4121_001.pdfRAM Engineering City of Edmonds Development Services Department 1215 th Avenue North Edmonds, WA 98020 RE: Select Homes SFR 19325 80'h Ave W, Plan Check BLD20180948 I't Review Comment Response RAM Job No. 18-014 Dear Staff: October 15, 2018 This letter outlines the revisions and corrections made per planning and engineering review comment letters dated August 1, 3, and 23, 2018. Below is a list of the comment response documents addressing the comments and requests: Planning Review: Mike Clugston, August 3, 2018: 1. Sheet SP-01: a. Label the datum point used for the height calculations or select a temporary bench mark on or near the site as a permanent point of reference such as a fire hydrant bolt, manhole rim, or water meter cover. Update the calculations if necessary on the site plan and elevations (Sheet Al). Response: Datum point added to sheet SP-01 as requested. Engineering Review: Jennifer Lambert, August 23, 2018: DENIQ (BI,D20180947) 1) Show how the runoff from exposed soils of the portion of asphalt driveway that is to be removed will remain on site. If it is intended to use the existing driveway as a construction entrance for the construction of the new SFR (BLD20180948), please note as such on the plans and revise plans for permit BLD20180948 to be consistent. Response: Exposed soils will be protected per TESC EIMPS, notes added to plan. House will have separate construction entrance. See Lot 1 plan TP-01. 2) Show the sewer cut and capped at the property line or a minimum of 20' from existing home foundation if the sewer is to be reused. Response: Sewer system for Lot 2/short plot constructions is located within 20ft, new stub will be provided with short plot construction. 3) Show the water service line cut at the property line with an AVB installed. Response: A VB note added. 4) Please note how the site will have access to water during demo of the single family. Added note for water service shall be maintained throughout project with AVB at property line. GENERAL 5) Please add the building permit number to the plans, BLD20180948. Response: BLD20180948 number added to plan set. RESUB OCT I b 2018 PYBUIUANG DEPARTMENT CITY OF EDMONDS Select Homes SFR 19325 80th Ave W Plan Check BLD20180948 1st Review Comment Response RAM Job No. 18-014 6) Submit Side Sewer P�n�iit Application form.' Response: Side sewer permit application will be mode by applicant. 7) A Stormwater Covenant is required to be recorded against the property based on the proposed stormwater facilities for the project. Please complete the covenant, including notarization and any required exhibits and submit to the city. Ensure the stormwater covenant meets Snohomish County Record Drawing requirements. The document must be complete, but will not be recorded prior to permit issuance. Prior to construction, final location of facilities are to be verified (by field inspection and asbuilt) and then the covenant will be recorded. Response: See attached signed Stormwater Covenant. 8) Show all private casement infori-nation within the plan sets. Note AFN's for existing easements. Response: AFN added to existing easements. 9) Please note that the driveway can be concrete up to the existing asphalt driveway if you choose since this is a private driveway. Response: Concrete adjusted, see plan. SHEET 1 OF 4 (SITE DEVELOPMENT PLAN) NOTES 1) Remove note #2, since it does not apply to this project. Response: Note #2 removed as requested. SIDE SEWER NOTES 1) Remove, since it does not apply to this project (this would have been addressed during the short plat). Response: Side Sewer Notes removed as requested. STORM DRAINAGE NOTES 1) Please remove the 2"d sentence unless this note becomes applicable as changes are made to the plans. Response: 2 nd sentence removed as requested Page 2 of 4 WATER 1) Clearly distinguish between what was/will be installed with the short plat and what is being installed with the single family residence. Response: Revised line weights and callouts to clearly distinguish between SFR and short plat construction. 2) Add a note to the plans indicating where the landscape irrigation backflow assembly will be located (if one is proposed). Response: No landscape meter proposed. SEWER 1) Per the finished floor elevations it appears that the sewer will not have a minimum of 2' of cover. Please revise the plans accordingly. Response: Sewer elevations adjusted, see plans. RAM Engineering 16531 131h Ave W, Suite A108 Lynnwood WA 98037 (425) 678-6960 RAM engineer! nginc.corn Select Homes SFR 19325 80th Ave W Plan Check BLD20180948 1st Review Comment Response RAMJob No. 18-014 2) The 12" cast iron lamphole cover is not required at this location, but is required at the property line (adjacent to 801h — which would be addressed during the short plat). Please revise the plans accordingly. SSCO removed as port of new sewer layout. STORM 1) On CB2, please callout which pipe will receive a riser. Response: Riser collout added to southeriv invert as requested. 2) Show an observation well on the infiltration system consistent with Standard Detail, SD — 636. Response: Observation well added to plans as requested. 3) The surface water runoff for the new driveway shall be collected and mitigated; however, based on the proposed slope of the driveway and the location of the trench drain, there is a significant portion of the driveway not being mitigated. Please revise the plans accordingly. Response: Trench drain relocated to collect additional driveway area. 4) The yard drain/CB shown in the new portion of the driveway (to be installed with short plat) will need to be a solid lid or relocated so that areas that are required to be mitigated discharge to the appropriate stormwater systems. Response: Solid lid callout added to plans. Page 3 of 4 5) Please add a note to the plans that the existing driveway is to remain. If it is determined that the existing driveway is to be replaced, a stormwater management system will be required. Response: Existing driveway area to remain note added as requested. Added legend to clarify hatching. 6) Show where the retaining wall drainage will discharge to if drainage is to be installed. Response: Drywell discharge pit added to plans. STORMWATER ENGINEER REVIEW See separate comment letter. Response: See responses below. SIIEET 2 OF 4 (GENERAL NOTES AND DETAILS) GENERAL NOTES 1) Note I — Change 2016 to 2018 Response: Date changed to 2018 as requested. DETAILS 1) Please replace the observation detail with the City's Standard Detail, SD — 636. Response: Detail SD-636 added to plans. 2) Please replace the asphalt driveway detail with the City's Standard Detail, TR-510. Response: Asphalt detail removed, no additional asphalt proposed with BLD plan. RAM Engineering 16531 131h Ave W, Suite A108 Lynnwood WA 98037 (425) 678-6960 RAM engineeri nginc. corn Select Homes SFR 19325 80th Ave W Plan Check BLD20180948 1st Review Comment Response RAM Job No. 18-014 SHEFF3 OF 4 (CLEARING, GRADING, & TESC PLAN) TESC 1) Please only show the construction entrance on this plan and not the asphalt/concrete driveway unless it is intended to be part of the construction entrance. Response: New osphalticoncrete areas removedfrom sheet 3 of 4. 2) Show protective fencing around the location of the infiltration system. Response: Protective fencing added around infiltration system area as requested. SHEET 4 OF 4 (GENERAL DETAILS) No Comments Stormwater Engineering Review: Zach Richardson.. PE, August 1, 2018: Review Comments: 1. It appears that a majority of the driveway (asphalt portion) is downslope of the proposed collection points and therefore is not mitigated; update plan as needed collect and mitigate runoff from the driveway surfaces. Response: Trench drain relocated to collect additional driveway area. 2. If any new plus replaced impervious surface is to drain to an existing yard drain or CB, provide elevation information for the existing driveway and structures enough to verify that drainage will flow to collection points as intended. It appears that curb removal is needed and not noted on these sheets; ensure curb removal is on plans for demolition permit if not on this plan. Response: Curb removal note added to plans as requested. 3. Identify where the concrete retaining wall footing drain will outlet, and/or provide details for construction of the wall and drainage system (or lack thereof if not proposed to have drainage). Response: Drywell discharge pit added to plans. 4. Provide a legend identifying the hatches used for various pavements. Response: Hatch legend added as requested. 5. Remove text in storm drain note referring to CPEP pipe. Response: CPEP pipe removedfrom storm drain note as requested. Page 4 of 4 If there are any questions regarding the items above, please contact me at your earliest convenience; I can be reached at (425)678-6960 or RobL@RAMengineeringinc.com. Thz Mil Principal RAM Engineering 165311311 Ave W, Suite A108 Lynnwood WA 98037 (425) 678-6960 RAMengineeringinc.corn