SPT")blows/foot
4)
a)
S
D'Z3 C
no fines
Coarse- Very Loose 0 to 4
E2 0)
M
0
LL
�GR
LO
�—_ �-_.
0 0oo. 0
00000
Poorly -graded gravel
Loose 4 to 10
Grained Soils Medium Dense 10 to 30 Test Symbols
8
"a Iq
Vil
000q
00000
OP
and gravel with sand,
Dense 30 to 50
C.
C)
6
00000
00000
little to no fines
Very Dense >50 G = Grain Size
C-4
Z
00000
M = Moisture Content
(2
)blows/foot
6
Consistency SPT A = Atterberg Limits
Z
r_
LO 0
0 a
��
,
Silty gravel and silty
Very Soft 0 to 2 C = Chemical
0
0
itil
0
GM
gravel with sand
Fine -Soft 2 to 4 DID = Dry Density
Grained Soils
0
3
Medium Stiff 4 to 8 K = Permeability
stiff 8 to 15
Clayey gravel and
Very Stiff 15 to 30
t4l
M
ac
clayey gravel with sand
Hard >30
el
C)
U)
Component Definitions
Descriptive Term Size Range and Sieve Number
.....
Well -graded sand and
0
15
xx
SW
sand with gravel, little
Boulders Larger than 12"
0
12
LL
to no fines
Cobbles 3" to 12"
E2
Poorly -graded sand
Gravel 311 to No. 4 (4.75 mm)
0
(J)
0
SP
and sand with gravel,
Coarse Gravel 311 to 3/411
Fine Gravel 3/4" to No. 4 (4.75 mm)
C0
little to no fines
Sand No. 4 (4.75 mm) to No. 200 (0.075 mm)
0
0 Z
Coarse Sand No. 4 (4.75 mm) to No. 10 (2.00 mm)
9
2 ra
CD
Silty sand and
Medium Sand No. 10 (2.00 mm) to No. 40 (0.425 mm)
12
sm
silty sand with
Fine Sand No. 40 (0.425 mm) to No. 200 (0.075 mm)
0
u_
gravel
Silt and Clay Smaller than No. 200 (0.075 mm)
LO
cm
00
Clayey sand and
(3 Estimated Percentage
Moisture Content
sc
clayey sand with gravel
Component Percentage by Weight
Dry - Absence of moisture,
U)
. . . . . _... ,
dusty, dry to the touch
.
I
Trace <5
Slightly Moist - Perceptible
sandy silt, gravelly silt,
moisture
W
>
MLISilt'
silt with sand or gravel
Some 5 to <12
Moist - Damp but no visible
0
Modifier 12 to <30
water
Clay of low to medium
C3
0
—
(silty, sandy, gravelly)
Very Moist - Water visible but
C�
0 .
plasticity; silty, sandy, or
not free draining
0
Z
_j
CL
gravelly clay, lean clay
Very modifier 30 to <50
Wet - Visible free water, usually
0
(D
E
(silty, sandy, gravelly)
from below water table
1
U)
-1
Organic clay or silt of low
Symbols
EL
T
OL
plasticity
Blows/6" or
0
Sampler portion of 6"
Cement grout
'y"
surface seal
silt, claye y silt, silt
2 Sampler Type
IR
M,IE[astic
with micaceous or
S�01-tOD
'I _So 15 Description
poon (A4)
:1
Bentonite
seal
C,
ID
diatomaceous fine sand or
S ampler 3.0" OD Split -Spoon Sampler
Filter pack wilth
-0
silt
(SPT) 3.25" OD Split -Spoon Ring Sampler (4)
Ig
blank casing
Clay of high plasticity,
U)
00
LO
CH
sandy or gravelly clay, fat
Bulk sample
pi
3.011 OD Thin -Wall Tube Sampler
section
Screened casing
E
49:3
clay with sand or gravel
(including Shelby tube)
Z
or Hydrotip
with filter pack
Cb
Grab Sample
End cap
C:
Organic clay or silt of
Portion not recovered
OH
medium to high
(1) Percentage by dry weight (4) Depth of ground water
plasticity
(2) (SPT) Standard Penetration Test
(ASTM D-1586) Y ATD = At time of drilling
3 a Static water level (date)
In General Accordance with
Peat, muck and other
0)
0
PT
highly organic soils
Standard Practice for Description Combined USCS symbols used for
U)
0
IN
and Identification of Soils (ASTM D-2488) fines between 5% and 12%
0 Classifications of soils in this report are based on visual field and/or laboratory observations, which include density/consistency, moisture condition, grain size, and
plasticity estimates and should not be construed to imply field or laboratory testing unless presented herein. Visual -manual and/or laboratory classification
methods of ASTM D-2487 and D-2488 were used as an identification guide for the Unified Soil Classification System.
a s s o c i a t e d
FIGURE Al
earth sciences EXPLORATION LOG KEY
i n c o r p o r a ', e d
0
M
LOG OF EXPLORATION PIT NO. EP-1
This log is part of the report prepared by Associated Earth Sciences, Inc. (AESI) for the named project and should be read
together with that report for complete interpretation. This summ%glies only to the location of this trench at the time of
Subsurface
excavation. conditions may change at this location wit t e passage of time. The data presented are a simplfication
of actual conditions encountered.
DESCRIPTION
Topsoil
Loose, moist, reddish brown, silty SAND; with scattered rootlets and organics; unsorted (SM).
1
Weathered Vashon Lodgement Till
2
Loose to medium dense, moist, brown, silty fine to medium SAND, some fine to coarse gravel;
unsorted (SM).
3
Vashon Lodgement Till
4
Dense, moist, brownish gray, very gravelly, silty SAND; unsorted; diamict texture (SM).
5
Very dense, moist, brownish gray, silty SAND, some gravel; cemented; unsorted; diamict texture (SM).
6
7
8
As above.
9
Bottom of exploration pit at depth 8.5 feet
No seepage. No caving.
10
11
12
13
14
15
16
17
18
19
Edmonds Apartments
0
Edmonds, WA
0
n
a s s o c i a t e d
Project No. KE140265A
Logged by: DMG
earth sciences
Approved by: CJK i n c o r p o r a t e d 9/28/15
0
LOG OF EXPLORATION PIT NO. EP-2
This log is part of the report prepared by Associated Earth Sciences, Inc. (AESI) for the named project and should be read
together with that report for complete interpretation. This summ%glies only to the location of this trench at the time of
excavation. Subsurface conditions may change at this location wit t e passage of time. The data presented are a simplfication
of actual conditions encountered.
DESCRIPTION
Topsoil
Loose, slightly moist, brown, silty SAND; abundant rootlets; unsorted (SM).
1
2 --\Washed
1 -inch gravel (old drain field/utility?) in half of pit.
Vashon Lodgement Till
3
Medium dense to dense, slightly moist, tan, gravelly, silty SAND; unsorted; diamict texture (SM).
4
Becoming more dense.
5
Very dense, moist, brownish gray, gravelly, silty SAND; cemented; unsorted; diamict texture (SM).
6
7
Bottom of exploration pit at depth 6 feet
No seepage. No caving. Refusal at 6 feet.
8
9
10
11
12
13
14
15
16
17
18
19
Edmonds Apartments
0
Edmonds, WA
0
n
a s s o c i a t e d
Project No. KE140265A
Logged by: IDIVIG
earth sciences
Approved by: CJK i n c o r p o r a t e d 9/28/15
0
LOG OF EXPLORATION PIT NO. EP-3
This log is part of the report prepared by Associated Earth Sciences, Inc. (AESI) for the named project and should be read
together with that report for complete interpretation. This summ%glies only to the location of this trench at the time of
Subsurface
excavation. conditions may change at this location wit t e passage of time. The data presented are a simplfication
of actual conditions encountered.
DESCRIPTION
Gravel Driveway Pad
Vashon Lodgement Till
Medium dense to dense, slightly moist, tan, very gravelly, silty SAND; unsorted; diamict texture (SM).
2
3
Becoming more dense.
4
Very dense, moist, brownish gray, silty to very silty, fine SAND, some gravel to gravelly; cemented;
unsorted; diamict texture (SM).
5
6
Bottom of exploration pit at depth 5.5 feet
No seepage. No caving.
7
8
9
10
11
12
13
14
15
16
17
18