RE: Request to Waive Sidewalk Requirements — Short flat S-04-108 at 15810 75"' Place West
Dear Mr. and Ms. Thiry:
I have reviewed your letter dated February 11, 2005, requesting reconsideration of the sidewalk
requirement under the subject short plat.
Based on your meeting with staff February 9, 2005 and on further discussion with Lyle Chrisman and
Steve Bullock, it is my understanding the existing house encroaches onto your other lot, and in order to be
able to construct a house on the empty lot, the Planning Division required you to submit for a short plat so
modifications could be made to the existing property lines.
When the City designed and constructed the walkway along 75"' Place West (from 157"' Street SW to
North Meadowdale Road), that portion of the walkway along your property frontage was not constructed
because the steep roadway and side slope would have required a specially constructed walkway. The cost
to construct such a walkway was well beyond the budget for the project, and since there were other areas
between your property and Meadowdale Beach Road that required specially designed and constructed
walkways, the decision was made not to include the walkway along your frontage.
Since your application is really for a modified lot line adjustment, and the City did not construct a
walkway along your frontage due to the expense of constructing an elevated walkway, the requirement to
construct a walkway along your property frontage is hereby waived as being economically infeasible to
construct, per Chapter 18.90.030B of the Edmonds Community Development Code. Attached is a copy
of the revised Engineering Requirements for the subject short plat.
If you have any questions, please contact Lyle Chrisman at 425-771-0220 Ext. 1324.
Sincerel
AVKK,
BERT, P.E.
City Engineer
DKG/ALC/cmc
Enclosure
c: Duane Bowman, Development Services Director
Steve Bullock, Senior Planner
M:Advrw\sp\04-108 thiry ltndoc
0 Innnrnnrated Auau.gt 11. 1890
CITY OF EDMONDS
ENGINEERING REQUIREMENTS FOR PLATS AND SUBDIVISIONS
Name: Thiry File No.: S-04-108
Approved by: Vicinity:15810 75th PL W
Engineering Program Manager date
ReW&
lkeqd w/bldg.
Bond poste
Complete
prior to
Permit
recording
1 Rights -of -way for public streets:
X
2. Easements (City utilities, private access, other utilities):
Provide all easements as needed.
X
Lot 2 shall share the private access driveway with lot 1
X
3 Street improvements (ACP with curb and gutter):
None required
x
4. Street turnaround:
Provide on -site turn around to City Stds.
X
5 Sidewalks and/or walkways:.
None required
x
6 Street lights:
N/A
7 Planting strip:
N/A
8 Water system improvements (pipelines, lire hydrants, pump
stations, telemeterin , D.S.H.S., etc.):
Provide service to each lot.
X
Connect to public water system.
X
9 Sanitary sewer system improvements (pipelines,; pump
Stations, telemeterin , health district, etc:OVWSD
Provide new service to each lot
X
Connect to public sewer system
X
10. Storm sewer system improvements (pipelines, pump
Stations, DOE, fisheries, etc.):
Provide storm sewer service to all proposed lots.
X
Construct storm detention system sized to provide adequate
X
capacity for proposed single family dwellings and access
improvements in accordance with ECDC 18.30.
Connect to Public Storms stem
X
11. On -site drainage (plan per Ord. 3013):
Connect all new impervious surfaces to detentions stem.
X
12. Underground wiring (per, Ord.1387):
Required for all new services
X
13. Excavation and grading (per UBC, Chapter 70 :
Submit a grading plan as part of engineered site plan.
X
14. Si na a(per City Engineer):
All signs shall be vinyl letters and to City Stds. No silk screen
N/A
signs will be permitted
Provide "Private Access Ends"
N/A
Provide fire and aid address si na e
X
VAdvnv\sp\04-108 thiryplt.doc
N/A
for all utilitv construction.
X
a) Plat showing lots, easements, legals, survey information X X
b) Legal documents for each lot X
c) Field stake lot corners (by professional engineer) X
d) Clustered mailbox location per Postmaster
e Maintenance agreements
18. Engineering fees:
a) Storm drainage connection charge per lot ($428) X
b) Sewer connection charge/LID fees to be paid in full. X
c) Plat inspection fee: 2.2% of improvement costs $ X
d) Plan review fee: $860 $ 860. X
e Traffic mitigation: $200 per pm peak trip $_ I X
ENGINEERING PROGRAM MANAGER, CITY OF EDMONDS DATE
The Engineering requirements have been completed and the subdivision can be recorded.
Authorized for recording by: Date: