Loading...
3694_001.pdf&ASSOCIATES, INC. GEOTECHNICAL ENGINEERING e ENVIRONMENTAL ENGINEERING CONSTRUCTION TESTING & INSPECTION August 27, 2018 Mr. Nick Chou (E-Mail) EDMONDS SCHOOL DISTRICT NO. 15 20420 680 Avenue W. Lynnwood, WA 98036 RE: CONSTRUCTION TESTING AND INSPECTION ESD Sherwood Elementary Portable Classrooms 22901 10611 Avenue W Edmonds, Washington KA No. 096-183 5 2 Permit: BLD2018-0470/0471 Dear Mr. Chou, In accordance with your request and authorization, our firm performed construction testing and inspection for the above -referenced project. The sampling and testing was performed by our inspectors and reports are included. If you have any questions, or if we can be of further assistance, please do not hesitate to contact our office. KAAZAN�"SSOCIATES, INC. Ryman er cr Projec 'an _cr �40rt Paci c orl i�weA Division RLIvV]kj C C.- KPFF (E-MAIL) 4303 1981h Street SW, Lynnwood, Washington 98036 9 (425) 485-5519 * FAX (425) 485-6837 With Offices Serving the Western United States 09618352 DFR.doc & Associates FIELD REPORT 0337 GEoTGcHNicAL ENCRNEERING ENVIRONMENTAL ENGNEERING CONSTRUCTION TESTING AND INSPECTION DATE:-- S CONTRACTOR:— ex-C4�"'� PROJECT* e7V 4 Z 9 9 K Z JURISDICTION: PROJMT: -. &4 0/,-W=z PERMIT #: -. - ge- - �OCATION: 2--e-4. Cd-l- 1-0 --4e�!j INSPECTOR, 7—_ Z�V-A,,\ KRAZAN PROJECT MANAGER: a:k� WEATHER: -0:4ewe TEMP- V 1000' 40 if r -Ij V, All 0, W. &' WO Equipment/Asset Number(s): 4 To the best of my knowledge, the abovc*� I WAS NOT performed in accordance with the approved plans, spft�ions, and regu 1.7 requirements. Superintendent/Representative: Teclinici n: to '7 or This report Indicates our Inspector's observation and testing results based on the site condItion and contractor's activities. This Inlorm ei Is 'E' ISW prior to 11n4 6ubm,usl. By signing this report, our '7 1 "' = decirl. Inspector does not accept responsibility for validity of the results, Some Information on this report may have been provided by others on silef 7hu Information provided on this report Is prepared for the exclusive ugeol the client. This report may not be reproduced in any format vvithout the written permission of the eflont and Krazan & Assoc. thp Wp-atpm 11hitPd.4QtatPs I ��Nm M �_�w Re= an &ASSOCIATES, INC. GEOTECHNICAL ENGINEERING 9 ENVIRONMENTAL ENGINEERING CONSTRUCTION TESTING & INSPECTION August 14, 2018 Mr. Nick Chou (E-Mail) EDMONDS SCHOOL DISTRICT NO. 15 20420 681 Avenue W. Lynnwood, WA 98036 RE: CONSTRUCTION TESTING AND INSPECTION ESD Sherwood Elementary Portable Classrooms 22901 1061 Avenue W Edmonds, Washington Dear Mr. Chou, KA No. 096-18352 Permit: BLD2018-0470/0471 In accordance with your request and authorization, our firm performed construction testing and inspection for the above -referenced project. The sampling and testing was performed by our inspectors and reports are included. If you have any questions, or if we can be of further assistance, please do not hesitate to contact our office. Respectfully submitted, KRAZAN & ASSOCIATES, INC. Ayman aLMercVer" Project Manager Pacific Northwest Division RLM/1ki cc: KPFF (E-MAIL) 4303 19811 Street SW, Lynnwood, Washington 98036 * (425) 485-5519 @ FAX (425) 485-6837 With Offices Serving the Western United States 09618352 DFR.doc Krazan& Associates, Inc. GEOTECHNicAL ENGINEERING I ENVIRONMENTAL ENGINEERING CONSTRUCTION TESTING AND INSPECTION DATE:M71 �� 10 1 P� . — - PROJECT* PROJECT P� LOCATION..! 12— q-" KRAZAN PROJECT MANAGER: I Z__ FIELD REPORT 0462 'P:V - L '�- CONTRACTOR—C I —1C 04,0151 JURISDICTION: PERMIT#: INSPECTOR: WEATHER: T E M P: e T L") L, ^j C� L - 2; b /_)1i 1-15 C a C 111, 7 =- I = - EquipmenVAsset Number(s): To the best of my knowledge, the abo<e LWAS / As NOT performed in accordance with the approved plans, specifications, and regulatory requirements, Superintendenti"RepDr htive: Technician: This report Indicates our inspectors observation and testing results based on the site condition and contractors activities. This Information Is subject to review prior to final submittal. By signing this report, our Ingpectof does not accept responsibility for validity or the results some information on this -report may have been provided by olhars on site. The information provided on this report is prepared for tha eWuelve use of the client. This report may not be reproduced in any format without the written permission of the client and Krazan & Assoc. _qprvine7 thp Wp-atom 11nitpd qtatp.q 4UKrazan& Associates, Inc. GEOTECHNICAL ENGINEERING - ENVIRONMENTAL ENGNEEFUNr. CONSTRUCTION TESTINr, AND INSPECTION DATE: Ligypz!�AA, b 1 -9 1146 PROJECT#: PROJECT_ .2- KRAZAN PROJECT MANAGER: FIELD REPORT 0449 CONTRACTOR-P�C V44 LAJ I. JURISDICTION: IJN PERMIT#: k —7 INSPECTOR: WEATHER: TEMP: . AA. . � — _--� \_� \ =7 %.4 7z anc fSCSL'7� =-nr-7 -1-1 C: iT '71 CC. `0�6�P!IIIIZ -sit 4�r-1 ".17 7_� __11C__> />r ny�LL_l TZ.V67-7 r%) LA C2 7-L-V-s 1 -1 T-M PK\ L T�� A -'�, S1-77--,'n EquipmentlAsset Number(s): To the best of my knowledge, the abovQWAS >/.AS NOT performed in accordance with the app7T plans, specifications, and regulatory requirements. Superintendent/Representative: Technician/ I - -%.- VA This report indicates our Inspector's observation and testing results based on the site condition and contractors activities. This information is subject to review prior to final submittal. By signing this report, our irIv. does not accept responsibility tar validity of the results. Some information on this -report may have been provided by others on site. The information provided on Ihis report Is prepared for theexclusNe use of the client. This report may not be reproduced in any format without [he written permission of the client and Krazan &Assoc. I'Minae _qPrv1na thp Wp-ctpm 11nitPd.qtatP,* U _;L�v dKrazan& ASSOCIATES, INC. GEOTECHNICAL ENGINEERING e ENVIRONMENTAL ENGINEERING CONSTRUCTION TESTING & INSPECTION August 3, 2018 Mr. Nick Chou (E-Mail) EDMONDS SCHOOL DISTRICT NO. 15 20420 681 Avenue W. Lynnwood, WA 98036 RE: CONSTRUCTION TESTING AND INSPECTION ESD Sherwood Elementary Portable Classrooms 22901 1061 Avenue W Edmonds, Washington Dear Mr. Chou, KA No. 096-18352 Permit: BLD2018-0470/0471 In accordance with your request and authorization, our firm performed construction testing and inspection for the above -referenced project. The sampling and testing was performed by our inspectors and reports are included. If you have any questions, or if we can be of further assistance, please do not hesitate to contact our office. Respectfully submitted, KRAZAN & ASSOCIATES, INC. Ryman L. Mercer Project Manager Pacific Northwest Division RLM/Ikj cc: KPFF (E-MAIL) 4303 198m Street SW, Lynnwood, Washington 98036 - (425) 485-5519 - FAX (425) 485-6837 With Offices Serving the Western United States 09618352 DFRdoe Page I of I QKmzan& Ass oci ate s, Inc. Geotechnical Engineering * Environmental Engineering Construction Testing and Inspection Field Report NO.: 09618352DFR812018WB DATE: 8/1/2018 Set Count: CONTRACTOR: PROJECT #: 09618352 PERMIT #: BLD 2018-0470/ 0471 PROJECT: ESD Sherwood Elern INSPECTOR: William Bui LOCATION: 22901 106' Ave W RMSDICTION: Edmonds KA P.M.: Rvman Mercer WEATHER: Cloudy TENT: 59 Krazan representative arrived on site for anchor inspection. Contractor drilled 20 holes (6" embed and 5/8" dia) (5 holes each comer) at classroom A Holes are clean by air- brush -air method. Contractor used wedge anchor (7"X 5/8") Simpson Strong tie Anchors are tie finn in place and look good. 01 Reviewed BY: I QUAJU--1 ASTM Test #: Asset To the best of my knowledge, the above WAS performed in accordance with the approved plans, specifications and regulatory requirements. Sunefintendent/Remsentative: I Technician: Offices Serving the Western United States Lynnwood (425) 485-5519 - Poulsbo (360) 598-2126 - Tacoma (253) 939-2500 The infmmfion provided on ibis report is prepared for the cKclusive we of the client This report may not be reproduced in Any fonnat withmt the writ(on pwniu im ofthc client and Vj=n & Associsam ThIsrcpart Indicates our irdpwars obsew,,atlon and testing results based on site conditions and oommeto, activitics. This information is subject to review prior to fiml submittal By signing this report, our inspector does not accept responsibility for validity ofrasults. The same information has been provided by others on sit&