DATE: September 11, 2019
TO: Architects NW
FROM: Donovan Akau, Plans Examiner
RE: Plan Check: BLD2019-0909
Project Address: 21222 Pioneer Way
Scope: New SFR, ADU, R-3, VB Construction.
Please be advised that the building plans for the above referenced project have been disapproved for the purposes of
obtaining a building permit. During a review of the plans by the Building Division for compliance with the applicable
building codes, it was found that the following information, clarifications, or changes are needed. Reviews by other
divisions, such as Planning, Engineering, or Fire, may result in additional comments that require attention beyond the
scope of this letter. Items that recur on this list appear in italics.
A complete review cannot be performed until the revised plans/documents, including a written response in
itemized letter format indicating where the ‘clouded’ or otherwise highlighted changes can be found on the
revised plans, have been submitted to a Permit Coordinator.
Resubmittals must be made at the Development Services Department on the 2nd Floor of City Hall. Permit Center hours
are M, T, Th, & F from 8am-4:30pm and from 8:30am-12pm on Wednesdays.
General:
1. The primary residence and the proposed ADU must act as independent dwellings. Please indicate on the
plans where the electrical panel, water shut off, and heating appliances will be located for each dwelling.
These locations must be readily accessible to the dwelling they service without having to access through
the adjacent dwelling. Please indicate on the plans where the water shut off(s) and electrical panel(s) will
be located for the primary residence and ADU.
2. The notes on the proposed plans appear to indicate that an electric dryer is to be installed for the ADU.
The permit application indicates a gas line is to be installed for both dryers. Combustion air will be
required to be provided to a fuel burring appliance. Please clarify and indicate on the plans.
3. The proposed ADU will require a whole house mechanical “whole house” ventilation in accordance with
M1507.3.1 of the 2015 International Residential Code. Please indicate how the requirement will be
achieved on the plans.
4. Please correct the calculations for the deck and make and corrections to calculations used for the deck of
this project. See amended table R301.5, 2015 IRC, or omit from plans if there is no deck for this project.
5. Please have Engineer of record stamp/sign the plan sheets that has calculations done by Engineer for this
project.
6. Have Architect/Engineer review the spans and scale for this project. It appears that the spans and scale is
not in correspondence with calculations provided by Engineer of record.
7. Plans indicate a hot water tank located in the garage. Application indicates a tankless hot water tank. Make
corrections/clarify.
8. Please indicate and provide location of hose bibs for this project on the plans and the permit application.
City of Edmonds
PLAN REVIEW COMMENTS
BUILDING DIVISION
(425) 771-0220
Page 2 of 2
9. Please clarify floor drain /sink (5) on permit application.
10. Indicate the location of the Heat Pump Unit on the plans.
I have reviewed the most recent WSFU tables sent via email on 5/21/19. The provided information is in
compliance with Appendix C of the 2015 UPC. A ¾” water meter with a minimum of a 1” water line will be sufficient.
Please add the provided tables to the plans.
Upon review of the resubmitted documents, additional comments may be generated .
Sincerely,
Donovan Akau