BLD18-0447 - Northpoint Recovery - Approval Ltr by DBeck (8-5-2018).docTransmittal
August 5, 2018
Leif Bjorback
Building Official
City of Edmonds
121 5th Avenue North
Edmonds, WA 98020-3145
Subject: BLD18-0447
Northpoint Recover
Enclosed:
(1) set of reviewed drawings (stamped REVIEWED, signed cover sheet)
(1) set of submitted documents
Beck Fee Structural & Non-Structural $18,177.00 x 0.42.5 = $7,725.22
Our review of the permit application materials & drawings is now complete. The following items should be noted as Conditions of Permit Approval:
King County Health Department and WA State Department of Health approvals are required for this project. It is the responsibility of the applicant to obtain these approvals.
Construction of suspended ceilings shall conform to Technical Document 401: Suspension Systems for Acoustic Lay-In Ceilings as produced by the Northwest Wall & Ceiling Bureau.
Redlines can be found on sheets G1.00, A2.00, A2.10, A2.20, and S-731.
The following items are required to be submitted as Deferred Submittals to this permit:
Glazing systems at canopies
Anchorage of roof-supported mechanical equipment to the mechanical curb.
The Engineer of Record (EOR) shall be responsible for reviewing design drawings and calculations for compliance with the design criteria and compatibility with the design of the primary
structure, including review of all connections to the primary structure. The EOR shall review the submittal prior to providing it to the City for review. The submitted documents shall
bear the shop drawing stamp of the EOR.
The Specialty Structural Engineer (SSE) shall provide drawings and calculations for the deferred design submittal to the EOR for review. Design shall conform to loading & deflection
criteria as required by the 2006 IBC. Drawings and calculations for deferred submittals shall be designed by a structural/civil engineer licensed in the state of Washington. Deferred
submittals shall be stamped/signed by the SSE and shall include all material requirements and manufacturer literature.
Special inspections are required on this project as specified within the structural drawings (S-004): concrete; reinforcing steel; steel fabrication & erection; post-installed anchors;
wood panel sheathed shear walls, roofs, and floors; cold-formed steel light-frame construction; all components of the lateral force resisting system including drag struts, bracing,
straps, and holdowns. Reference sheet S-004 for additional special inspections required by the EOR and detailing of the special inspection program.
Shannon & Wilson, Inc. is required to observe subgrade preparation and foundation construction (p. 14 of 16)
Please contact me at should you have any questions. Thank you.
Douglas Beck, PE, SE