Memorandum
Date: 5/31/17
To: Kernen Lien
From: Shawn Nguy - PACLAN D
Subject: Response to Completeness Comments
Planning Division Comments:
Landscaping:
a. Type I Landscaping Requirements- Type I landscaping between the subject property and the
residential zoned property to the west of the site. While the landscaping plan on sheet L-1
indicates some existing trees will be retained, the landscaping shown along the western
property boundary is not consistent with the Type I landscaping requirements as detailed in
ECDC 20.13 .030.A. Please revise the landscape plan so the landscaping along the western
property boundary is compliant with the Type I landscaping requirements.
Response: The landscape plan has been updated to show Type I landscaping along the west
side of the site. Refer to the updated Landscape Plan.
b. Potential Impact from Adjacent Development -A development on the adjacent property has
proposed to use this property for potential stormwater facilities (File Number PLN201 60053,
plans of which have been provided to you). I understand the property owners are in discussion
to potentially grant and utility easement for the Stormwater facility. The location of those
stormwater facilities would be in the northwest corner of the subject property. If an easement is
granted, this could alter the landscaping in this area. Please update the landscaping plans as
necessary if the property does grant an easement for stormwater facilities as noted on the plans
under file numberPLN20160053.
Response: Noted. Landscape plan has been updated to account for the potential easement
area. Refer to the updated Landscape Plan.
2. Signage: Signs are shown on the proposed building elevations and a separate sheet for a free standing
sings. Please note that this design review is not approving any particular signage. Signs will be approved
under separate building permits. It should be noted that signs are being shown on the west side of the
proposed structure. Signs on the west side of the building would not be consistent with ECDC
20.60.025.A.2 as that facade is not a qualifying frontage (does not contain a primary public entrance or
is frontage along a public street). If the goal is ultimately to have signage on that facade, pursuant to
ECDC 20.60.015.13 the request would be reviewed by Architectural Design Board.
Page 2 of 4
City of Edmonds
May 31, 2017
Response: Noted. The applicant intends on pursuing signage on the west side of the building as it
is a significant issue for the tenants. We request the proposed signage plan be reviewed by the
Architectural Design Board.
3. Height calculations: Please provide height calculations for the proposed building.
Response: A dimension has been added to all elevations showing the 40'height max being met
per IBC 2015 504. 1. See attached. The maximum height of the proposed building is 28ft.
4. Access improvements: Please note that if there is any regrading and other improvements along the
access road connecting the site to 244 1h Street SW, a geotechnical report consistent with the
requirements of ECDC 23.80 will be required.
Response: Improvements and grading are not proposed along the access road with our project.
Based on the proposed development plans for the adjacent property, water line and pavement
repair will need be completed to serve that development. The adjacent development will also
need to improve the driveway on 244th to ADA standards since it serves as access to their
property. The owners of the property are currently coordinating a development agreement to
address these issues.
Engineering Division Comments
1. The plans indicate a 6-foot walkway connection between the parking lot and the sidewalk along
Highway 99. Please confirm with the City of Shoreline (and provide a response in writing to the City)
that a walkway in this location is acceptable. The grass area along the property frontage may provide a
stormwater benefit that cannot be disturbed/regraded without appropriate design.
Response: We have submitted the proposed development plans to the City of Shoreline and have
received approval for the walkway. See attached email confirmation from Kendra Dedinsky with
the City of Shoreline.
2. The subject development falls within the Olympic View Water& Sewer District for water and sewer
utilities. Please provide written confirmation that the District finds the proposed development to be
feasible with regards to water & sewer availability.
Response: See attached availability letter from OVWSD.
Stormwater Comments
1. A preliminary stormwater report has been submitted to the City to confirm project feasibility. Please
respond to the following:
Background
This is classified as a Large Project because it involves 1 or more acres of land disturbing activity. Large
Project are subject to Small Site Minimum Requirements 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, and 11 .
Minimum Requirement #1 -Preparation of Stormwater Site Plan
Comments 1 and 2 shall be addressed as part of the project feasibility review:
1. Stormwater Report, WWHM page 2: Use Puget East rain gage, not Everett rain gage. This is
selected in the project information screen by selecting "Use WSDOT data"
Page 3 of 4
City of Edmonds
May 31, 2017
Response: See attached WWHM Stormwater results. The analysis has been updated
using the Puget East rain gage.
2. Sheet PC-2: Grading to the west of the proposed building will lower the existing grade by
about 1 -foot. It should be noted that there is high groundwater in this area.
Response: Geotechnical investigation of the site did not encounter groundwater at
16ft below existing grade. We also reviewed the Geotech report for the adjacent
development and their boring logs did not encounter groundwater at depths 8.5ft
below groundwater. We will further investigate this issue. Should shallow
groundwater he encountered, the project will install a groundwater intercept system
below the pavement to redirect the water to the proposed stormwater system or
other acceptable discharge locations.
Comments 3-10 are provided to assist in a more complete civil plan submittal at time of building
permit:
Response: Acknowledged. Construction documents will include the detailed information
requested.
Fire Department Comments
1. Sheet PC 1 - Call out the distance/dimensions and turning radius of all fire access roads. Fire access
roads shall comply with the Department of Fire Prevention Emergency Access Standard (attached in PT).
Response: Distance, dimensions, and turning radius have been added to the site plan. An
Autoturn route for the proposed fire access route is provided on the site plan. See updated Site
Plan.
2. Sheet PC2- Storm Water vault must be rated to support 75,000lbs point load for aerial fire apparatus
outriggers.
Response: Noted. The storm vault is designed to meet the required load. See attached Vault
plans.
3. Sheet PC3- Coordinate with the Engineering Division and Fire Prevention for the location of the vault
(DCVA) for the private fire hydrants and fire sprinkler line.
4. Sheet PC3 -Call out Fire Department Connection (FDC) location. Prefer within 10' of either private
hydrant, remote from the building. FDC shall comply with Department of Fire Prevention FDC
Standard.
5. General Note: Provide a Fire Control room for placement of the fire riser and fire alarm control panel
with exterior access
Response: The project is not proposing a sprinkler system. Additional hydrants will be added to
the site. Based on coordination with Fire Official Kevin Zweber, a sprinkler system is not
required per the IBC based on the following:
Page 4 of 4
City of Edmonds
May 31, 2017
The building is a Mixed -Use building. Building I is A-2 and building 2 is M. The two occupancy
types are separated by a 2hr fire wall per table 508.4. The A-2 Restaurant may not exceed 99 occ
load and is below the max allowable footage requirement of 5,000 sq. feet per IBC 903.2.1.2.
The 3 retail spaces as M occupancy is below the max allowable footage requirement of 12,000 sq
feet and meets all other requirements per IBC 2015 903.2.7. This has been noted on the attached
floor plan.